GOALS COLLABORATIVE TEACHER IMPROVED CLASSROOM SCHOOL - - PowerPoint PPT Presentation

goals
SMART_READER_LITE
LIVE PREVIEW

GOALS COLLABORATIVE TEACHER IMPROVED CLASSROOM SCHOOL - - PowerPoint PPT Presentation

PROGRAMMING SCHOOL CONSOLIDATION PK-8 TERRACE HILLS / COLLINS PK-8 SCHOOL CONSOLIDATION PROJECT IS COMMITTED TO EMBRACING EPISDS STRATEGIC PRIORITIES & LEARNING GOALS. PROJECT BASED LEARNING BREAK OUT AREAS SAFE CAMPUS WITH FRESH


slide-1
SLIDE 1

TERRACE HILLS MIDDLE CONSOLIDATING COLLINS ELEMENTARY

Active Learning Great Community School Community Partnerships Leading with Character & Ethics Critical, Knowledgeable, & Creative Thinkers Informed Problem Solvers Effective Bilingual Communications Responsible Leaders & Productive Citizens Socially & Emotionally Intelligent Individuals

PROGRAMMING

SCHOOL CONSOLIDATION PK-8

TERRACE HILLS / COLLINS PK-8 SCHOOL CONSOLIDATION PROJECT IS COMMITTED TO EMBRACING EPISD’S STRATEGIC PRIORITIES & LEARNING GOALS.

PROJECT BASED LEARNING BREAK OUT AREAS SAFE CAMPUS WITH FRESH IDENTITY COLLABORATIVE TEACHER WORKSPACES IMPROVED CLASSROOM UTILIZATION SCHOOL CONSOLIDATION

BIG PICTURE

GOALS

slide-2
SLIDE 2

TERRACE HILLS MIDDLE CONSOLIDATING COLLINS ELEMENTARY

FLEXIBLE

CORE CLASSROOMS COMBINED WITH OPEN

COLLABORATION

PROGRAMMING

21ST CENTURY LEARNING

THE LIBRARY, A RESEARCH CENTER, SOCIAL HUB AND MAKER SPACE

LLS BOSQUE ELEMENTARY SCHOOL, PRE RENOVATION LLS BOSQUE ELEMENTARY SCHOOL, POST RENOVATION RISD PECOS ELEMENTARY SCHOOL, PRE RENOVATION RISD PECOS ELEMENTARY SCHOOL, POST RENOVATION JEFFERSON MIDDLE SCHOOL MUSIC STUDIO

slide-3
SLIDE 3

TERRACE HILLS MIDDLE CONSOLIDATING COLLINS ELEMENTARY

SEPTEMBER 2017 - OCTOBER 2018 FALL 2021

PROJECT BUDGET

DEMOLITION

  • Partial ES Collins

NEW CONSTRUCTION

  • Admin. & Main Entry
  • ES Classrooms
  • MS Fine Arts

DESIGN CONSTRUCTION

PHASE

PHASE 1 DEMO. - MS 8TH GRADE PHASE 1 DEMO. - ES LIBRARY PHASE 1 DEMO. - ES SOUTH WING PHASE 3 DEMO - ES COLLINS

PHASE III DEMO - ES COLLINS

PHASE 2 RENOVATION - MS CLASSROOMS & ADMIN. PHASE 1ADDITION - LIBRARY

  • ADMIN. & ES CLASSROOM

MS FINE ARTS PHASE SUMMER RENOVATION - KITCHEN SERVING LINE PHASE SUMMER RENOVATION -

  • MECH. UPGRADE

PHASE 3 DEMO - MS BAND & CHOIR PHASE 3 REMOVE - PORTABLE CAMPUS PHASE 3 SITE WORK PHASE 3 SITE WORK PHASE 1 NEW CONSTRUCTION PHASE 3 SITE WORK

CONSOLIDATED CAMPUS PK-8 SUMMER 2019 06 . 2020 TO 06 . 2021 12 . 2018 TO 05 . 2020 06 . 2021 TO 10 . 2021

1

SUMMER 2020 RENOVATION

  • Cafeteria Kitchen

Serving Lane RENOVATION

  • TH Main MS

Classroom Building

WINTER 2018

2 3

RENOVATION

  • MS Gym

Mechanical Upgrade DEMOLITION & SITE WORK

PROJECT SCHEDULE

BOYS RR GIRLS RR

PROPOSED

PHASING

. .

RENOVATION: $ 8,558,700 ADDITIVE ALTERNATES: $ 2,710,000 CONSTRUCTION COST LIMIT:

100 % CCL : (CCL)

$ 27,300,000 $ 24,570,000

90 % CCL :

NEW - DEMOLITION & CONSTRUCTION: $ 16,007,959 RENOVATION: $ 8,558,700

10 % CCL : 90 % CCL :

slide-4
SLIDE 4

TERRACE HILLS MIDDLE CONSOLIDATING COLLINS ELEMENTARY PROPOSED

SITE PLAN

EXISTING TO REMAIN NEW CONSTRUCTION RENOVATIONS FENCE & ACCESS

N

slide-5
SLIDE 5

TERRACE HILLS MIDDLE CONSOLIDATING COLLINS ELEMENTARY PROPOSED

FLOOR PLANS - LEVEL 1

ELEMENTARY SUPPORT ADMIN SPED MIDDLE SCHOOL STORAGE KITCHEN

N DN DN UP UP UP

LEGEND

ELEMENTARY CAFETERIA MIDDLE SCHOOL SPED ADMIN SUPPORT STORAGE

KILN STOR STOR ELEC OFFICE ART BAND PR PR PR PR ORCHESTRA STOR STOR OFFICE BOYS GIRLS ENSEMBLE PRACTICE IT MECH JAN CHOIR OFFICE PR STOR PR LOBBY VEST VEST RECEPTION ASST PR ASST PR CP SEC PRCPL CONF SRO VAULT FRONT OFFICE MAIL / WORK HEALTH STO. RR IT RECEP COUNS COUNS RR CONF PRE-K CLASSROOM RR PRE-K CLASSROOM RR RR STOR PRE-K CLASSROOM COMMONS KINDER CLASSROOM KINDER CLASSROOM KINDER CLASSROOM ART RR STOR KILN RR RR JAN ELEC IT LIFE SKILLS ES BIC STOR RR TEACHER LOUNGE RR STOR STOR BOYS GIRLS 1ST GRADE CLASSROOM 1ST GRADE CLASSROOM 1ST GRADE CLASSROOM 1ST GRADE CLASSROOM COMMONS JAN. W M MECH .

DOWN

.

DOWN

.

DOWN

W M COMMONS NEW SERVING LINE GYMNASIUM VEST M STORAGE W VEST VEST STOR JAN VEST BOYS LOCKER ROOM SHOWER SHOWER GIRLS LOCKER ROOM VEST HALL OFFICE RR GIRLS BOYS RR OFFICE HALL VEST S ATHLETIC STORAGE TRAINING ROOM MECHANICAL STOR ROTC CLASSRM ATHLETIC STORAGE ACTIVE LEARNING LEADERS LAB OFFICE STOR SCIENCE LAB SCIENCE CLASSROOM SCIENCE CLASSROOM COMPUTER LAB MECH JAN BOYS GIRLS BOILER ROOM STOR STOR BOYS GIRLS COMPUTER LAB E CRC RR CRC / LIFE SKILLS RISER STOR STOR SCIENCE LAB SCIENCE CLASSROOM SCIENCE CLASSROOM LARGE CONFERENCE ASST PRCPL ASST PRCPL ISS WAITING AREA COMMONS CUSTODIAN LOCKERS / OFFICE SRO JAN GIRLS TEST COORD SECURE TESTING MATERIALS ARDs CONFERENCE ROOM OFFICE OFFICE OFFICE OFFICE SPED WORKRM ARDs CONFERENCE ROOM BOYS W CREATIVE LAB OPEN COMPUTER AREA ES READING / STACKS MS READING / STACKS OFF MAKER SPACE OPEN COMPUTER AREA OPEN COMPUTER AREA WORKRM MEDIA STOR BOYS GIRLS RR MECH ELEC JAN CAFETERIA STAGE STOR JAN BOYS STUDENT INTERNET CAFE GIRLS SERVING LINE KITCHEN WALK IN COOLER FREEZER D / W RR LAUNDRY EL R OFFICE STORAGE M COUNSELING RECEPTION STOR COUNSELING CONFERENCE OFFICE OFFICE OFFICE PARENT ROOM STOR 1 A 2 3 4 5 B C D 1 2 3 4 5

3/2/2018 2:41:45 PM

Terrace Hills/Collins PK8 School

4835 Blossom Ave, El Paso, TX 79924

slide-6
SLIDE 6

TERRACE HILLS MIDDLE CONSOLIDATING COLLINS ELEMENTARY PROPOSED

FLOOR PLANS - LEVEL 2

ELEMENTARY SUPPORT ADMIN SPED MIDDLE SCHOOL STORAGE KITCHEN

N DN

LEGEND

ELEMENTARY MIDDLE SCHOOL SPED ADMIN SUPPORT STORAGE

COMPUTER LAB 2ND GRADE CLASSROOM 2ND GRADE CLASSROOM BOYS GIRLS 3RD GRADE CLASSROOM 3RD GRADE CLASSROOM 4TH GRADE CLASSROOM 4TH GRADE CLASSROOM ELEC. IT READING ENRICHMENT 5TH GRADE CLASSROOM BOYS GIRLS 5TH GRADE CLASSROOM 5TH GRADE CLASSROOM 5TH GRADE CLASSROOM SCIENCE STOR 2ND GRADE CLASSROOM 2ND GRADE CLASSROOM 3RD GRADE CLASSROOM COMMONS 3RD GRADE CLASSROOM 4TH GRADE CLASSROOM 4TH GRADE CLASSROOM WORKRM STORAGE COMPUTER LAB COMMONS 5TH GRADE CLASSROOM JAN M W STORAGE

OPEN TO BELOW OPEN TO BELOW

ALTERNATIVE RR STOR BIC BIC RR STOR BOOKROOM AND CLERK CLASSROOM CLASSROOM CLASSROOM CLASSROOM COMMONS GIRLS JAN STAFF LOUNGE CLASSROOM CLASSROOM CLASSROOM BOYS W M CLASSROOM CLASSROOM CLASSROOM CLASSROOM CLASSROOM CLASSROOM CLASSROOM CLASSROOM CLASSROOM STORAGE TEACHER WORKROOM STOR EXTG STOR BOYS GIRLS BOILER ROOM M W PLC WRKRM PLC PLC EXTG STOR EXTG STOR 1 A 2 3 4 5 B C D 1 2 3 4 5

3/2/2018 2:37:02 PM

Terrace Hills/Collins PK8 School

4835 Blossom Ave, El Paso, TX 79924

slide-7
SLIDE 7

TERRACE HILLS MIDDLE CONSOLIDATING COLLINS ELEMENTARY PROPOSED

CAMPUS 3D VIEWS

NEW MAIN ENTRY