Group Meeting #2 >Welcome Mittagong RSL 8 October 2018 Agenda - - PowerPoint PPT Presentation

group
SMART_READER_LITE
LIVE PREVIEW

Group Meeting #2 >Welcome Mittagong RSL 8 October 2018 Agenda - - PowerPoint PPT Presentation

Berrima Colliery - Closure Working Group Meeting #2 >Welcome Mittagong RSL 8 October 2018 Agenda 1. Welcome and Apologies 2. Review of minutes & actions 3. Terms of Reference 4. Groundwater storage volume 5. Water Quality Trends and


slide-1
SLIDE 1

Berrima Colliery - Closure Working Group Meeting #2

Mittagong RSL 8 October 2018

>Welcome

slide-2
SLIDE 2

Titlefefefefeffff4g45g4545

Agenda

  • 1. Welcome and Apologies
  • 2. Review of minutes & actions
  • 3. Terms of Reference
  • 4. Groundwater storage volume
  • 5. Water Quality Trends and Preliminary Macroinvertebrate Comments
  • 6. EPA Presentation – Ecotoxicology Study
  • 7. Bulkhead Seals Explanation
  • 8. EPL/MOP Updates
  • 9. Communications Plan

10.Loch Catherine Update 11.General business 12.Next meeting

slide-3
SLIDE 3

Titlefefefefeffff4g45g4545

Welcome - CWG Representatives, Apologies & Guests

  • Boral - Fabio Colusso, Greg Johnson, David Spears,
  • Resource Regulator - Greg Kininmonth, Will Mitry
  • Environment Protection Authority - William Dove, Andrew Couldridge
  • WaterNSW - Ravi Sundaram
  • Wingecarribee Shire Council - Barry Arthur (apologies), Proxy?
  • Western Sydney University - Dr Ian Wright
  • Community - Clive West, Alan Lindsay, Graham Kelly, Ray Nolan, Julian

Brophy

  • Independent chair - Brad Mullard
  • Minute taker – Rob Byrnes
  • Guest - Pamela Klioufis
slide-4
SLIDE 4

Titlefefefefeffff4g45g4545

Review of Minutes – suggested amendments

slide-5
SLIDE 5

Titlefefefefeffff4g45g4545

Review of Actions

  • CWG Terms of Reference and that it is not the only way Boral will engage with the Community
slide-6
SLIDE 6

Titlefefefefeffff4g45g4545

Terms of Reference

Minor change to clarify that the CWG will not be the only way Boral engages with the Community.

slide-7
SLIDE 7

Titlefefefefeffff4g45g4545

Estimated volume of water contained in the workings

548ML (Based on: Mine ceasing discharge on 1/09/2015 and free draining on 21/03/2016. 203 days X 2.7ML = 548ML)

There was also a question in relation to the size of the mine void in total: 5.5 million m2 x 2.2 m (seam height) x 0.4 (% recovery) = 4.8 Million cubic metres This equates to around 7 Million tonnes (using SG of 1.45). Or 4,800 ML if all the void could be filled with water, which wouldn’t happen

slide-8
SLIDE 8

Titlefefefefeffff4g45g4545

The underground treatment was installed in 3 stages from early December 2017 until mid January 2018

slide-9
SLIDE 9

Titlefefefefeffff4g45g4545

Site and surrounding environment

slide-10
SLIDE 10

Titlefefefefeffff4g45g4545

Discharge Volumes

  • Additional pumping commenced

early August 2018

  • Water level has now dropped 800-

900mm

  • Sufficient level to install bulkheads
  • Additional pumping has ceased and

will revert to likely levels of 2.7ML average

slide-11
SLIDE 11

Titlefefefefeffff4g45g4545

Water Quality Trends - pH & EC

slide-12
SLIDE 12

Titlefefefefeffff4g45g4545

Water Quality Trends - Iron and Manganese

slide-13
SLIDE 13

Titlefefefefeffff4g45g4545

Water Quality Trends - Nickel and Zinc

slide-14
SLIDE 14

Titlefefefefeffff4g45g4545

Water Quality Trends along the treatment path - Iron example

  • 400 D12 Sump - Pump

pick up location

  • 400 C8 - After

aeration, treatment through lime bed and filtered through goaf

  • Adit Discharge - V -

Notch sample

slide-15
SLIDE 15

Titlefefefefeffff4g45g4545

Macroinvertebrate study update - Preliminary findings

Based on (two sampling occasions in Autumn 2018) similar story to what was observed previously (2017), although thorough analysis not been completed at this stage.

  • There was a loss of sensitive order mayflies (families Baetidae, Caenidae and Leptophlebiidae) and riffle beetle Elmidae upto

1km d/s of the adit.

  • Stonefly Gripopterygidae was observed to be impacted 100m downstream (in 2017), however at 300-500m d/s this was not as

evident and appears to have recovered 500m d/s.

  • There was some caddis missing (Philopotamidae) 500m d/s however they were present in good numbers 1km d/s.
  • In general there appears to be an impact up to 1km downstream, however the macroinvertebrate fauna appear to be recovering

at this distance downstream.

  • At 2km downstream the aquatic fauna appears to have fauna that were missing at sites 500m d/s and 1km d/s and I suspect

closer to upstream reference condition.

slide-16
SLIDE 16

Titlefefefefeffff4g45g4545

EPA Presentation – Ecotoxicology Assessment

slide-17
SLIDE 17

Titlefefefefeffff4g45g4545

Interim Sealing Plan - Location in respect of workings

slide-18
SLIDE 18

Titlefefefefeffff4g45g4545

Bulkhead Seal design - Explained

slide-19
SLIDE 19

Titlefefefefeffff4g45g4545

Environmental Protection Licence/ Mine Operations Plan Updates

EPL 608

  • Background - Special Condition R3 was added to the EPL late last year as a means to monitor the

performance of the underground treatment trial. The condition requires water quality summary reports to discuss effectiveness of the trial every 2 - 6 months and annual scientific reports including sediment and macroinvertebrates due annually on 31 Jan 2019 and 31 January 2020.

  • Boral difficulties

○ The Special Conditions were agreed prior to the installation of the complete system. ○ The full treatment system was not operational until mid January 2018. ○ Weather and other conditions (bushfire) can vary time of month sampling ○ Laboratory results can take 7+ days from sampling to be received ○ Macroinvertebrate numbers even longer ○ Time required to analyse and assess trends

  • Administrative request submitted to the EPA to vary submission dates by 6 weeks

“to allow more time for the licensee's consultants to complete and synchronise the in-situ water quality, sediment and macro- invertebrate sampling and report preparation as required in the Performance Monitoring Program”.

slide-20
SLIDE 20

Titlefefefefeffff4g45g4545

Environmental Protection Licence/ Mine Operations Plan Updates

MOP - Stage 1 Mine Closure Plan Background - The current approved closure plan dated January 2018 excludes detail on the proposed

  • bulkheads. Post the last CWG Boral provided the Resources Regulator a letter update on the bulkheads as

an attachment to the Stage 1 Plan.

  • The RR requested feedback from Water NSW and the NSW EPA.
  • The RR also requested evidence from Mine Safety they were satisfied with proposed designs
  • WaterNSW and the EPA requested how waters will be monitored during and post installation of

bulkheads. Boral Actions

  • Boral has agreed to an updated sampling plan that will be included in a letter amendment to the

MOP.

  • Once the final bulkhead designs are finalised, Boral will further consult with Mine Safety and provide

correspondence with the RR

slide-21
SLIDE 21

Titlefefefefeffff4g45g4545

Communication Plan - Workshop

Pamela Klioufis

slide-22
SLIDE 22

Titlefefefefeffff4g45g4545

Loch Catherine Update

slide-23
SLIDE 23

Titlefefefefeffff4g45g4545

General business

slide-24
SLIDE 24

Titlefefefefeffff4g45g4545

Next meeting date

Proposing: Monday 11 February 2019 9am – 1pm Location – Berrima Colliery (including a pit top site inspection)

slide-25
SLIDE 25