highlights of ti2 lhc synchronization test with beam
play

Highlights of TI2-LHC Synchronization Test with Beam M. Lamont and - PowerPoint PPT Presentation

CMS Commissioning Meeting August 15 th , 2008 CERN - Geneva (CH) Highlights of TI2-LHC Synchronization Test with Beam M. Lamont and S. Redaelli on behalf of the OP team Outline Introduction: goals / layouts Beam and magnet availability


  1. CMS Commissioning Meeting August 15 th , 2008 CERN - Geneva (CH) Highlights of TI2-LHC Synchronization Test with Beam M. Lamont and S. Redaelli on behalf of the OP team

  2. Outline • Introduction: goals / layouts • Beam and magnet availability • List of “Firsts” • Detailed beam measurements • Conclusions S. Redaelli, CMS Comm, 12-08-2008 2

  3. Acknowledgments Hardware Commissioning Coordination (HCC) Survey group Access System team Cryogenics Magnets [PO, MPP, QPS, PIC...] Accelerator systems: Injection team, beam instrumentation, (BPM, BLM, BCT, screens ...), beam interlock system, radio-protection, collimators, controls ... Contributions of many people who actively participated to the first LHC beam studies. Comprehensive overview of achieved results at http://cern.ch/lhc-injection-test/meetings/120808/injection-test-120808.htm S. Redaelli, CMS Comm, 12-08-2008 3

  4. Layout of beam path D3 D4 Q6.L D4 D3 Q5.L Q4.L Q4.R Q5.R Q6.R DS 500 4.5 Beam 1 400 3 ! y ! x Dispersion function [ m ] D x ! functions [ m ] 300 1.5 200 0 100 -1.5 0 -3 6.5 6.6 6.7 6.8 6.9 7 Longitudinal coordinate, s [ km ] (1) Commission end of TI2 (beam on TDI on IP2-left) (2) Steer beam up to IR3 (3) Stop beam on the collimators (5 Carbon primary+secondary colls; TI2 4 Tungsten absorbers) S. Redaelli, CMS Comm, 12-08-2008 4

  5. Details of injection region TI2 B. Goddard Septum (MSI), beam offset in Q5, kicker (MKI) Beam instrumentation: beam position and current monitors, screens TDI collimator to protect ALICE during injection steering S. Redaelli, CMS Comm, 12-08-2008 5

  6. Goals of beam test M. Lamont: http://lhc-injection-test.web.cern.ch/lhc%2Dinjection%2Dtest/ S. Redaelli, CMS Comm, 12-08-2008 6

  7. Beam on the injection region screens (2) (1) (3) (4) S. Redaelli, CMS Comm, 12-08-2008 7

  8. Beam on screen at IR3 (first shot!) S. Redaelli, CMS Comm, 12-08-2008 8

  9. Extracted beams (9 th to 11 th Aug.) I bunch [ 1e10 ] First arc First recovery First beam- First shot aperture First beam after pre-cycle induced on TDI First access scans through an quench during beam LHC arc operation S. Redaelli, CMS Comm, 12-08-2008 9

  10. Availability of cryo-magnets Weekend of the beam tests Current in dipoles of Pre-cycles (4655A) ARC23 Quench Also sector 56 kept Injection plateau (757A) at E inj throughout the weekend (connected to energy tracking system) S. Redaelli, CMS Comm, 12-08-2008 10

  11. Outline • Introduction: goals / layouts • Beam and magnet availability • List of “Firsts” • Detailed beam measurements • Conclusions S. Redaelli, CMS Comm, 12-08-2008 11

  12. First trajectory (after a few corrections) J. Wenninger et al. Beam position monitors (BPM’ s) triggered at the first passage (asynchronous acq.) Orbit correction to ± 10 mm in both planes within a few shots! S. Redaelli, CMS Comm, 12-08-2008 12

  13. First optimized trajectory J. Wenninger et al. Peak-to-peak: ± 3 mm (LHC design specs: ± 4mm!) S. Redaelli, CMS Comm, 12-08-2008 13

  14. First aperture scan... LHC Project Report 44 (1996) Indeed, we quenched a main dipole in the region Q8 → Q7 left of IP3 with a pilot " The intensity of the bunch shall therefore not be much larger than 3 10^9 protons. " beam of less than 4 x 10 9 p!! S. Redaelli, CMS Comm, 12-08-2008 14

  15. ... and first beam-induced quench! Transition to normal conducting state triggered by quench Voltage heaters Threshold of Quench Protection System (QPS): 100 mV over 10 ms 200 ms Extracted from QPS post-mortem buffer S. Redaelli, CMS Comm, 12-08-2008 15

  16. First beam loss analysis During “gentle” Quad. quench threshold (B1) aperture scans: Dipole quench threshold (B2) Up to a factor 4 higher then calculated limit, but did not quench! LHC beam loss monitors BLM measurements B. Dehning et al. Room for improvement/fine tuning on the definition of quench thresholds! Comprehensive collection of data! S. Redaelli, CMS Comm, 12-08-2008 16

  17. First solution Baseline: pilot “probe” beams of ~5x10 9 protons to trigger asynchronous BPM acquisitions (no fine timing) By reducing the injected beam intensity, we established that the BPMs can trigger also at <2 x 10 9 protons! More margin during commissioning phases! M. Lamont, R. Jones, PSB operations, at al. S. Redaelli, CMS Comm, 12-08-2008 17

  18. Outline • Introduction: goals / layouts • Beam and magnet availability • List of “Firsts” • Detailed beam measurements • Conclusions S. Redaelli, CMS Comm, 12-08-2008 18

  19. Injection aperture scans Probe the aperture in the injection region Aperture model by inducing beam oscillations at the end of TI2. Simulated beam trajectories B. Goddard, I. Agapov et al. Bottleneck in injection region found, now fixed! S. Redaelli, CMS Comm, 12-08-2008 19

  20. Arc aperture measurements MEASURED beam trajectories Horizontal arc aperture of 18-20 mm!! Vertical limitation at Q8/Q7-L3 of about 10 mm. S. Redaelli, CMS Comm, 12-08-2008 20

  21. Understanding of optics model IP2 ARC-23 IP3 J. Wenninger, K. Fuchsberger Matrix response measurements by using ~50% of the correctors Check BPM/corrector polarities (only 1 wrong BPM found) BLM calibrations: good within 15-20% Compare with design optics model Slight mis-match found close to IP3-left, under investigation S. Redaelli, CMS Comm, 12-08-2008 21

  22. Loss response at collimators A5R3 TCP.6L3 TCSG.5L3 TCSG.4R3 B5R3 TCLA ’ s D3 D4 Q6.L D4 D3 Q5.L Q4.L Q4.R Q5.R Q6.R DS 500 4.5 Beam 1 400 3 ! y ! x Dispersion function [ m ] D x ! functions [ m ] 300 1.5 200 0 100 -1.5 0 -3 6.5 6.6 6.7 6.8 6.9 7 Longitudinal coordinate, s [ km ] 20 LHC collimators on the beam path (7 in TI2 + 4 in IP2 + 9 in IP3) First BLM response measurements in IR3 Carbon (TCP/TCSG ’ s) vs Tungsten (TCLA ’ s) response S. Redaelli, CMS Comm, 12-08-2008 22

  23. Conclusions Access system looks good Very good condition during the weekend CRYO, QPS, PIC, BIS, power converters Aperture looks very good No significant limitations found in the arc 23 Bottle neck in injection region now fixed No time to measure the insertions Optics looks good Small phase advance error in arc Something suspicious left of 3. Instrumentation looks very good BPMs in asynchronous mode BLMs up and running from first shot Screens etc Magnet model looks good Controls/Databases looks good (some features…) Beam transfer, RF synchronization looks good S. Redaelli, CMS Comm, 12-08-2008 23

  24. Outlook Results of first beam tests are very encouraging... ...but there is still a long way to go! Next challenge in one week! A journey of a thousand miles begins with a single step! Lao-tzu, The Way of Lao-tzu Chinese philosopher (604 BC - 531 BC) TI8 S. Redaelli, CMS Comm, 12-08-2008 24

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend