ICRP Recap 1 Closure and Reclamation Planning Describe activities - - PowerPoint PPT Presentation

icrp recap
SMART_READER_LITE
LIVE PREVIEW

ICRP Recap 1 Closure and Reclamation Planning Describe activities - - PowerPoint PPT Presentation

ICRP Recap 1 Closure and Reclamation Planning Describe activities to be planned and completed prior to and following the end of the operational life of a facility to make sure that it is properly closed and reclaimed Guidance provided


slide-1
SLIDE 1

1

ICRP Recap

slide-2
SLIDE 2

2

Closure and Reclamation Planning

  • Describe activities to be

planned and completed prior to and following the end of the

  • perational life of a facility to

make sure that it is properly closed and reclaimed

  • Guidance provided in

Mackenzie Valley Land and Water Board’s (MVLWB) “Guidelines for the Closure and Reclamation of Advanced Mineral Exploration and Mine Sites in the Northwest Territories”.

slide-3
SLIDE 3

3

Interim Closure and Reclamation Plan (ICRP)

  • Interim plan for closure & reclamation

which will be reviewed during the remaining life of the Operations

  • Required under the SLWB-issued

Water Licence for the Operations

  • Working Group has been the main

vehicle for ensuring that community perspectives and requirements are reflected in the ICRP

  • A more defined version of this plan

will be developed closer to the scheduled closure of the Operations.

slide-4
SLIDE 4

4

ICRP Planning & Working Group Involvement 2014-2015

slide-5
SLIDE 5

5

ICRP Planning & Working Group Involvement 2016-2018

slide-6
SLIDE 6

6

C&R Planning Approach

  • Follows the Objectives-Based

approach recommended in the MVLWB guidelines

  • Imperial and the Working Group

agreed to adopt the overall closure goal from the guidelines: “To return the site and affected areas to viable and wherever practicable, self- sustaining ecosystems that are compatible with a healthy environment and with human activities.”

slide-7
SLIDE 7

7

Closure Objectives

  • Describe what the selected closure

activities should aim to achieve

  • Set measurable, achievable targets
  • Site-wide Objectives apply property-

wide and address:

> overarching values as established by the Working Group > key environmental components or ‘media’, including air, land, water and wildlife.

slide-8
SLIDE 8

8

Site-wide Objectives: Overarching Values

  • Landscape closed and reclaimed in a manner that reflects consultation with

community members and associated Traditional Knowledge and use.

  • Removal or mitigation of physical and chemical hazards.
  • Incremental disturbance of land required to support closure and reclamation

activity minimized.

  • Compliance with legal, regulatory and corporate obligations.
  • Archaeological and historically significant sites identified by entities such as

the Prince of Wales Northern Heritage Centre, Norman Wells Historical Society, regional Land Corporations and Secretariat are protected and preserved.

slide-9
SLIDE 9

9

Site-wide Objectives: Environmental

  • Water quality that is safe for humans, wildlife and aquatic life
  • Water quality that does not cause an adverse effect on natural watercourses

such as the Mackenzie River and Bosworth Creek.

  • Hydrology and drainage of the reclaimed land surface generally consistent

with the character of the local watershed and appropriate to the defined land use.

  • Terrain restoration to allow safe utilization and passage by terrestrial wildlife.
  • Soil that is safe for people and the environment.
  • Closed and reclaimed landscape that is physically stable, safe, and

consistent and compatible with the surrounding natural area.

  • Dust levels at the closed and reclaimed site safe for people, vegetation,

wildlife, and aquatic life.

  • Above-ground facilities, infrastructure and debris are removed.
  • Below ground facilities and infrastructure are abandoned or removed as

appropriate for safe utilization of the defined future land use.

slide-10
SLIDE 10

10

Closure Components

  • Closure Components help

coordinate a consistent approach to planning

  • 4 distinct geographic areas:

> 1 Mainland, > 2 Natural Islands, > 3 Artificial Islands, and > 4Natural Watercourses.

  • 3 different types of major

infrastructure/functional features:

> Surface Buildings & Equipment, > Subsurface Infrastructure, and > Wellbores.

slide-11
SLIDE 11

11

Component Specific Objectives

  • Objectives developed for Closure Components.
  • Some match the site-wide objectives. Others are unique to a project

component.

  • Common themes:

> Reflects consultation with community members, Traditional Knowledge and use. > Soil and water that are safe for humans and the environment. > Compliance with legal, regulatory and corporate obligations. > Removal or mitigation of physical and chemical hazards. > Identified Archaeological and historically significant sites protected and preserved. > Closed landscape that is physically stable, safe, and compatible with the surrounding natural area.

slide-12
SLIDE 12

12

Closure Options

  • Set of proposed alternatives for

closing each project component

  • Closure options for the Operations

were evaluated to determine:

> how well each option met the closure

  • bjective(s)

> how well each was expected to perform > how well each addressed potential safety and environmental risks > possible benefits to the community (e.g., business & employment benefits).

slide-13
SLIDE 13

13

Closure Activities

  • Specific actions and measurements

completed to meet closure objectives.

  • Closure activities are described in the

ICRP.

  • Key closure activities and ICRP

planning priorities:

> Long Term Management Facility (LTMF) > Artificial Islands

slide-14
SLIDE 14

14

ICRP – Next Steps

  • Seek Working Group and other

stakeholder input on ICRP planning priorities (i.e. LTMF, Artificial Islands)

  • Update ICRP to reflect current

planning, stakeholder feedback and technical studies (2019)

  • Ongoing Stakeholder and Sahtu

community engagement

slide-15
SLIDE 15

15

Artificial Islands

slide-16
SLIDE 16

16

Artificial Islands

  • The islands were constructed

between 1983 and 1984 and are located in relatively shallow water near the edge of the main river channel

  • Constructed with a sand core

dredged from the river channel contained with a rock berm sourced from the local quarry

  • Surface infrastructure and facilities on

the islands include:

> docking areas > access ramps > well/facility pads > both injection and production wells

slide-17
SLIDE 17

17

Artificial Islands - Construction

slide-18
SLIDE 18

18

Artificial Islands - Slope Protection

  • Islands need to withstand the forces
  • f ice, rapidly changing water levels,

extreme currents and waves

  • Critical areas of slope protection

(armouring) maintained on sections with high erosion potential, and areas most vulnerable to ice action

slide-19
SLIDE 19

19

Mackenzie River at Norman Wells

  • Reach at Norman Wells is

relatively straight and very wide

(1.4km to 6km wide)

  • Carries a naturally high sediment
  • load. Suspended sediment values

at Norman Wells can seasonally exceed CCME Guidelines for the Protection of Aquatic Life

  • Fish species present near Norman

Wells include Arctic grayling, northern pike, walleye, Goldeye, Burbot, inconnu, mountain whitefish, longnose sucker, broad whitefish and Arctic lamprey

slide-20
SLIDE 20

20

Artificial Islands - C&R Options

  • Impacted soils that do not meet

criteria will be consolidated within the Mainland LTMF

  • Imperial is examining various

alternatives for the islands post closure

> Options include allowing the natural erosion processes and movement of the Mackenzie River to return the sands in the core of the islands to the riverbed after all or portions of the existing island armour is removed > Decisions on possible reclamation approaches will be informed by upcoming technical studies and stakeholder engagement and consultations

slide-21
SLIDE 21

21

Artificial Islands - Further Studies

  • Imperial is planning to complete an

assessment of the fish and fish habitat in the immediate vicinity of the Artificial Islands

  • Purpose is to understand the extent
  • f fish habitat that that may have

established within the armouring of the islands since their construction in the mid-1980’s

  • Outcomes of this study will be used

along with previously collected baseline fisheries information and

  • ther technical studies to inform
  • ngoing consideration of post-closure
  • ptions for the islands
slide-22
SLIDE 22

22

Artificial Islands - Further Studies

  • Additional studies will be undertaken

to assess possible reclamation approaches based on:

> Mackenzie River morphology (i.e. sediment release and deposition) > Fish and fish habitat > Green and Sustainable Remediation (GSR)

  • Ongoing Stakeholder and Sahtu

community engagement

slide-23
SLIDE 23