HORSESHOE DESIGN-BUILD PROJECT TEXAS DEPARTMENT OF TRANSPORTATION - - PowerPoint PPT Presentation

horseshoe design build project
SMART_READER_LITE
LIVE PREVIEW

HORSESHOE DESIGN-BUILD PROJECT TEXAS DEPARTMENT OF TRANSPORTATION - - PowerPoint PPT Presentation

HORSESHOE DESIGN-BUILD PROJECT TEXAS DEPARTMENT OF TRANSPORTATION DALLAS DISTRICT TexITE Meeting June 8, 2012 HORSESHOE DESIGN-BUILD PROJECT OUTLINE Background: Project Pegasus Breakout Project: Horseshoe Proposed Project


slide-1
SLIDE 1

HORSESHOE DESIGN-BUILD PROJECT

TexITE Meeting June 8, 2012

TEXAS DEPARTMENT OF TRANSPORTATION – DALLAS DISTRICT

slide-2
SLIDE 2

HORSESHOE DESIGN-BUILD PROJECT

 Background: Project Pegasus  Breakout Project: Horseshoe  Proposed Project  Purpose & Need  Project Challenges  Work Complete/Underway  Schedule

OUTLINE

slide-3
SLIDE 3

HORSESHOE DESIGN-BUILD PROJECT

  • IH 30 from Sylvan Avenue to IH 45
  • IH 35E from Empire Central Drive (North of SH 183) to 8th Street

BACKGROUND: PROJECT PEGASUS

slide-4
SLIDE 4

Houston Street Viaduct’s Location in Mixmaster Interchange

Jefferson Street Viaduct

Houston Street Viaduct

IH 35E

N

slide-5
SLIDE 5

HORSESHOE DESIGN-BUILD PROJECT

COMPONENTS OF PROJECT PEGASUS: LOWER STEMMONS

slide-6
SLIDE 6

HORSESHOE DESIGN-BUILD PROJECT

COMPONENTS OF PROJECT PEGASUS: CANYON

slide-7
SLIDE 7

HORSESHOE DESIGN-BUILD PROJECT

COMPONENTS OF PROJECT PEGASUS: HORSESHOE

slide-8
SLIDE 8

HORSESHOE DESIGN-BUILD PROJECT

 Background: Project Pegasus  Breakout Project: Horseshoe  Proposed Project  Purpose & Need  Project Challenges  Work Complete/Underway  Schedule

OUTLINE

slide-9
SLIDE 9

HORSESHOE DESIGN-BUILD PROJECT

BREAKOUT PROJECT: HORSESHOE

slide-10
SLIDE 10

HORSESHOE DESIGN-BUILD PROJECT

 Replace I-30 & I-35E bridges and connecting

roadways that cross the Trinity River

 Upgrade outdated roadway geometry  Construct additional lanes  Margaret McDermott Bridges

HORSESHOE: PROPOSED PROJECT

slide-11
SLIDE 11

HORSESHOE DESIGN-BUILD PROJECT

HORSESHOE: PROPOSED PROJECT

slide-12
SLIDE 12

HORSESHOE DESIGN-BUILD PROJECT

 Background: Project Pegasus  Breakout Project: Horseshoe  Proposed Project  Purpose & Need  Project Challenges  Work Complete/Underway  Schedule

OUTLINE

slide-13
SLIDE 13

HORSESHOE DESIGN-BUILD PROJECT

 I-30 & I-35E carry over 460,000 vehicles per weekday  Rated in the top 20 most congested roadways in Texas  Outdated roadway geometry  Bridge deterioration  Increasing costs to maintain & repair

HORSESHOE: PURPOSE & NEED

slide-14
SLIDE 14

HORSESHOE DESIGN-BUILD PROJECT

2010 TEXAS TOP 20 CONGESTED ROADWAYS

12TH: I-35E From SH 183 to I-30 29TH: I-30 From Hampton to I-35E 16TH: I-35E From US 67 to I-30 15TH: I-30 From I-35E to Loop 12

slide-15
SLIDE 15

HORSESHOE DESIGN-BUILD PROJECT

USA Today, September 9, 2000

HORSESHOE: OUTDATED ROADWAY GEOMETRY

slide-16
SLIDE 16

HORSESHOE DESIGN-BUILD PROJECT

40 45 50 55 60 65 70 2002 2004 2006 2008 2010

IH 30 WB IH 30 EB IH 35E SB IH 35E NB

Sufficiency Rating Inspection Years

I-30 AND I-35E: BRIDGE SUFFICIENCY RATINGS

slide-17
SLIDE 17
slide-18
SLIDE 18

HORSESHOE DESIGN-BUILD PROJECT

I-30 BRIDGE PICTURES

slide-19
SLIDE 19

HORSESHOE DESIGN-BUILD PROJECT

I-35E NB BRIDGE PICTURES

slide-20
SLIDE 20

HORSESHOE DESIGN-BUILD PROJECT

 Background: Project Pegasus  Breakout Project: Horseshoe  Proposed Project  Purpose & Need  Project Challenges  Work Complete/Underway  Schedule

OUTLINE

slide-21
SLIDE 21

HORSESHOE DESIGN-BUILD PROJECT

 Maintaining traffic during construction  Construction of the Margaret McDermott Bridges  Reconstruction of 2 major freeway interchanges  Crossing of the Trinity River Levees  Accommodating the future Trinity Lakes Project

HORSESHOE: PROJECT CHALLENGES

slide-22
SLIDE 22

HORSESHOE DESIGN-BUILD PROJECT

Houston Street Viaduct’s Location in Mixmaster Interchange

Jefferson Street Viaduct

Houston Street Viaduct

IH 35E

N

slide-23
SLIDE 23

HORSESHOE DESIGN-BUILD PROJECT

HORSESHOE: Margaret McDermott Bridges

slide-24
SLIDE 24

HORSESHOE DESIGN-BUILD PROJECT

 Hike/Bike facilities along the IH 30 eastbound

and westbound frontage roads

 Designed and engineered to 100% by Santiago

Calatrava, LLC

 Under contract with the City of Dallas  Built by the Design-Build Contractor

HORSESHOE: Margaret McDermott Bridges

slide-25
SLIDE 25

HORSESHOE DESIGN-BUILD PROJECT

HORSESHOE: Margaret McDermott Bridges

slide-26
SLIDE 26

HORSESHOE DESIGN-BUILD PROJECT

CROSSING THE TRINITY RIVER LEVEES

slide-27
SLIDE 27

HORSESHOE DESIGN-BUILD PROJECT

ACCOMMODATING FUTURE TRINITY LAKES PROJECT

slide-28
SLIDE 28

HORSESHOE DESIGN-BUILD PROJECT

 Background: Project Pegasus  Breakout Project: Horseshoe  Proposed Project  Purpose & Need  Project Challenges  Work Complete/Underway  Schedule

OUTLINE

slide-29
SLIDE 29

HORSESHOE DESIGN-BUILD PROJECT

HORSESHOE: WORK COMPLETE/UNDERWAY

 Pegasus FONSI complete July 2005  Horseshoe FONSI expected December 2012  I-30: 30% design complete  I-35E: 30% design complete  Commission approved funding  Commission approval to “Design-Build”

slide-30
SLIDE 30

HORSESHOE DESIGN-BUILD PROJECT

WORK COMPLETE: APPROVED FUNDING

slide-31
SLIDE 31

HORSESHOE DESIGN-BUILD PROJECT

 Background: Project Pegasus  Breakout Project: Horseshoe  Proposed Project  Purpose & Need  Project Challenges  Work Complete/Underway  Schedule

OUTLINE

slide-32
SLIDE 32

HORSESHOE DESIGN-BUILD PROJECT

 Issued RFQ – December 9, 2011  Shortlist Announced- March 29, 2012  Draft RFP for Industry Review- April 26, 2012  Final RFP- July 3, 2012  Proposals Due- September 25, 2012  Conditional Award- October 25, 2012  USACE 408 permit Fall 2012 (estimated)  Environmental Assessment – December 2012

(estimated)

 Design-Build Contract Executed- January 2013  Begin Construction- Spring 2013

HORSESHOE: SCHEDULE

slide-33
SLIDE 33

HORSESHOE DESIGN-BUILD PROJECT

slide-34
SLIDE 34

HORSESHOE DESIGN-BUILD PROJECT

Ceason Clemens, P.E. Dallas Horseshoe Project Deputy Project Engineer

QUESTIONS