HOWARD STREET TUNNEL: POSITIONING MARYLAND FOR SUCCESS Greater - PowerPoint PPT Presentation

HOWARD STREET TUNNEL: POSITIONING MARYLAND FOR SUCCESS Greater Baltimore Committee September 21, 2016 CSX IS A PREMIER TRANSPORTATION COMPANY CSX Rail Network and Major Terminals Company Profile Revenue* $11.8B Capital Investment** $2.4B


  1. HOWARD STREET TUNNEL: POSITIONING MARYLAND FOR SUCCESS Greater Baltimore Committee September 21, 2016

  2. CSX IS A PREMIER TRANSPORTATION COMPANY CSX Rail Network and Major Terminals Company Profile Revenue* $11.8B Capital Investment** $2.4B Miles of Track 21,000 miles Employees 28,000 500+ trains online at any point in time *2015 2 **2016 projected

  3. BUSINESS DIVERSIFIED ACROSS BROAD MARKET BASE 2015 Volume by Market: 6.9 Million Rail Car Loads Merchandise: 42% (Agriculture, Construction & Coal: 17% Industrial) (Domestic & Export) Intermodal: 41% (Domestic & International) 3

  4. CSX AND MARYLAND: A 190-YEAR PARTNERSHIP Company Profile in MD (2015) Employees 1680 Customers 1000+ Miles of Track 1400+ Miles of Track $62.5M  Seagirt: Intermodal  Curtis Bay: Coal  Jessup: Auto 4

  5. THE POWER OF TWO FEET: HELPING TO TRANSFORM MARYLAND’S ECONOMY  Positions Port for strong growth  Deep water allows for largest ships  High-frequency, on-dock rail  Making existing businesses more competitive (and Today (19 ft) help attract new businesses) Single Stacked  Creates jobs  500 jobs to construct & 3200 statewide  Quicker and safer trip home for commuters  178,000 trucks off the road  Cleaner environment Tomorrow (21ft)  CO 2 equivalent of 700,000 cars Double Stacked 5

  6. CSX/MD STUDY: CLEARING HST TO SEAGIRT FEASIBLE  Existing HST is structurally sound  To prolong HST’s useful life, frequent flooding must be addressed  9 other obstructions between Howard Street and Seagirt must be cleared  Project cost ~$425M  4-5 years to complete with minimal impact to public  Freight operations continue through tunnel during construction 6

  7. PUBLIC-PRIVATE PARTNERSHIP POSITIONS HST PROJECT FOR SUCCESS Entity Cost Share ($M’s) Maryland 145 CSX 125 Federal 155 Total 425 CSX investing additional $20M now to progress HST project (drainage upgrades and design/engineering) CSX is fully committed to working with local, state and federal officials to make the Howard Street Tunnel project a reality 7

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.