I DI Q . Pre-Proposal Conference RFP-FQ18033 General - - PowerPoint PPT Presentation

i di q pre proposal conference
SMART_READER_LITE
LIVE PREVIEW

I DI Q . Pre-Proposal Conference RFP-FQ18033 General - - PowerPoint PPT Presentation

Washington Metropolitan Area Transit Authority RFP-FQ18033 General Architectural and Engineering Consultant Services Program Management, Construction Management, and Engineering Support Services I DI Q . Pre-Proposal Conference RFP-FQ18033


slide-1
SLIDE 1

RFP-FQ18033

  • General Architectural and Engineering

Consultant Services – Program Management, Construction Management, and Engineering Support Services I DI Q.

Pre-Proposal Conference

Request for Proposal/Contract Number – FQ18033 January 8, 2018 10:00am-12:00pm EST Meeting Room JGB

Washington Metropolitan Area Transit Authority

RFP-FQ18033

General Architectural and Engineering Consultant Services – Program Management, Construction Management, and Engineering Support Services I DI Q.

1

slide-2
SLIDE 2

Opening Remarks

 Silence all Cell phones and pagers 

No Recording

This presentation and attendee list will be provided on WMATA.com website

Safety Tip: “Before shoveling or doing any strenuous work, avoid caffeine and nicotine. They increase your heart rate and may cause your blood vessels to constrict.”

Washington Metropolitan Area Transit Authority

RFP-FQ18033

General Architectural and Engineering Consultant Services – Program Management, Construction Management, and Engineering Support Services I DI Q.

2

slide-3
SLIDE 3

 Norie Calvert, Contracting Officer, PRMT  Guzel Gufranova, Contract Administrator, PRMT  John Thomas, Capital Project Director  Chen Zhou, Senior Program Manager

Introduction of WMATA Personnel

Washington Metropolitan Area Transit Authority

RFP-FQ18033

General Architectural and Engineering Consultant Services – Program Management, Construction Management, and Engineering Support Services I DI Q.

3

slide-4
SLIDE 4

PURPOSE

 To promote a common understanding of:  RFP –

  • Authority’s requirements
  • Solicitation Instructions

 To provide answers to questions regarding the RFP  Networking opportunity

Washington Metropolitan Area Transit Authority RFP – FQ18033

General Architectural and Engineering Consultant Services – Program Management, Construction Management, and Engineering Support Services I DI Q.

4

slide-5
SLIDE 5

After today’s conference, if you have additional questions, they must be received via electronic mail by the Contract Administrator. Email your questions to ggufranova@wmata.com by January, 12, 2018, COB.

PURPOSE

Washington Metropolitan Area Transit Authority

RFP-FQ18033

General Architectural and Engineering Consultant Services – Program Management, Construction Management, and Engineering Support Services I DI Q.

5

slide-6
SLIDE 6

The Pre-proposal Conference is for information purposes

  • nly. It may answer some Offeror questions.

Statements or representations made during the Conference are not legally binding. Changes resulting from this Conference are official only if issued through an Amendment to the Request For Proposals (RFP)

Disclaimer Regarding Changes to the Solicitation

Washington Metropolitan Area Transit Authority

RFP-FQ18033

6

slide-7
SLIDE 7

DESCRI PTI ON Washington Metropolitan Area Transit Authority

RFP-FQ18033 The Washington Metropolitan Area Transit Authority (WMATA/Authority/Metro) requires the services of a professional on-call general architectural and engineering contractor (“Contractor”) to provide engineering and construction support services in support of WMATA’s transit system. The Contractor shall assist the Authority by providing architectural and professional engineering services associated with Project Management/ Construction Management, and Engineering Support Services as outlined further in the RFP.

7

slide-8
SLIDE 8

DESCRI PTI ON Washington Metropolitan Area Transit Authority

RFP-FQ18033

It is anticipated that up to 4 Contractors which are deemed to be best qualified will be awarded a Contract. The number of awardees depends

  • n the number of best qualified firms identified through the evaluation

process. The estimated aggregate value for all task orders awarded will not exceed $100,000,000 over the Ordering period. The Ordering Period establishes the time limits for the issues of individual Task Orders and shall be five (5) years from the Notice of Award date. The guaranteed minimum for this contract is $50,000 per Contract, over the Ordering Period.

8

slide-9
SLIDE 9

DESCRI PTI ON Washington Metropolitan Area Transit Authority

RFP-FQ18033

Only Architect or Engineering firms may compete for this contract. Firms are required to submit documentation that the firm is an architect and/or engineering firm and is to provide that documentation in Section H-2, Block 30

  • f

the SF330. The Proposer and its Subcontractors as a proposed team shall demonstrate that it is permitted by law to practice the profession

  • f

architecture

  • r

engineering in the State of Maryland, the District of Columbia, and the Commonwealth of Virginia.

9

slide-10
SLIDE 10

1 original hard copy of: VOLUME I TECHNICAL PROPOSAL SOLICITATION, OFFER AND AWARD FORM

including CONTINUATION SHEET

6 USB flash drives; All electronic copies shall

be labeled with the RFP number, the Offeror’s identity, and volume number.

PROPOSAL SUBMI SSI ON Washington Metropolitan Area Transit Authority

RFP-FQ18033

10

slide-11
SLIDE 11

PROPOSAL SUBMI SSI ON Washington Metropolitan Area Transit Authority

RFP-FQ18033

VOLUME I – TECHNICAL PROPOSAL SECTION Page Limit

  • I. Proposal Cover Letter

2

  • II. Table of Contents for Technical Proposal

2

  • III. Glossary OF ABBREVIATIONS AND ACRONYMS (if applicable)

No limit

  • IV. A. Past Experience and Performance

10pages for Section F

  • IV. B. Relevant Technical Qualifications and Experience

10pages for Section E

  • IV. C. Management Approach

5pages for Section H-3

  • IV. D. DBE participation

3 pages

11

slide-12
SLIDE 12

PROPOSAL SUBMI SSI ON Washington Metropolitan Area Transit Authority

RFP-FQ18033

SF 330 – ARCHI TECT-ENGI NEER QUALI FI CATI ONS

  • Follow the directions included in the instructions of the SF 330 unless

directed otherwise in the Solicitation

  • 4 EVALUATION CRITERIA:
  • 1. Past Experience and Performance (40% weight):

SF 330, Section F – example projects (10 pages) SF 330, Section H 1 – Performance Evaluation Forms

12

slide-13
SLIDE 13

4 EVALUATION CRITERIA (continued):

  • 2. Relevant Techn-l Qualifications and Expertise (Weight: 30%)

Section A – Contract Information Section B – A&E point of contact Section C – Proposed Team Section E – Resumes of Key Personnel proposed for this Contract (2pages per resume for up to 5 key personnel) Section G – Key Personnel participation in example projects Section I – Authorized Representative Section H-2: Documentation showing a Proposer is a professional A&E firm. Proposed Team by law can practice Architecture and/or Engineering in MD, DC VA

Washington Metropolitan Area Transit Authority

RFP-FQ18033

13

slide-14
SLIDE 14

4 EVALUATION CRITERIA (continued): Washington Metropolitan Area Transit Authority

RFP-FQ18033

  • 3. Management Approach (Weight 20%)

Section D – Org Chart of Proposed Team Section H-3 – Narrative on the management approach (5 pages) SF 330, Part II – General Qualifications

  • 4. DBE Participation (Weight 10%) 3 pages
  • Summary of DBE utilization
  • Other examples of promoting sub opportunities for DBE goal
  • DBE Approach and commitment

14

slide-15
SLIDE 15

PROPOSAL SUBMI SSI ON Washington Metropolitan Area Transit Authority

RFP-FQ18033 Volume II Price Proposal and Volume III Contractual Proposal will be requested separately from the proposers deemed best qualified.

WMATA requires a minimum acceptance period of 120 calendar days.

15

slide-16
SLIDE 16

PROPOSAL SUBMI SSI ON Washington Metropolitan Area Transit Authority

RFP-FQ18033

Proposals are to be received no later than January 23, 2018, 2:00 PM EST.

16

slide-17
SLIDE 17

 SUBMI SSI ON OF THE PROPOSALS The outside of the sealed envelope shall show:

  • HOUR and DATE specified in the RFP for proposal

closing, the RFP number, and the full legal name and address of the offeror on the face of the envelope

  • PROPOSAL SHALL BE ADDRESSED TO: WASHINGTON

METROPOLITAN AREA TRANSIT AUTHORITY 600 5th Street, N.W. Washington, DC 20001 Room 3C-02 Attn: Guzel Gufranova /CA Washington Metropolitan Area Transit Authority

RFP-FQ18033

slide-18
SLIDE 18

SCHEDULE EVENT DATE RFP Release December 20, 2017 Pre-Proposal Conference January 8, 2018 Deadline for Proposer Questions January 12, 2018 Proposals Due January 23, 2018 Award Date (estimated) May 23, 2018

Dates Subject to Change

Washington Metropolitan Area Transit Authority

RFP-FQ18033

18

slide-19
SLIDE 19

Washington Metropolitan Area Transit Authority

RFP-FQ18033

DBE Compliance, Appendix “B”

19

slide-20
SLIDE 20

Disadvantaged Business Enterprises Disadvantaged Business Enterprise (DBE) Submit complete

schedule of DBE participation and Letters of Intent. All DBEs must have current WMATA DBE certifications.

It is the policy of WMATA, the Federal Transit Administration (FTA) and the U.S. Department of Transportation (US DOT) that Disadvantaged Business Enterprises (DBE’s) shall have an equal opportunity to receive and participate in performing federally -assisted contracts, including contractors and subcontractors at any tier. Washington Metropolitan Area Transit Authority

RFP-FQ18033

slide-21
SLIDE 21

SUMMARY OF SUBMITTALS With the Task Order Proposal

  • 1. Completed “Schedule of DBE Participation” with current

certification letters attached for each listed DBE.

  • 2. Executed “Letters of Intent to Perform as a Subcontractor/Joint Venture”
  • 3. Justification for grant of relief (waiver of DBE goal), if applicable. Include

completed “DBE Unavailability Certifications” as appropriate.

Washington Metropolitan Area Transit Authority

RFP-FQ18033

21

slide-22
SLIDE 22

SUMMARY OF SUBMITTALS Task Order DBE Proposal Requirements

  • 1. All DBEs must submit a copy of their current WMATA or DC DOT

certification letters or a certification letter issued by the MWUCP.

  • 2. DBE Manufacturer’s Affidavit, if applicable, must be submitted in order

to receive 100 percent of the allowable credit for expenditures to DBE manufacturers/suppliers (Attachment B-4).

  • 3. Schedule B Information for Determining Joint Venture Eligibility, if

applicable (Attachment B-5, pgs. 1, 2, 3, 4).

  • 4. Copy of Joint Venture Agreement, if applicable.
  • 5. Certification letter of the DBE regular dealer/supplier, if applicable.

Washington Metropolitan Area Transit Authority

RFP-FQ18033

22

slide-23
SLIDE 23

SUMMARY OF SUBMITTALS

After Contract Award

  • 1. “Prompt Payment Report-Prime Contractor’s Report”

Attachment B-6) – submitted monthly.

  • 2. “Prompt Payment Report-Subcontractor’s Report” (Attachment

B-7) – submitted monthly.

  • 3. Request to substitute DBE contractor (see paragraph 8.C.) –

submitted as required.

  • 4. Copies of subcontracts-submitted at the time of their execution.

Washington Metropolitan Area Transit Authority

RFP-FQ18033

23

slide-24
SLIDE 24

Washington Metropolitan Area Transit Authority

RFP-FQ18033

QUESTIONS?

24