Deltaport Shore Power Project November 17, 2016 Container Shore - - PowerPoint PPT Presentation

deltaport shore power project
SMART_READER_LITE
LIVE PREVIEW

Deltaport Shore Power Project November 17, 2016 Container Shore - - PowerPoint PPT Presentation

Deltaport Shore Power Project November 17, 2016 Container Shore Power Projects In 2015, federal government/ VFP A announced funding for installation of shore power at two terminals - Deltaport and Centerm Project funding is approx.


slide-1
SLIDE 1

Deltaport Shore Power Project

November 17, 2016

slide-2
SLIDE 2

Container Shore Power Projects

  • In 2015, federal government/

VFP A announced funding for installation of shore power at two terminals - Deltaport and Centerm

  • Project funding is approx. $14

million: $7 million from T ransport Canada’s Shore P

  • wer T

echnology for P

  • rts Program and $7 million

from VFP A

  • Working to make shore power

connections available and incenting shipping lines to use shore power through harbour dues discounts 2

slide-3
SLIDE 3

Rationale

  • Shipping line readiness:

2012 study suggested an increasing number of shore power equipped container vessels are expected to call at Port of Vancouver

  • Provisioning of shore power

facilities recommended

  • Regulatory environment:

shore power compliance is voluntary

slide-4
SLIDE 4

Shore Power Locations

Centerm Deltaport Canada Place (Cruise)

slide-5
SLIDE 5

Key Items Needed

  • Funding agreement
  • Favorable rate structure from

BC Hydro

  • Operating agreements
  • T

erminal resources available and committed to project

  • Confirmed standard

technology

slide-6
SLIDE 6

Deltaport Third Berth

  • T

wo HVSC pits to support port side berthing

  • BC Hydro 69 kV transmission service

6

1 2

Transformer yard Berth 3 HVSC substation Berth 1 Berth 2 Berth 3

slide-7
SLIDE 7

Cables Connecting to Shore Power

slide-8
SLIDE 8

Pit open Pit closed Note hinge and locking pin, in some installations the bull rail is on rollers

High Voltage Shore Connection Pit

slide-9
SLIDE 9

Receptacle pit with junction box and connector plugs

High Voltage Shore Connection Equipment

Removable cover to accommodate cable access from ship

slide-10
SLIDE 10

10

Berth 3 High Voltage Shore Connection Locations

slide-11
SLIDE 11

11

Deltaport Shore Power Preliminary Design

Shore Power Transformer Switchgear Port Side HVSC Starboard Side HVSC (pending funding) 6+94m 7+59m 9+91m 10+77m Duct Bank Service Tunnel

slide-12
SLIDE 12

12

Shore Power Transformer

Substation

Transformer

slide-13
SLIDE 13

Schedule

slide-14
SLIDE 14

2015 Shore Power Capable Ship Calls

14

Container term inal # of shore pow er capable calls

Deltaport 44 Centerm 36

  • Actual number of connections will depend on:
  • Configuration of land based equipment
  • Location and limitations of ship based equipment
  • Ship willingness to connect
  • Cost of connection
  • Availability of power from BC Hydro
slide-15
SLIDE 15

Key Benefits

  • Reduces air emissions
  • Improves air quality for terminal

employees and community

  • Reduces noise impact
  • Improves crane productivity if
  • perations stopped due to vessel

fumes and in-shore winds

15

slide-16
SLIDE 16

Environmental Benefits

slide-17
SLIDE 17

Noise Reduction – Shore Power

  • Auxiliary engines shut

down while at berth

  • Remaining sources of

noise may include pumps, ventilation, refrigeration units, air conditioning

Low Frequency 40 to 160 Hz Mid Frequency 500 to 2000 Hz

slide-18
SLIDE 18

55 60 65 70 75 80 85 LAeq(dB)

Leq 40Hz

Leq shows lower dB values due to the A-Weighting applied, which discounts the lower frequencies.

Noise Reduction – Low Frequency on Background

Pre Arrival Post Departure

Vessel Berth 1 Vessel Berth 2

slide-19
SLIDE 19

Noise Reduction – Sound Power Level (dBA)

Noise Source ( Container Ship) Aux Engine Shore Pow er Change Total ( calculated) 107 119 105 111 2 – 8 Aux engine – funnel 100 115 n/ a n/ a Aux engine – ventilation 100 115 n/ a n/ a Main engine – ventilation 93 107 91 97 Bridge/ deck – ventilation 80 90 80 90 Reefers 105 111 105 111

  • Internoise 2010, J. White, Noise from Moored Ships
  • Sample size 7; 8,000 to 80,000 DWT (1000 to 7000 TEU)
  • Sound Power Level – sound energy in Watts per Area
slide-20
SLIDE 20

Distribute notice to nearby residents 10 days prior to construction / physical activities which includes:

  • Description of works and activities
  • Hours of operation
  • Monday to Saturday between 7:00 am to 8:00 pm
  • No construction and physical activities during Sundays or

holidays

  • Contact information

Community Communication

slide-21
SLIDE 21

Construction Notification Mail Drop Area Map

slide-22
SLIDE 22

Thank you