GENERAL MANAGERS REPORT Regular Board Meeting Monday, July 27, 2020 Beaconsfield Park Playground Renewal Invitation to Tender posted on July 22, 2020. Construction to start in September. Expected completion December 2020.


slide-1
SLIDE 1

Regular Board Meeting Monday, July 27, 2020

GENERAL MANAGER’S REPORT

slide-2
SLIDE 2

2

Beaconsfield Park Playground Renewal

  • Invitation to Tender posted
  • n July 22, 2020.
  • Construction to start in

September.

  • Expected completion

December 2020.

  • Playground features; New

swings, spinners, slides, trampolines, a climbing net, a wooden play hut

Current state of Beaconsfield Park

slide-3
SLIDE 3

3

Montgomery Park Request for Proposals Montgomery Park Project

  • Invitation to Tender posted on

July 20, 2020.

  • Upgrades include installation of

new irrigation and drainage systems which will expand the playfield area by more than 50%.

  • New field will feature four

baseball diamonds; can accommodate a variety of field sports.

  • Construction is targeted to begin

this fall.

  • Completion is expected by August

2021.

slide-4
SLIDE 4

4

New Point-of-Sale Solution

  • Successfully launched in early July at

nine (9) Park Board concessions: Second Beach, Stanley Park Info Booth, Lumberman’s Arch, Spanish Banks East & West, Locarno Beach, Jericho Beach, Kitsilano Pool and Sunset Beach.

  • Allows operators to process orders

quicker and more efficiently:

  • Improves customer service
  • PCI compliant
  • Has the ability to better

communicate with our existing financial and inventory control systems.

slide-5
SLIDE 5
  • One year anniversary of SP Restaurant and

Brewpub this week.

  • Series of “backyard-themed” events featuring yoga,

picnic dining experiences and acoustic music scheduled to take place between July 29 and August 2.

5

Stanley Park Restaurant and Brewpub

slide-6
SLIDE 6

6

Board Briefing Memos and Emails: June 22 to July 27, 2020

Date Topic Jul 16 COVID-19 - Special Events and Filming Update Jul 16 COVID-19 - Restaurant Patio Temporary Expansion Permit Jul 22 COVID-19 - 2019-2022 Capital Plan Recalibration Jul 22 COVID-19 Reopening - Community Center Childcare Services Jul 22 Skateboard Amenities Strategy Request for Proposals