I-5: Roberts Cr South Umpqua River Paving and Climbing Lane Project Mobility Advisory Committee August 21, 2018 I-5: Roberts Cr South Umpqua River Project Mobility Review Paving Project Overview Exit 119 Widening Grind and
SLIDE 1
SLIDE 2
Exit 113 Exit 119 Paving Widening
Project Overview
- Grind and pave Interstate 5 between
mile points 112.64 and 117.74
- Construct northbound and southbound
climbing lanes over Roberts Mountain; mile points 115.30 to 117.70
- All widening for the climbing lanes will
be to the west side of I-5.
- ODOT is requesting a Sunrise/Sunset
exemption of 7pm to 7am.
- Daytime configuration: Two lanes each
direction with 28’ clearance
- Nighttime configuration: Will allow a
single 14’ lane in one direction
- Deep pavement repair locations:
- Exit 113: route traffic via the
interchange ramps
- South Umpqua River: Single 13’ lane
2 3 4
Exit 112
5 1
I-5: Roberts Cr – South Umpqua River Project – Mobility Review
SLIDE 3
Location 1
Climbing lane section north of summit, looking south
I-5: Roberts Cr – South Umpqua River Project – Mobility Review
SLIDE 4
Location 2
Climbing lane section south of summit, looking south
I-5: Roberts Cr – South Umpqua River Project – Mobility Review
SLIDE 5
Location 3
Paving section south of Roberts Mtn
I-5: Roberts Cr – South Umpqua River Project – Mobility Review
SLIDE 6
Location 4
Deep pavement repair, Exit 113; Detour on interchange ramps
I-5: Roberts Cr – South Umpqua River Project – Mobility Review
Exit 113
SLIDE 7
Location 5
Deep pavement repair, South Umpqua River Bridges; Single 13’ lane