IN-SITU IMPOUNDMENT CLOSURE AND GROUNDWATER CORRECTIVE ACTION TECHNOLOGY
World of Coal Ash 2019
- St. Louis, Missouri
Tim Silar, P.G.
Principal Geoscientist
John Magee, P.E.
Principal Engineer
IN-SITU IMPOUNDMENT Tim Silar, P.G. Principal Geoscientist - - PowerPoint PPT Presentation
IN-SITU IMPOUNDMENT Tim Silar, P.G. Principal Geoscientist CLOSURE AND John Magee, P.E. GROUNDWATER Principal Engineer CORRECTIVE ACTION World of Coal Ash 2019 TECHNOLOGY St. Louis, Missouri PRESENTATION OBJECTIVE To present a
World of Coal Ash 2019
Principal Geoscientist
Principal Engineer
FIRST UP CONSUL TANTS
To present a permanent, technically sound, minimally disruptive and cost effective impoundment closure and groundwater corrective action option including:
challenges/concerns
technology
reduction
2
head
practices
ISS: In‐place mechanical mixing of media with dry reagent or an injected engineered grout mixture
Result: Monolithic structure with increased strength/stability and decreased permeability Typical Reagents: Portland Cement, Slag, Bentonite Typical Performance Goals
Construction Techniques
Discrete Layer Construction Horizontal Hydraulic Barrier Full Depth Construction Vertical Barrier and Geotechnical Stability
=>Evaluate dewatering =>Complete Geotechnical Eval =>Perform GW Assessment to establish baseline conditions & interface => Evaluate Grading Plan
Major Activities ‐ Review records and develop CSM ‐ Conduct Constructability evaluation ‐ Perform ISS treatability study to determine performance criteria/construction parameters ‐ Conduct on‐site investigation
ASH IMPOUNMENT FILL CAN BE UNEVEN & UNSTABLE CONCERN: Grading & Stabilization may be required to construct liner. =>Regrade/stabilize ash to establish construction platform
ASH IMPOUNMENT SATURATED/ POSSIBLE STANDING WATER CONCERN: Impoundment may require dewatering over time and hydraulic head can exacerbate leaching =>Begin dewatering to facilitate construction and overall effectiveness
Begin ISS construction of linear system and perimeter columns. ISS full depth along perimeter berms to construct perimeter containment and provide stability.
Begin ISS construction of linear system and perimeter columns. ISS full depth along perimeter berms to construct perimeter containment and provide stability.
Both Full and Discrete ISS provides complete coverage
Complete ISS construction of liner system and final cover system
Import fill or ISS swell to establish subgrade for final cover. Low permeability layer (e.g. geomembrane, compacted clay, Closure Turf TM ) Final Cover protective layer (e.g. soil, Closure Turf TM )
Applications of ISS on CCP
limited
applications Discrete ISS: Successfully Pilot Tested at CERCLA Site Baseline Laboratory Treatability Testing on CCP
Cement, Slag, Bentonite)
compressive strength, monolithic leaching)
Full depth ISS mixing recently proven at CCP impoundment
Grout Amendments and Proportions 10% Portland Cement 0.5% Bentonite 7.5% GGBFS 2.5% Portland Cement Curing Days Prior to Testing 14 14 14 28 14 28 14 28 14 28 Moisture Content (%) (pretreatment) 31 31 37 37 37 37 37 37 23.5 23.5 Density (lbs/ft3) (pretreatment) 102 102 97.63 97.63 97.63 97.63 97.63 97.63 97.63 97.63 Unconfined Compressive Strengh (psi) 221 184 80 101 38 76 70 86
Hydraulic Conductivity (cm/sec) 4.1 x 10-7 1 x 10-6
GGBFS = Ground Granulated Blast Furnace Slag
8% Portland Cement 6% GGBFS 2% Portland Cement 8% Portland Cement 0.5% Bentonite 18% GGBFS 6% Portland Cement 2% Bentonite
Grout Amendments and Proportions 10% Portland Cement 0.5% Bentonite 7.5% GGBFS 2.5% Portland Cement Curing Days Prior to Testing 14 14 14 28 14 28 14 28 14 28 Moisture Content (%) (pretreatment) 31 31 37 37 37 37 37 37 23.5 23.5 Density (lbs/ft3) (pretreatment) 102 102 97.63 97.63 97.63 97.63 97.63 97.63 97.63 97.63 Unconfined Compressive Strengh (psi) 221 184 80 101 38 76 70 86
Hydraulic Conductivity (cm/sec) 4.1 x 10-7 1 x 10-6
GGBFS = Ground Granulated Blast Furnace Slag
8% Portland Cement 6% GGBFS 2% Portland Cement 8% Portland Cement 0.5% Bentonite 18% GGBFS 6% Portland Cement 2% Bentonite
Compare in situ closure to excavation & off-site disposal
Cost Evaluation: Assumptions
Volume Assumptions: Assume the impoundment volume is approximately 1.29 million cubic yards (40 acres by 20’ thick)
Excavation Assumptions:
million cubic yards
disposed within 20 miles
weighs 2,700 lbs
dewatering and water treatment
partially backfilled and vegetated In situ Closure Assumptions:
cubic yards including 5’ thick discrete bottom liner and 10’ wide fully penetrating perimeter walls to 25’ below grade
will be used in ISS batch plant
capped with swell , geotextile, and soil cover
Cost evaluated on recent experience and discussions with contractors
Excavation and Off-Site Disposal In situ Closure (ISS) Item Estimated Quantity Units Unit Price $ Amount $ Unit Price $ Amount $ General Conditions
$ 2,750,000 $ 2,750,000
Mobilization & Temporary Facilities Setup 1 Lump Sum
$ 700,000 $ 700,000 $ 700,000 $ 700,000
Site Preparation, Site Survey, Remove Ponded Water 1 Lump Sum
$ 1,500,000 $ 1,500,000 $ 1,500,000 $ 1,500,000
Clearing, Grubbing and Erosion Controls Installation, Maintenance & Monitoring 1 Lump Sum
$ 300,000 $ 300,000 $ 300,000 $ 300,000
Demobilization & Record Documents 1 Lump Sum
$ 250,000 $ 250,000 $ 250,000 $ 250,000
Excavation and Off-Site Disposal In situ Closure (ISS) Item Estimated Quantity Units Unit Price $ Amount $ Unit Price $ Amount $ Excavation / Disposal vs. ISS $ 69,373,351 $ 31,977,640 Excavate Ash, Dewater, and Load 1,290,667 Cubic Yards $ 20 $ 25,813,340 $ - $ - Transport and Dispose of Ash 1,742,400 Tons $ 25 $ 43,560,011 $ - $ - Mobilize ISS Treatment Equipment and Materials 1 Lump Sum $ - $ - $ 500,000 $ 500,000 In situ Solidification/Stabilization (ISS) 366,000 Cubic Yards $ - $ - $ 80 $ 29,280,000 ISS Swell Management (15%) 54,900 Cubic Yards $ - $ - $ 4 $ 197,640 Geotextile Cap 40 Acres $ - $ - $ 50,000 $ 2,000,000
Excavation and Off-Site Disposal In situ Closure (ISS) Item Estimated Quantity Units Unit Price $ Amount $ Unit Price $ Amount $ Dewatering - Excavation $ 2,624,000 $ 272,000 Frac Tank Mobilization, Setup and Demobilization 8 Each $ 3,000 $ 24,000 $ - $ - Site Water Management 104 Week $ 25,000 $ 2,600,000 $ - $ - Dewatering - ISS Frac Tank Mobilization, Setup and Demobilization 4 Each $ - $ - $ 3,000 $ 12,000 Site Water Management 52 Week $ - $ - $ 5,000 $ 260,000 Site Restoration $ 10,598,942 $ 918,942 Backfill with Off-site fill 645,334 Cubic Yards $ 15 $ 9,680,000 Topsoil 32,267 Cubic Yard $ 26 $ 838,942 $ 26 $ 838,942 Seed and Mulch 40 Acres $ 2,000 $ 80,000 $ 2,000 $ 80,000 TOTAL COST $ 85,343,293 $ 35,918,582 COST PER ACRE $ 2,133,582 $ 897,965
In-situ Closure Technology Satisfies Key Objectives & Reduces Risk
catastrophic failure and leaching of CCP constituents into groundwater
potential environmental impacts and risks associated with siting and permitting new landfills, ash excavation/handling, ash transportation, etc
will meet regulatory closure requirements
Stakeholders: Impoundment Owners, Regulators, Environmental Groups, General Public, Rate Payers
This method is applicable for:
require groundwater corrective action
require improved stability
where an active groundwater remedy is also needed
reducing groundwater impacts
impoundments and allows for future harvesting
emissions, etc.
available resources
Continue to share the technology with stakeholders Seek collaborative opportunities to demonstrate the remedy and advance the technology ‐ Continue Bench Testing on CCP ‐ Impoundment Implementation ‐ Site Pilot Testing
www.silarservices.com 2019 WOCA Paper “In‐Situ Impoundment Closure and Groundwater Corrective Action Technology” In Situ Waste Remediation and Systems US Patent No. 9,909,277 B2