How is the design progressing? relocated ticket stair m.r. - - PowerPoint PPT Presentation

how is the design progressing
SMART_READER_LITE
LIVE PREVIEW

How is the design progressing? relocated ticket stair m.r. - - PowerPoint PPT Presentation

How is the design progressing? relocated ticket stair m.r. extent of new existing elevator building footprint commercial of stair opportunity to be relocated 5m 15m 30m coat check/ merchandise open to below


slide-1
SLIDE 1
slide-2
SLIDE 2

How is the design progressing?

slide-3
SLIDE 3

extent of existing building

relocated stair footprint

  • f stair

to be relocated ticket

  • commercial
  • pportunity

m.r. new elevator 5m 15m 30m

slide-4
SLIDE 4

extent of existing building

coat check/ merchandise

  • pen to

below sound booth w/c w/c st. bar 5m 15m 30m

slide-5
SLIDE 5
slide-6
SLIDE 6

MASSING OPTION 1 BIRDSEYE VIEW MASSING OPTION 1 PERSPECTIVE VIEW

slide-7
SLIDE 7

MASSING OPTION 2 PERSPECTIVE VIEW MASSING OPTION 3 PERSPECTIVE VIEW

slide-8
SLIDE 8 CHARCOAL CORRUGATED METAL PANEL CHARCOAL CORRUGATED METAL PANEL (PERFORATED) FEATURE GLAZING PRE-CAST PANEL TO MATCH EXISTING ALUMINUM SOFFIT (WITH LED MARQUEE LIGHTING) GREY GLAZING
slide-9
SLIDE 9

INTERIOR VIEW

slide-10
SLIDE 10

RECESSIVE WALLS AND CEILING FEATURE RIBBON

slide-11
SLIDE 11
slide-12
SLIDE 12

INTERIOR ELEVATIONS

slide-13
SLIDE 13

Budget update

  • Construction manager on the team to

provide best-possible budget estimates as project progresses

  • Latest estimate: $14.2M, hard and soft

costs included

  • Lots of slack, but no provision for further

development in Lower Level, so using the 14M number as a planning baseline

  • Options:
  • Theatre refurb only ($5-6 M)
  • Expansion + refurb ($12-14M)

Item Amount Construc*on Costs 9,637,097 Furniture, fixtures, and equipment (e.g. new ligh*ng and sound, seats, etc) 2,110,000 Consultants and Design 1,163,909 Con*ngency (10%) 1,291,101 Total 14,202,107

slide-14
SLIDE 14

Where are we in the planning and design process?

Concept Design Concept Design

  • Schick Shiner report

Schematic Design

  • We are in this phase

Design Development Construction Documents

slide-15
SLIDE 15

Design Phase Costs

  • Design Development – grant applied for, but award would be late.

Will be bringing this to a Council soon to discuss making a reserve allocation in the interim.

  • We are aiming to bring the project to the red line before pausing to

assess fundraising. Phase Cost Notes Concept Design 47,375 Schick Shiner. Funded by grant. Schema*c Design 95,030 Funded by benefit surplus Design Development 97,645 Grant applied for, but will be late Contract Documents 333,890 Funded by project capital plan

slide-16
SLIDE 16

Myer Horowitz Fundraising Update


November 1st, 2016

slide-17
SLIDE 17

Outline Outline

§ Goals § What we’ve done § What we’re doing § What is left to do § Fundraising Risks § Alternatives § Recommendation § Conclusion

slide-18
SLIDE 18

Goals Goals

Minimize cost to students Create a link

slide-19
SLIDE 19

Goals Goals

Fundraise $10 million

slide-20
SLIDE 20

What we’ve done What we’ve done

Extensive Consultation Extensive Consultation

  • Meetings with professionals
  • Consultation with Advancement &

Alumni Relations

  • Development of a case
  • Data collection
slide-21
SLIDE 21

What we’ve done What we’ve done

Cr Creation of the Friends of the Myer eation of the Friends of the Myer Hor Horowitz

  • witz
  • Not-for-profit society
  • Board of Directors to act as

consultants

  • Anyone who donates becomes a

member

slide-22
SLIDE 22

What we’ve done What we’ve done

FMHT - Membership FMHT - Membership

  • Maria David Evans – AB Gov & NFPs
  • Myer Horowitz – Former U of A President
  • Remco Van Eeuwijk - AIMCO
  • Katherine Huising – AB Gov
  • Gerry Kendal – Office of the Provost
  • Andrew Sharman – VP Facilities & Operations
  • Michael Phair – U of A Board Chair
slide-23
SLIDE 23

What we’r What we’re doing e doing

Fundraising Strategy Fundraising Strategy

  • Creation of a Capital Campaign

Plan

  • A plan for SIEF
  • Finalizing the case
  • Compiling alumni data
slide-24
SLIDE 24

What we’r What we’re doing e doing

Phased Fundraising Appr Phased Fundraising Approach

  • ach
  • The Theatre o The Experience o The Students
slide-25
SLIDE 25

What’ What’s left to do s left to do

Cr Creation of Fundraising Materials eation of Fundraising Materials

  • Stand-alone website
  • Print materials &

design

slide-26
SLIDE 26

What’ What’s left to do s left to do

Finalize planning and engage donors Finalize planning and engage donors

  • Capital Campaign Plan
  • Structure a fundraising team
  • Approach donors
slide-27
SLIDE 27

Fundraising Risks Fundraising Risks

Major Considerations Major Considerations

  • Unable to fundraise enough
  • Unpredictability
  • Turnover
slide-28
SLIDE 28

Alter Alternatives natives

Options Options

  • Begin fundraising

immediately

  • Hire an external team
  • Complete a test of the

market

slide-29
SLIDE 29

Recommendation Recommendation

slide-30
SLIDE 30

Recommendation Recommendation

Feasibility Study Feasibility Study

  • Industry standard
  • Recommended by Office of

Advancement

  • Risk mitigation
slide-31
SLIDE 31

Recommendation Recommendation

Feasibility Study - Uses Feasibility Study - Uses

  • Tool for fundraising
  • Setting up the SU for

success

  • Reducing turnover risk
slide-32
SLIDE 32

Recommendation Recommendation

Feasibility Study - Pr Feasibility Study - Process

  • cess

Tabulation and Analysis Develop Recommendations Preliminary Report Final Report Presentation to Board Planning Meeting Interviewee Identification Preparation of Materials Personal Interviews - Internal first

slide-33
SLIDE 33

Recommendation Recommendation

Feasibility Study - T Feasibility Study - Timeline imeline

  • 14-15 weeks
  • Possibly longer due to

Christmas season

  • Timeliness is a factor
slide-34
SLIDE 34

Recommendation Recommendation

Feasibility Study – Costs Feasibility Study – Costs

  • $39,000 plus GST and travel
  • $45,000 from Capital Reserve
  • Current total: $527,899
  • Repayment plan of $9,000 a

year for 5 years from

  • perating efficiencies
slide-35
SLIDE 35

Recommendation Recommendation

Feasibility Study – Deliverables Feasibility Study – Deliverables

  • All-encompassing report and

recommendations

  • Creation of a narrative
  • Feedback on material

creation

slide-36
SLIDE 36

Conclusion Conclusion

Aligns with V Aligns with Values alues

Plan for tomorrow Always keep moving

slide-37
SLIDE 37

Conclusion Conclusion

Aligns with Strategic Plan Aligns with Strategic Plan

  • 4a. Develop and

expand non-student revenue sources

slide-38
SLIDE 38

Conclusion Conclusion

Recommendation to Council Recommendation to Council

Release $45,000 from the Capital Reserve for the completion of a feasibility study.

slide-39
SLIDE 39

Questions?

Robyn Paches VP Opera*ons & Finance robyn.paches@su.ualberta.ca

slide-40
SLIDE 40