Grindleford Pavilion Development GRINDLEFORD PAVILION DEVELOPMENT WORK STARTS 26 MARCH OUTLINE OF SCHEME Grindleford Pavilion Development EXTENSION HERE EXISTING PAVILION OUTLINE OF SCHEME Inside Grindleford Pavilion Development
Grindleford Pavilion Development
OUTLINE OF SCHEME
EXTENSION HERE
EXISTING PAVILION
Grindleford Pavilion Development
FUNDS LIMIT WHAT WE CAN DO
- INSIDE:
- Youth Room (2nd meeting room)
- Level Access Storage Rooms
- Disabled Accessible WC
- Outside Code Access WC
- New Main Entrance Door
with covered porch
- New Entrance Lobby
- New Boiler for whole building
- New Fire alarm / detection system
OUTLINE OF SCHEME Inside
Grindleford Pavilion Development
OUTLINE OF SCHEME Outside
FUNDS LIMIT WHAT WE CAN DO - OUTSIDE:
- New retaining walls
- New Front Entrance Area
- Regraded ramps
- New planting beds
- Building works to enable Platform Lift
installation later
Grindleford Pavilion Development
CONSTRUCTION AREAS
CONSTRUCTION AREA
Grindleford Pavilion Development
ACCESS ARRANGEMENTS
X
access blocked
Start
- f
Construction
Grindleford Pavilion Development
ACCESS ARRANGEMENTS
X
access blocked
Later in Construction
Grindleford Pavilion Development
ACCESS ARRANGEMENTS
EXISTING FACILITIES AVAILABLE ** FOR USE DURING CONSTRUCTION:
- Main Club Room (although some area may be shuttered off)
- Kitchen
- Inside WC / Washrooms
- Shower Rooms
- Undercroft storage
- Outside shed storage
** Break-ins for services may interrupt utilities for short periods
Grindleford Pavilion Development
ACCESS ARRANGEMENTS
CONSTRUCTION AREA
Ramp
Grindleford Pavilion Development
PARKING
CONSTRUCTION AREA CONST. VANS ACCESS TO CHILDREN’S PLAY AREA NO PARKING IN CENTRE OF CAR PARK DURING WORKING HOURS
Grindleford Pavilion Development
PARKING
PARKING LIMITATIONS:
- Half car park being used for construction compound & access
- NO Parking in the middle of the car park during working hours
- Severely LIMITED parking
- In Summer, if dry, we will try to add some parking space on field
(no parking on field until authorised to do so)
Grindleford Pavilion Development
CHILDREN’S PLAY AREA
ACCESS TO CHILDREN’S PLAY AREA
Grindleford Pavilion Development
MAJOR EVENTS
SHOULD BE POSSIBLE - With Restrictions:
- Severely LIMITED parking in Car Park
- Field fully available
- Parking on field subject to weather conditions
- Pavilion available with restrictions:
- No outside toilet - consider hiring “Portaloos”
- Club Room space may be curtailed
- Existing inside WC’s operational
- Kitchen should be available
- Outside water tap not available
- Contractor aware and will try to work around our major events
Grindleford Pavilion Development
HEALTH & SAFETY
- Updated Risk Assessments have been undertaken for Pavilion &
External Areas.
- Risk Assessments for Contractors work have been undertaken by
architect
- Pavilion Emergency Action Plan updated and on display.
- Conditions of Use updated.
- Event Guidelines updated.
Grindleford Pavilion Development
EMERGENCY ACTION PLAN
Grindleford Pavilion Development
EMERGENCY ACTION PLAN
Grindleford Pavilion Development
CONDITIONS of HIRE / USE
Grindleford Pavilion Development
FIELD EVENT GUIDELINES
Grindleford Pavilion Development
HEALTH & SAFETY
- Pavilion & Playing Field Documents for above available.
- Risk Assessments
- Pavilion Emergency Action Plan
- Conditions of Use
- Event Guidelines.
- User groups / Event Organisers may need to update their own
assessments / procedures.
Grindleford Pavilion Development
END RESULT
Grindleford Pavilion Development
IN THE MEANTIME
- Pavilion & Facilities
remain open for business!
- Some compromises need