Neighborhood Transportation Improvement Program (NTIP) Update Plans and Programs Committee Agenda Item 6 SA SAN N FRAN ANCI CISCO SCO COUN OUNTY Y TRAN ANSPO SPORT RTATIO TION N AUTH UTHORIT RITY Januar ary y 12, 2016 NTIP


  1. Neighborhood Transportation Improvement Program (NTIP) Update Plans and Programs Committee Agenda Item 6 SA SAN N FRAN ANCI CISCO SCO COUN OUNTY Y TRAN ANSPO SPORT RTATIO TION N AUTH UTHORIT RITY Januar ary y 12, 2016

  2. NTIP Overview Purpose  Response to SFTP mobility and equity analysis findings:  Walking, biking, and transit reliability initiatives are important ways to address socio-economic and geographic disparities  Public and Board input:  Focus on neighborhoods  Focus on Communities of Concern and other underserved neighborhoods  Project delivery analysis:  Strengthen project delivery pipelines SAN SA N FRAN ANCI CISCO SCO COUN OUNTY Y TRAN ANSPO SPORT RTATIO TION N AUTH UTHORIT RITY 2

  3. NTIP Overview Funding  Planning funds  $100,000 in Prop K funds for planning in each supervisorial district  Capital funds Transportation Authority and SFMTA  $600,000 in Prop K local match funds for NTIP coordinators work together to capital projects in each supervisorial district support Commissioners by:  Prop K should leverage other funds to ideally • Helping to identify potential NTIP deliver 2 neighborhood scale (small- to mid- projects sized) projects • Assisting with development of scope, schedule, and budget  Funds approved in 2014 Prop K Strategic information to support allocation Plan, includes funds for NTIP program of NTIP grants support • Ensuring regular communication with commissioners on NTIP SAN SA N FRAN ANCI CISCO SCO COUN OUNTY Y TRAN ANSPO SPORT RTATIO TION N AUTH UTHORIT RITY 3

  4. NTIP Allocations to Date (December 2015) Pro rop p K Funds ds Pro rop p K Funds ds Remaining ning Avail ilable able All lloca cated ed to Date Funds ds NTIP Planning $1,100,000 $600,000 $500,000 NTIP Capital $6,600,000 $560,000 $6,040,000 TOTAL $7,700,00 000 $1,1 ,160,000 00 $6,540,00 000  Planning allocations: Districts 1, 2, 3, 5, 7, 9  Capital allocations: Districts 2, 10 SAN SA N FRAN ANCI CISCO SCO COUN OUNTY Y TRAN ANSPO SPORT RTATIO TION N AUTH UTHORIT RITY 4

  5. NTIP Map of Funded Projects SA SAN N FRAN ANCI CISCO SCO COUN OUNTY Y TRAN ANSPO SPORT RTATIO TION N AUTH UTHORIT RITY 5

  6. NTIP Program Observations to Date  Planning  Allow for supervisor and community priorities to advance in the near-term  Include wide-ranging community involvement tailored to specific neighborhood and project context  Capital  Advance capital projects quicker than may have otherwise occurred  Expected to improve competitiveness for other funds SA SAN N FRAN ANCI CISCO SCO COUN OUNTY Y TRAN ANSPO SPORT RTATIO TION N AUTH UTHORIT RITY 6

  7. District 1 – Planning (SFMTA) Improving Connections from Golden Gate Park to the Presidio  $100,000 allocated  Develop conceptual designs for safer connections for people walking and biking along 8 th and 23 rd Avenues, and Arguello Boulevard  SFMTA has created initial project concepts for the Arguello corridor based on previous community outreach efforts SAN SA N FRAN ANCI CISCO SCO COUN OUNTY Y TRAN ANSPO SPORT RTATIO TION N AUTH UTHORIT RITY 7

  8. District 1 – Planning (SFMTA) Improving Connections from Golden Gate Park to the Presidio  Next round of public participation for Arguello on January 28, 4 - 5:30pm (meet at northeast corner of Arguello and Fulton for walkthrough)  SFMTA developing draft conceptual designs for 8 th and 23 rd Avenues, as well as community outreach approach for those corridors  Final report: June 2016 SA SAN N FRAN ANCI CISCO SCO COUN OUNTY Y TRAN ANSPO SPORT RTATIO TION N AUTH UTHORIT RITY 8

  9. District 2 – Planning (Transportation Authority) Managing Access to the Lombard "Crooked Street"  $100,000 allocated  Identify and evaluate options to manage circulation while maintaining street’s character, managing vehicle and pedestrian congestion, and avoiding spillover effect onto adjacent streets  Completed data collection and analysis to develop existing conditions report SA SAN N FRAN ANCI CISCO SCO COUN OUNTY Y TRAN ANSPO SPORT RTATIO TION N AUTH UTHORIT RITY 9

  10. District 2 – Planning (Transportation Authority) Managing Access to the "Crooked Street"  Initial outreach regarding existing condition findings and universe of potential solutions: January-February 2016  Develop draft recommendations: February - March 2016  Additional Outreach: April 2016  Final report and recommendations: May 2016 SA SAN N FRAN ANCI CISCO SCO COUN OUNTY Y TRAN ANSPO SPORT RTATIO TION N AUTH UTHORIT RITY 10 10

  11. District 2 – Capital (SFMTA) Lombard Street/US-101 Corridor Pedestrian Safety  $400,000 allocated  Fully funds design phase for pedestrian and transit improvements, ahead of Caltrans paving project in 2018  Scope includes 19 new bus and pedestrian bulbouts along Lombard  SFMTA completing conceptual engineering  Design includes feedback from earlier rounds of community outreach SA SAN N FRAN ANCI CISCO SCO COUN OUNTY Y TRAN ANSPO SPORT RTATIO TION N AUTH UTHORIT RITY 11 11

  12. District 2 – Capital (SFMTA) Lombard Street/US-101 Corridor Pedestrian Safety  High level of interagency coordination on design, environmental documentation, cost estimation, and construction  Prop K funds leveraging Regional Active Transportation Program grant, General Funds, General Obligation bonds for the construction phase  Anticipated completion (design phase): July 2016  Caltrans paving project anticipated completion: winter 2018/19 SAN SA N FRAN ANCI CISCO SCO COUN OUNTY Y TRAN ANSPO SPORT RTATIO TION N AUTH UTHORIT RITY 12 12

  13. District 3 – Planning (SFMTA) Kearny Street Multimodal Implementation Plan 1  $100,000 allocated  Develop conceptual designs to increase pedestrian safety, enhance transit performance, and develop bike facilities  Kearny and Montgomery (Market to Broadway); Washington and Clay (Stockton to Montgomery)  SFMTA reviewed existing conditions, developing first round of outreach (winter 2016)  Final report: Winter 2016/17 1 THIS PROJECT IS ON HOLD PENDING RECONSIDERATION BY COMMISSIONER PESKIN SA SAN N FRAN ANCI CISCO SCO COUN OUNTY Y TRAN ANSPO SPORT RTATIO TION N AUTH UTHORIT RITY 13 13

  14. District 5 – Planning (SFMTA) Western Addition Community-Based Transportation Plan  $100,000 allocated  Identify key transportation needs and develop project concepts to address those needs  Focus on pedestrian safety and security improvements throughout the project area  NTIP funds leverage additional Prop K and community-based planning grant from MTC SA SAN N FRAN ANCI CISCO SCO COUN OUNTY Y TRAN ANSPO SPORT RTATIO TION N AUTH UTHORIT RITY 14 14

  15. District 5 – Planning (SFMTA) Western Addition Community-Based Transportation Plan  SFMTA partnering with Mo’Magic on community outreach  Completed outreach events have helped to define planning project’s goals and priorities  SFMTA completed existing conditions analysis  Nearing completion second round of outreach, feedback from which will lead to draft conceptual designs  Final report: March 2017 SA SAN N FRAN ANCI CISCO SCO COUN OUNTY Y TRAN ANSPO SPORT RTATIO TION N AUTH UTHORIT RITY 15 15

  16. District 7 – Planning (Planning Department) Balboa Area Transportation Demand Management Study  $100,000 allocated  Develop recommendations for TDM measures to minimize impacts of development and activity in the area  Planning Department has initiated outreach; Consultant contract nearly final; starting data collection, surveys  Final report: July 2016 SA SAN N FRAN ANCI CISCO SCO COUN OUNTY Y TRAN ANSPO SPORT RTATIO TION N AUTH UTHORIT RITY 16 16

  17. District 9 – Planning (SFCTA) Alemany Interchange Improvement Study  $100,000 allocated  Develop pedestrian and bike improvements for area; new connections may include north/south path connecting San Bruno Avenue to Farmer’s Market, new bike lanes  Transportation Authority convened project team; existing conditions analysis and community outreach in spring 2016  Final report: October 2016 SA SAN N FRAN ANCI CISCO SCO COUN OUNTY Y TRAN ANSPO SPORT RTATIO TION N AUTH UTHORIT RITY 17 17

  18. District 10 – Capital (SFMTA) Cesar Chavez/ Bayshore/Potrero Intersection  $100,000 allocated  Advance design of wider multi-use or separated bike/ped paths, accessibility upgrades, lighting plan for interchange area  SFMTA held walking audit and meetings with key stakeholders including Supervisor Cohen’s office and SF Bike Coalition, started work on conceptual designs for two segments on Bayshore Blvd, planning outreach to Supervisor Campos’s office  SFPW surveyed key areas, initiated conceptual lighting plan  Anticipated completion: June 2016 SA SAN N FRAN ANCI CISCO SCO COUN OUNTY Y TRAN ANSPO SPORT RTATIO TION N AUTH UTHORIT RITY 18 18

  19. District 10 – Capital (Planning Department) Potrero Hill Pedestrian Safety and Transit Access  $60,000 allocated  Construct pedestrian bulbouts with high-impact planting barriers at five intersections  Project team is developing project charter, which will include revised project schedule  Anticipated completion: TBD SA SAN N FRAN ANCI CISCO SCO COUN OUNTY Y TRAN ANSPO SPORT RTATIO TION N AUTH UTHORIT RITY 19 19

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.