Deltaport Shore Power Project November 17, 2016 Container Shore - - PowerPoint PPT Presentation
Deltaport Shore Power Project November 17, 2016 Container Shore - - PowerPoint PPT Presentation
Deltaport Shore Power Project November 17, 2016 Container Shore Power Projects In 2015, federal government/ VFP A announced funding for installation of shore power at two terminals - Deltaport and Centerm Project funding is approx.
Container Shore Power Projects
- In 2015, federal government/
VFP A announced funding for installation of shore power at two terminals - Deltaport and Centerm
- Project funding is approx. $14
million: $7 million from T ransport Canada’s Shore P
- wer T
echnology for P
- rts Program and $7 million
from VFP A
- Working to make shore power
connections available and incenting shipping lines to use shore power through harbour dues discounts 2
Rationale
- Shipping line readiness:
2012 study suggested an increasing number of shore power equipped container vessels are expected to call at Port of Vancouver
- Provisioning of shore power
facilities recommended
- Regulatory environment:
shore power compliance is voluntary
Shore Power Locations
Centerm Deltaport Canada Place (Cruise)
Key Items Needed
- Funding agreement
- Favorable rate structure from
BC Hydro
- Operating agreements
- T
erminal resources available and committed to project
- Confirmed standard
technology
Deltaport Third Berth
- T
wo HVSC pits to support port side berthing
- BC Hydro 69 kV transmission service
6
1 2
Transformer yard Berth 3 HVSC substation Berth 1 Berth 2 Berth 3
Cables Connecting to Shore Power
Pit open Pit closed Note hinge and locking pin, in some installations the bull rail is on rollers
High Voltage Shore Connection Pit
Receptacle pit with junction box and connector plugs
High Voltage Shore Connection Equipment
Removable cover to accommodate cable access from ship
10
Berth 3 High Voltage Shore Connection Locations
11
Deltaport Shore Power Preliminary Design
Shore Power Transformer Switchgear Port Side HVSC Starboard Side HVSC (pending funding) 6+94m 7+59m 9+91m 10+77m Duct Bank Service Tunnel
12
Shore Power Transformer
Substation
Transformer
Schedule
2015 Shore Power Capable Ship Calls
14
Container term inal # of shore pow er capable calls
Deltaport 44 Centerm 36
- Actual number of connections will depend on:
- Configuration of land based equipment
- Location and limitations of ship based equipment
- Ship willingness to connect
- Cost of connection
- Availability of power from BC Hydro
Key Benefits
- Reduces air emissions
- Improves air quality for terminal
employees and community
- Reduces noise impact
- Improves crane productivity if
- perations stopped due to vessel
fumes and in-shore winds
15
Environmental Benefits
Noise Reduction – Shore Power
- Auxiliary engines shut
down while at berth
- Remaining sources of
noise may include pumps, ventilation, refrigeration units, air conditioning
Low Frequency 40 to 160 Hz Mid Frequency 500 to 2000 Hz
55 60 65 70 75 80 85 LAeq(dB)
Leq 40Hz
Leq shows lower dB values due to the A-Weighting applied, which discounts the lower frequencies.
Noise Reduction – Low Frequency on Background
Pre Arrival Post Departure
Vessel Berth 1 Vessel Berth 2
Noise Reduction – Sound Power Level (dBA)
Noise Source ( Container Ship) Aux Engine Shore Pow er Change Total ( calculated) 107 119 105 111 2 – 8 Aux engine – funnel 100 115 n/ a n/ a Aux engine – ventilation 100 115 n/ a n/ a Main engine – ventilation 93 107 91 97 Bridge/ deck – ventilation 80 90 80 90 Reefers 105 111 105 111
- Internoise 2010, J. White, Noise from Moored Ships
- Sample size 7; 8,000 to 80,000 DWT (1000 to 7000 TEU)
- Sound Power Level – sound energy in Watts per Area
Distribute notice to nearby residents 10 days prior to construction / physical activities which includes:
- Description of works and activities
- Hours of operation
- Monday to Saturday between 7:00 am to 8:00 pm
- No construction and physical activities during Sundays or
holidays
- Contact information