Hounslow Highways Spring Grove & Osterley Residents Association - - PowerPoint PPT Presentation

hounslow highways
SMART_READER_LITE
LIVE PREVIEW

Hounslow Highways Spring Grove & Osterley Residents Association - - PowerPoint PPT Presentation

Hounslow Highways Spring Grove & Osterley Residents Association meeting Tuesday 28 th February 2017 Timothy Hurley Roads & Pavements www.hounslowhighways.org What is included in the PFI? 2 Services Routine Maintenance of assets


slide-1
SLIDE 1

Hounslow Highways

Spring Grove & Osterley Residents Association meeting Tuesday 28th February 2017

Timothy Hurley Roads & Pavements

www.hounslowhighways.org

slide-2
SLIDE 2

What is included in the PFI?

2

slide-3
SLIDE 3

3

Services

  • Routine Maintenance of assets
  • Emergency and Winter Services
  • Street Cleansing
  • Illegal Waste Removal
  • Tree Maintenance and

Grass/Horticulture

  • Policy Setting and Highway Strategy
  • Management of Inventory
  • Highway Safety Inspections
  • Street Works – Permits and

Licenses

  • Environmental Education and

Management

  • Enforcement for Environment and

Highway offences

  • Management of Public Claims
  • Illegal Crossovers
slide-4
SLIDE 4

4

Condition Improvement Progress so far

Milestone 8 (4 Years) – Borough Wide Carriageways

  • 952 Schemes
  • 186 Km of roads

Footways

  • 822 Schemes
  • 205 Km of footways

Street Lighting

  • 14,357 new Street Lights replaced
  • 700 remaining lights to complete
slide-5
SLIDE 5

5

Progress across the borough

End of Year 4 (Milestone 8) Roads and Footway Improvements

  • The condition of roads and footways is measured every

year through detailed technical evaluation by a third-party survey organisation

  • The “gap” between current condition and the target is

represented by the Network Performance Gap (NPG)

  • The overall target for a compliant network is 0.5 NPG
  • The contract started at NPG of 4.58 and is reduced by

each new road or footway completed

  • At the end of Year 4 (Milestone 8) the NPG was 0.85
  • This represents a 81% improvement in overall condition

– ahead of the contract improvement profile

slide-6
SLIDE 6

6

  • The LBH road infrastructure asset value increased by £71 million to £778

million in the last financial year.

  • Road and Footway works continue through years 4&5 to achieve the

required level of compliance

  • Capital works will also take place in the following 20 years based on the

condition of the network each year

  • Day to day repairs that qualify for immediate action will continue to be

assessed and actioned.

  • Hounslow Highways remains responsible for all streets and their condition

through until 2037

Investment Programme

slide-7
SLIDE 7

7

Managing the Infrastructure

  • Highway Safety Inspections
  • Inventory Updates (269,284 assets)
  • Policy setting and Network Compliance Audit
  • Street Works – Licenses and Permits (LoPS)
  • Condition Surveys and specifications
slide-8
SLIDE 8

What is a Pothole ?

  • Hounslow Highways has adopted dimensional

definitions for potholes as part of the Safety Inspection Strategy and Plan

  • Response times and treatment of potholes is based on

importance of Carriageways, Footway, Cycle lanes and an assessment of risk

  • Having assessed and categorised the risk impact and

risk probability, the risk matrix is utilised to determine an appropriate response

8

slide-9
SLIDE 9

Potholes identified/ repaired by year 9

50 100 150 200 250 300

1 3 5 7 9 11 1 3 5 7 9 11 1 3 5 7 9 11 1 3 5 7 9 11 2013 2014 2015 2016 CW08 - CW: Pothole Linear (CW08 - CW: Pothole)

slide-10
SLIDE 10

10

When do we repair- Carriageways?

Table: Investigatory levels on Carriageways

Defect Type Investigatory level Crossings, Junctions and in or adjacent to the Kerb Other Locations on Link 1, 2, 3, and 4 Link 5 Pothole/Spalling 40mm depth 50mm depth 75mm depth Crowning 50mm depth 50mm depth 75mm depth Depression (area 2m2) 50mm 50mm 75mm Gap/Crack 20mm depth (20mm wide) 20mm depth (20mm wide) 30mm depth (20mm wide) Sunken and Raised Ironwork 20mm level difference 20mm level difference 25mm level difference Level Difference within Ironwork Framework 15mm 15mm 15mm

slide-11
SLIDE 11

11

Defect Type

Investigatory level

Place A & B Place C Place D Place E & PROW Hierarchy 1 Trip/Pothole 15mm depth 20mm depth 25mm depth 25mm depth Rocking Slab/Block 15mm vertical movement 20mm vertical movement 25mm vertical movement 25mm vertical movement Open Joint 20mm width x 200mm length (min depth 20mm) Tree Root Damage 15mm trip 20mm trip 25mm trip 25mm trip Sunken and Raised Ironwork 15mm level difference 20 mm level difference 25mm difference 25mm difference Dislodged Kerb 50mm horizontally 50mm horizontally 50mm horizontally 50mm horizontally Loose/Rocking Kerb 15mm vertically 20mm vertically 25mm vertically 25mm vertically Missing Kerb Yes

Table: Investigatory levels on Footways

When do we repair- Footways?

slide-12
SLIDE 12

12

Risk Matrix

Probability Impact Very Low (1) Low (2) Medium (3) High (4) Negligible (1) 1 2 3 4 Low (2) 2 4 6 8 Noticeable (3) 3 6 9 12 High (4) 4 8 12 16 Response Category Cat 2 Low (L) Cat2 Medium (M) Cat 2 High (H) Cat 1

Priority Risk Factor Response Priority 1 (Category 1 defect) 12 to 16 Make safe within 1 hour and complete temporary repair within 24 Hours, then complete a permanent repair within 28 days Priority 2 Cat2 H 8 to 11 Repair within 28 days Priority 3 Cat2 M 5 to 7 Repair within 56 days Priority 4 Cat 2 L 1 to 4 Repair during next available programme

slide-13
SLIDE 13

Works in Osterley & Spring Grove

13 2013-2016

  • No. RSL

Length (km) 109 23.5 CW 47 12.2 FW 62 11.3 2017

  • No. RSL

CW 11 FW 17

slide-14
SLIDE 14

Lighting in Osterley & Spring Grove

14

  • 2013 – 2016
  • Osterley + Spring Grove – 983 LED lighting points installed
  • 2017
  • 0 remaining - [Not including Heritage Lighting]
slide-15
SLIDE 15

Energy savings for the borough

  • HH have reduced the energy consumption for our Street Lighting assets by

55% since the contract started. HH are by far the leading London Borough in this aspect, and in turn we are reducing our carbon footprint.

slide-16
SLIDE 16

16

Tree Works

  • Current street tree stock is 11,398 trees
  • All street trees are surveyed every three years as part of a

rotational cycle of one third per year.

  • Survey used to establish maintenance requirement for each

tree.

  • Maintenance regime includes
  • Cyclical pruning
  • Clean Sweep
  • Large plane and lime tree maintenance
  • Felling and replanting Dead, Dying, Diseased and Dangerous
slide-17
SLIDE 17

17

Environment & Enforcement

slide-18
SLIDE 18

Flytipping

18

slide-19
SLIDE 19

19

What are we doing about?

slide-20
SLIDE 20

Working with the community

20

  • School visits
  • Community clean-up days
  • Graduates and apprenticeships
  • Volunteer programme – Lay

Assessors

  • Local workforce
  • Junior Citizens
  • Hounslow Business Awards
  • Enabling Enterprise
  • Joint task force
slide-21
SLIDE 21

Reporting Issues on Hounslow Highways website

21

  • Why is it important to report issues through our website?
  • 24/7 monitoring
  • Immediate response to Cat 1 hazards
  • Immediate assignment to the correct team/officer
  • Enquiries do not get lost
  • Customers get a reference number
  • Data allows us to monitor trends and know which services to provide
slide-22
SLIDE 22

Reactive Enquiries

22

slide-23
SLIDE 23

High Enquiry Areas

23

slide-24
SLIDE 24

24

slide-25
SLIDE 25

Lay Assessor Volunteers

25

  • Lay Assessor programme started November 2014
  • 10 Lay Assessors (each representing a ward)
  • Site visits/ Monthly coffee mornings
  • Additional contact i.e. user acceptance testing for website, meetings with the IC

(who signs off our schemes)

  • Always looking for new ideas to refresh the programme
  • Interested people should email businessmanagement@hounslowhighways.org
slide-26
SLIDE 26

Questions?

26