SLIDE 1
ISG 17 October
Generator Charging from 2010: DNO information on option C2 and next - - PowerPoint PPT Presentation
Generator Charging from 2010: DNO information on option C2 and next steps ISG 17 October Summary DNOs provided information on 3 schemes per area for connections > = 10MW and recalculated reinforcement costs in line with change in
ISG 17 October
ISG 17 October
ISG 17 October
ISG 17 October
Distribution of sample size
1 2 3 4 5 6 1 2 3 Sample size
Net compensation per MW
10 20 30
F F F F F F F&T F&T F&T F&T T T T T
Reinforcement driver: fault level (F), thermal (T) or both (F&T) £000/MW
ISG 17 October
ISG 17 October
ISG 17 October
ISG 17 October