hurricane hermine
play

HURRICANE HERMINE Wastew ater Collection System Challenges and - PowerPoint PPT Presentation

HURRICANE HERMINE Wastew ater Collection System Challenges and Response Sept. 20, 2016 David W. Porter, P.E. Public Utilities Director myclearw ater.com | 1 CITY OF CLEARWATER Overview Mayor Cretekos Remarks Storm duration


  1. HURRICANE HERMINE Wastew ater Collection System Challenges and Response Sept. 20, 2016 David W. Porter, P.E. Public Utilities Director myclearw ater.com | 1 CITY OF CLEARWATER

  2. Overview • Mayor Cretekos’ Remarks • Storm duration Tuesday, Aug. 30 through Friday, Sept. 2 • Rain (> 10”) • Sanitary Sewer Overflows: – Corona Avenue area (2.9 Million Gallons) – North Greenwood area (18.8 Million Gallons) – Marshall Street WRF (10 Million Gallons) | | 2 2 CITY OF CLEARWATER

  3. Collection System Challenges • Hurricane caused Inflow and Infiltration to be far greater than typically experienced • Flows were estimated at three to five times an average day • Collection system backup due to equipment failure at the MSWRF • Corona Avenue Collector Sewer bottleneck • Beach flooding induced excessive inflow and infiltration | | 3 3 CITY OF CLEARWATER

  4. Preparation and Response • Preparation began week before the storm • Response – Wednesday, Aug. 31 at 7 a.m. to Wednesday, Sept. 8 at 7 a.m. 24/7 vacuum truck operations at Corona Interceptor bottleneck manhole – Staff responded to SSO reports 24/7 throughout system during entire event – Thursday, Sept. 1 to date – Marshall Street WRF lift station failure response with temporary pumps • Extensive, multi-year collection system inflow and infiltration investigation and repair effort already underway • Corona Avenue Collector bottleneck solution final design underway | | 4 4 CITY OF CLEARWATER

  5. Moving Forward • Final completion of an after-event evaluation of storm-related issues and responses • Continue inflow and infiltration investigation and repair efforts • Correct Corona Avenue Collector Sewer bottleneck • Repair Marshall Street WRF Influent Lift Station | | 5 5 CITY OF CLEARWATER

  6. HURRICANE HERMINE Wastew ater Collection System Challenges and Response Sept. 20, 2016 David W. Porter, P.E. Public Utilities Director myclearw ater.com | 6 CITY OF CLEARWATER

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend