How would you do it? Tony Cox: CMIOSH David Butler: CMIOSH HSM - - PowerPoint PPT Presentation

how would you do it
SMART_READER_LITE
LIVE PREVIEW

How would you do it? Tony Cox: CMIOSH David Butler: CMIOSH HSM - - PowerPoint PPT Presentation

See 2 nd slide for update 'Keeping OSH on track: Spotting Hazards and Risk in a Complex Environment' How would you do it? Tony Cox: CMIOSH David Butler: CMIOSH HSM Network Rail 17 October 2019 Note to viewers using this pdf (22/10/19)


slide-1
SLIDE 1

'Keeping OSH on track: Spotting Hazards and Risk in a Complex Environment' How would you do it?

Tony Cox: CMIOSH David Butler: CMIOSH HSM Network Rail 17 October 2019

See 2nd slide for update

slide-2
SLIDE 2

Note to viewers using this pdf (22/10/19)

  • This icon indicates links to videos. These

require an internet connection to function and were current at the time of publication (22/10/19)

  • Feedback from delegate groups now included

(Session 2).

  • Additional material covered during the session is

now included at the end.

1

slide-3
SLIDE 3

2

Speakers

  • Tony Cox: CMIOSH

Health & Safety consultant.

More than forty years employed by the Regulator first as HM Inspector of Factories then as HM Inspector of Railways encompassing developments in UK & EU health & safety pre- Robens until retirement in the current decade. Became a IOSH RSP in 1989 and a Chartered Member in 2005. Experience in investigation, inspection and enforcement in most industry, service and railway sectors during that time.

  • David Butler: CMIOSH H&S Manager

(Strategic) Network Rail High Output Track Renewals

A business studies graduate, chartered H&S practitioner and former member of the Institute of Industrial Accident Investigation (MIIAI), I have been advising on H&S for over 15 years. I have experience in UK railway Railtrack, Railway Safety , RSSB, logistics and warehousing and retail – Royal Mail, Parcel Force and Amazon. Former chair of the Parcel Carriers’ Safety Association. Contributed to High Output achieving the British Safety Council 5 Star Audit award and Sword of Honour 3 years running.

slide-4
SLIDE 4

Introduction

  • Recent branch planning meeting –how we could help

members to be more confident when encountering situations well outside of their comfort zone

  • Chiltern is not a specialist group but we came up

with railway situation which we felt most if not all, are likely to be unfamiliar.

  • The example is real and we expect you to use first

principles to identify the various issues – and at the end David will tell you what actually has happened.

3

slide-5
SLIDE 5

4

Introduction continued..

  • The situation could arise as part of investigation,

audit or even regulatory enforcement.

  • expect tables to pool H&S experiences and to work

as a group.

  • Our time will be broadly divided into 3 sessions:
  • Session 1: basic analysis and feedback. Followed by

discussion on findings and greater speaker explanation.

  • Session 2: Further analysis and feedback
  • Session 3: Where are we now?
slide-6
SLIDE 6

5

Setting the scene

  • Network Rail currently has 20000 miles of track

covering the UK.

  • Our railways are one of the most intensively used in

the world – much of the infrastructure was laid down in the 19 century.

  • It needs regular maintenance to keep the trains

running – the scene of teams working trackside is going with introduction of mechanised inspection and maintenance equipment with better specification

  • f materials and design of equipment used. And a

lot of work now takes place at night.

slide-7
SLIDE 7

6

Setting the scene

  • Most of it is ballasted track where the rails are supported on a

base or foundation of crushed stone. Sleepers are used to keep the rails in gauge using fastenings, usually clips. Ballast ensures the rail is kept level and allows drainage.

slide-8
SLIDE 8

Setting the scene

  • Network Rail uses a number specialised machines to

for track maintenance or replacement.

  • Ballast: HIGH OUTPUT BALLAST CLEANER (HOBC).
  • There are now 4 HOBC machines in the country

costing about £20million each - sufficient to cover the routes including conductor rail DC (Southern).

  • They are normally used at night. After setting up

you probably on get 1hour or less work before the track has to be handed back to the operational railway.

  • At first sight it all seems complicated but..

7

slide-9
SLIDE 9

HOBC Machine

8

slide-10
SLIDE 10

HOBC Machine

9

slide-11
SLIDE 11

HOBC Machine

10

slide-12
SLIDE 12

HOBC Machine

11

slide-13
SLIDE 13

HOBC Machine

12

slide-14
SLIDE 14

HOBC Machine

13

slide-15
SLIDE 15

HOBC Machine

  • Cutter bar arrangement and installation (Photo)

14

slide-16
SLIDE 16

HOBC Machine

  • Video of BCS in operation (2010)
  • The whole working unit can be over ½ Mile (.8km)

long.

  • Staffing: team of 50-70 people are required per shift

to operate the unit (depends on condition of old ballast, extent of possession available etc etc). 8-12 will be operators and managers/supervisors.

  • Each shift costs around £100-150k to run

(missed/cancelled shifts are thus expensive).

15

slide-17
SLIDE 17

Over to you

  • Think outside the box – there are at least 16 areas
  • f potential interest.
  • Some of these are interrelated

16

slide-18
SLIDE 18

17

Session 2

slide-19
SLIDE 19

Delegate Feedback I

18

slide-20
SLIDE 20

Delegate Feedback II

19

slide-21
SLIDE 21
  • I. Risks which were later provided by

the speakers in summary

  • Dust and RCS
  • Noise
  • Travel and Fatigue
  • Communications between different teams
  • Movement of machinery
  • Any (Adjacent) lines open/open line working
  • Rail operations
  • Time constraints
  • Permit to work systems

20

slide-22
SLIDE 22
  • II. Risks which were later provided by

the speakers in summary

  • Machinery safety
  • Slips trips falls, lighting
  • Contractor management
  • Training
  • Geography and worksite characteristics – proximity

to line side neighbours

  • Welfare arrangements.
  • PPE
  • Electricity

21

slide-23
SLIDE 23
  • III. Risks which were later provided by

the speakers in summary

  • Working at Height
  • Projectiles (ballast)
  • Manual handling
  • Asbestos (ACM)
  • Biological hazards
  • Environmental hazards
  • Trespass/security/level crossings

22

slide-24
SLIDE 24

23

Session 3

slide-25
SLIDE 25
  • High Output Track renewals to day

https://youtu.be/4AomnSbnwus

  • Site briefings today

https://network-rail.wistia.com/medias/gxm8ahsaiu Watch from mins 1:07 until to mins 12:26

Session 3 – Where is Network Rail today ?

slide-26
SLIDE 26

What’s changed? Fatigue & Occupational Road Risk

slide-27
SLIDE 27

What’s changed? Open Line Working & ALO

https://network-rail.wistia.com/medias/ycaeytygsk

slide-28
SLIDE 28

Dust: the problem illustrated

27

slide-29
SLIDE 29

1) CoSHH Assessment, how does the substance cause, harm, to who, where, when 2) Precautionary Approach – Blanket approach to PPE controls 3) Commissioned RCS Monitoring and Analysis 4) Began Learning – implementing changes

What’s changed? Dust

First Steps Daily exposure limit…

slide-30
SLIDE 30

What’s changed? RPE/PPE

slide-31
SLIDE 31

What’s changed? Training

  • RPE Use
  • Buddy system wipe down and storage
  • Maintenance of RPE - replacing filters,
  • Face fit testing – for FFP3 and Airfed RPE
  • Trained - Face fit testers
  • Health awareness
  • Maintaining training records – for a

competence Alien to Network Rail

slide-32
SLIDE 32

What’s changed? Processes

slide-33
SLIDE 33

What’s changed? Engineered Solutions

slide-34
SLIDE 34

What’s changed? Eliminate at Source

Quarry Process Load and Transport to MHDs Store pending demand Load and Deliver to site Process into Track/ reuse existing Remove Spoil and transport to MHD Clean Down and Prepare Train

slide-35
SLIDE 35

We are Leading not Lagging

slide-36
SLIDE 36

Still Challenges & Opportunities ahead – no room for complacency!

slide-37
SLIDE 37

Your Thoughts ? …?

slide-38
SLIDE 38

37

Closing Summary

slide-39
SLIDE 39

Additional material

38

slide-40
SLIDE 40

Silica dust follow up after visit

39

  • Part of ORR presentation to Network Rail 10/10
slide-41
SLIDE 41

Making a point – regulator visit with air fed RPE (2010)

40

slide-42
SLIDE 42

HOBC Comms: Site presentation

41

Presentation given to ORR on site on comms requirements. Once the BCS reaches the work site it is no longer operated under railway rules In still needs contact on the lower 3 separate levels.

slide-43
SLIDE 43

Tamper (see BCS arrangements in slide 8)

42

slide-44
SLIDE 44

Diagrams

43

Fresh Ballast system RM900-RT Work Unit Ballast Screen

slide-45
SLIDE 45

Diagrams

44

Spoil Waggons (interconnected) Fresh Ballast waggons (interconnected)