Kenneth Hennon CleanAir Engineering Performance Group Clean Coal International Conference November 2013
Heat Rejection Cycle Testing Kenneth Hennon CleanAir Engineering - - PowerPoint PPT Presentation
Heat Rejection Cycle Testing Kenneth Hennon CleanAir Engineering - - PowerPoint PPT Presentation
Heat Rejection Cycle Testing Kenneth Hennon CleanAir Engineering Performance Group Clean Coal International Conference November 2013 Overview Heat Rejection Cycle Testing Combining Tests Water Flow Rate Cost of Malperformance
2
Overview Heat Rejection Cycle Testing
- Combining Tests
- Water Flow Rate
- Cost of Malperformance
- Case Studies
- Cooling tower thermal performance
testing
- Condenser cleanliness testing
- Pump performance through circulating
water flow rate determination
- Evaluation of the component impact on
turbine back pressure
Heat Rejection Cycle Testing
4
Why Test? ECONOMICS
- Thermal efficiency
– A 650 MW – 85 percent load factor – Fuel costs $50/ton
- Saves $950,000 in the first
year by improving heat rate by only one percent and reduces emissions.
50,000 gpm 57% of New Acceptance Tests >50,000 gpm Yielded Tower Capability
- f 100% or greater
Why Test? 2011 Test Results
6
40 50 60 70 80 90 100 110 120 130 140 150 160 10 100 1,000 10,000 100,000
Water Flow Rate (l/s) Test Capability -- % Design Flow
50,000 gpm
Why Test? 2010 Test Results
22% of New Acceptance Tests >50,000 gpm Yielded Tower Capability
- f 100% or greater
40 50 60 70 80 90 100 110 120 130 140 150 160 10 100 1,000 10,000 100,000
Water Flow Rate (l/s) Test Capability -- % Design Flow
50,000 gpm 38% of New Acceptance Tests >50,000 gpm Yielded Tower Capability
- f 100% or greater
Why Test? 2009 Test Results
Why Test?
2008 COOLING TOWER THERMAL TESTS ACCEPTANCE TESTS -- NEW COOLING TOWERS
40 50 60 70 80 90 100 110 120 130 140 150 160 10 100 1,000 10,000 100,000
Water Flow Rate (l/s) Test Capability -- % Design Flow
2,000 l/s (32,000 gpm) 6 out of 13 passed (46%)
Component Performance and CO2
Change in Component Performance Change in HR (BTU/kWh) Annual HR Cost Increase in CO2 (TPY) 10% Condenser Cleanliness 30 $330,000 17,000 10% Cooling Tower Capability 15 $165,000 8,500 10% Circulating Water Flow 20 $220,000 11,400
10
Component Performance and CO2
Change in Component Performance Change in HR (BTU/kWh) Annual HR Cost Increase in CO2 (TPY) 10% Condenser Cleanliness 30 $330,000 17,000 10% Cooling Tower Capability 15 $165,000 8,500 10% Circulating Water Flow 20 $220,000 11,400
11
Component Performance and CO2
Change in Component Performance Change in HR (BTU/kWh) Annual HR Cost Increase in CO2 (TPY) 10% Condenser Cleanliness 30 $330,000 17,000 10% Cooling Tower Capability 15 $165,000 8,500 10% Circulating Water Flow 20 $220,000 11,400
Component Performance and CO2
Change in Component Performance Change in HR (BTU/kWh) Annual HR Cost Increase in CO2 (TPY) 10% Condenser Cleanliness 30 $330,000 17,000 10% Cooling Tower Capability 15 $165,000 8,500 10% Circulating Water Flow 20 $220,000 11,400
13
Component Performance and CO2
Clean Air Engineering,
Change in Component Performance Cost in CO2 Allowances Annual HR Cost Total Annual Cost 10% Condenser Cleanliness $57,000 $330,000 $387,000 10% Cooling Tower Capability $29,000 $165,000 $194,000 10% Circulating Water Flow $39,000 $220,000 $259,000
Major Test Parameters
- Water Flow Rate
- Hot Water Temperature
- Cold Water Temperature
- Inlet Wet Bulb Temperature
- Fan Motor Power
Cooling Range Approach
Water Flow Instrumentation
- Unreinforced – risers
- Reinforced – large
pipes
Water Flow Rate Measurements
- Dye dilution can be used where
pitot tube access is limited
- Good applications for once-
through systems
- Can be used for closed loop
systems with large volumes
Alternative Flow Measurement Techniques
Dye Dilution Ultrasonic ???
18
Cooling Tower Performance Curves
Cooling Tower Performance Curves
- Water Flow Rate
- Wet Bulb Temp
- Hot Water Temp
- Cold Water Temp
- Fan Motor Power
Fan Blade Pitch
- On a historical basis, over 30% of
the tested cooling towers have fans that are drawing significantly less power than designed
- The loss of airflow equates to a
5% loss in operating cooling tower capability
- $82,500/yr in HR & 4,250 TPY
CO2
21
1/6 H H 1/2 H 5/6 H
22
- In flowing channel – matrix of temperature sensors are
used
Cold Water Hot Water Water Cooling Tower Circulating Water Pump Condenser Steam Fan Drift
Heat Rejection Cycle
Hot Water Temp at cooling tower is the condenser discharge temp
25
Water Flow Rate
– Key to heat rejection cycle
Water Flow Rate Measurements
- Pitot Tube, manometer,
accessories
- Water flow rate can be
measured in pipes up to 20ft in diameter
27
Condenser performance (cleanliness) has the greatest impact
- n heat rejection
cycle. Relatively easy to address cleanliness issues – air infiltration.
Clean Air Engineering,
Case Study 1 AC Power – Colver, PA
- 110 MW waste coal
fired plant
- Single Pressure
Condenser
- Four cell counterflow
tower
- Two circulating pumps
Clean Air Engineering,
Case Study 1
Test Parameter Unit Design Test Water flow rate gpm 57,000 56,873 Hot water temperature F 101.0 80.0 Cold water temperature F 81.0 59.8 Wet bulb temperature F 72.0 36.2 Cooling range F 20.0 20.5 Fan power hp 192.4 246.7 Capability % 100 98 Cold water temperature deviation at design conditions °F 0.3
Case Study 1
Parameter Units Design Test Heat duty Btu/hr 4.94x108 5.76x108 Steam condensed lbm/hr 522,520
- Condensing steam pressure
InHg 2.3 1.48 Condensing steam temperature °F 105.85 91.3 Circulating water flow Gpm 57,000 56,873 Inlet water temperature °F 91.0 59.5 Outlet water temperature °F 101.0 80.0 Cleanliness 85% 67%
Case Study 1 AC Power – Colver, PA
- Cooling tower
performance – OK
- Pump performance – OK
- Condenser – significant
issues
- Other plant
instrumentation issues
Comparison of 67% to 85% Condenser Cleanliness
10 20 30 40 50 60 70 54 59 64 69 74 79 Inlet Water Temperature (F) Change in Heat Rate (Btu/kWhr) 32 39.7 47.4 55.1 62.8 70.5 Wet Bulb Temperature (F)
Case Study 1
55 Btu/kWh increase in HR due to Condenser Cleanliness at 70.5 WB
33
Predicted Pressure
1.0 1.5 2.0 2.5 3.0 3.5 30 40 50 60 70 80 90 Wet Bulb Temperature (F) Predicted Pressure (InHg) Current Cooling System Performance 100% Cooling Tower 85% Cleanliness
Case Study 1
.3 InHg backpressure increase due to Condenser Cleanliness
Case Study 2 Hope Creek NGS
- 1220 MW nuclear
- Natural draft CF tower
- 15% uprate approved
- Single pressure
condenser
- Four circulating water
pumps
35
Case Study 2
Test 1 Test 2 Test Parameter Unit Design 11:20-12:20 12:20-13:20 Water Flow Rate gpm 552,000 571,736 571,736 Hot Water Temperature F 119.0 110.9 111.1 Cold Water Temp F 90.0 86.7 87.2 Wet Bulb Temperature F 76.0 61.8 62.2 Dry Bulb Temperature F 87.3 71.4 71.4 Barometric Pressure In Hg 29.92 29.86 29.86 Cooling Range F 29.0 24.2 23.9 Relative Humidity % 60 58 60 Wind Speed mph N/A 7.6 4.8 Capability % 100 76 75 Cold Water Temperature Deficit °F 4.6 4.8
Case Study 2
Parameter Units Value Number of units 2 Heat duty Btu/hr 7726x106 Steam condensed lbm/hr 7.926x106 Condensing steam pressure inHg 4.56 Condensing steam temperature °F 130.3 Circulating water flow gpm 552,000 Inlet water temperature °F 92.0 Outlet water temperature °F 120.0 Cleanliness 64%
37
Case Study 2 Hope Creek NGS
- Cooling tower – significant
issues
- Condensers performance- OK
- Circulating flow rate - OK
Expected Condenser Pressure
2.00 2.50 3.00 3.50 4.00 4.50 5.00 40 50 60 70 80 Wet Bulb Temperature (F) Condenser Pressure (inHg) Current Cooling Tower Perf 100% Cooling Tower
Case Study 2
.6 InHg backpressure increase at 75F WB
39
Predicted Power
1200 1210 1220 1230 1240 1250 1260 1270 40 45 50 55 60 65 70 75 80 Wet Bulb Temperature (F) Predicted Power (MW) Current Cooling System Performance 100% Cooling Tower 70% Cleanliness
Case Study 2
14 MW loss due to cooling tower at 75F WB About 3 MW loss due to condenser at 75F WB
Planning a performance test begins with defining its
- bjectives:
- The validation of contractual guarantees for a new
- r modified plant,
- Diagnostic tests to identify or quantify problems
- Establish a performance benchmark against which
future performance can be contrasted
Planning for a Test
Heat Rejection Cycle Testing
- Solid tool for effective allocation of O&M
- Quantifying impact and payback
– Some problems are easy\inexpensive to fix
- Complements other plant test programs
Any Questions?
43