generator charging from 2010 dno information on option c2
play

Generator Charging from 2010: DNO information on option C2 and next - PowerPoint PPT Presentation

Generator Charging from 2010: DNO information on option C2 and next steps ISG 17 October Summary DNOs provided information on 3 schemes per area for connections > = 10MW and recalculated reinforcement costs in line with change in


  1. Generator Charging from 2010: DNO information on option C2 and next steps ISG 17 October

  2. Summary � DNOs provided information on 3 schemes per area for connections > = 10MW and recalculated reinforcement costs in line with change in connection boundary (C2 option) � Exercise highlights general reinforcement trends > = 10MW � DNOs noted various issues with exercise ISG 17 October

  3. Issues with data � Bias towards most recent connection projects � Limited availability of historical data � Some issues noted with: – MEA calculations – Inclusion/ exclusion of O&M costs – Customers who accepted constraints rather than ‘deep’ charge – Inclusion of transmission reinforcement costs ISG 17 October

  4. Results � 15 projects included reinforcement Distribution of sample size 6 (out of a potential sample of 42) 5 No. of DNOs 4 – 5 DNOs noted no cases of 3 reinforcement works required 2 – Negative compensation in 3 cases 1 0 � ‘Compensation’ range: 0 1 2 3 Sample size -20£/ kW to 25 £/ kW Net compensation per MW 30 � Median age at 2010: 20 £000/MW 9 years [ max: 19yr] 10 0 � Median size: F F F F F F F&T F&T F&T F&T T T T T -10 35MW [ range 10 – 480MW] -20 Reinforcement driver: fault level (F), thermal (T) or both (F&T) ISG 17 October

  5. General trends � Many DNOs stated that reinforcement is a rare occurrence: – A limited number of generators would receive compensation under option C2 � Of those noting reinforcement: – Some DNOs noted apportionment or discount was carried out at time of ‘deep’ charging regime – Net compensation per MW for fault level reinforcements higher than for thermal reinforcements ISG 17 October

  6. Options for charging � Objective: prime driver to ensure parties see economic signals, but proportional � To achieve this a number of options discussed: – Option C1: Unclear at this stage what charges will be, models not developed – Option C2: Historic info difficult, although few generators affected – Option C3: Simple backstop date, less precise, bilateral contracts still option ISG 17 October

  7. Options for charging � Do we need something more targeted? � Alternative options: – Option D: introduce GDUoS charge for existing generators based on a trigger, e.g. when costs are expected to be imposed. – Option E: introduce GDUoS charge with revenue = 0 for existing generators Allow DG to be constrained or incur the charge ISG 17 October

  8. Next steps � Views invited on way forward: – Wait for charging methodologies development (e.g. delay a year)… provide clearer picture but delay certainty to parties – Ofgem consults wider audience – DNOs lead development to ensure economic outcome ISG 17 October

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend