gb sqss sub group of oteg
play

GB SQSS sub-group of OTEG Illustration of cost benefit analysis - PowerPoint PPT Presentation

GB SQSS sub-group of OTEG Illustration of cost benefit analysis reasults 1 Network arrangement examples 33 kV 33 kV 33 kV Windfarm electrical system 132 kV 132 kV 132 kV 33 kV 132 kV/220kV 132 kV 400 kV 132kV/220 kV 400 kV Onshore


  1. GB SQSS sub-group of OTEG Illustration of cost benefit analysis reasults 1

  2. Network arrangement examples 33 kV 33 kV 33 kV Windfarm electrical system 132 kV 132 kV 132 kV 33 kV 132 kV/220kV 132 kV 400 kV 132kV/220 kV 400 kV Onshore network Onshore network 2

  3. Platform design: Number of transformers 1 SGT or 2 SGTs 3

  4. One, two or three transformers (MTTR 3 months) Test 1 Technology AC Voltage (kV) (All) Wind generation (MW) 400 MW 50 45 40 35 30 Cost (m£) 25 20 15 10 5 0 1 2 1 2 1 2 1 2 1 2 1 2 1 2 3 t. 3 t. 2 t. 3 t. 2 t. 2 t. 1 t. 120 MW t. 150 MW t. 180 MW t. 240 MW t. 300 MW t. 360 MW t. Data Platform & plant cost (m£) EEC cost (m£) Losses cost (m£) Mainenance cost (m£) Transformer rating (MW) Number of transformers Wind profile index 4

  5. One, two or three transformers (MTTR 4.5 months) Test 1 Technology AC Voltage (kV) (All) Wind generation (MW) 400 MW 50 45 40 35 30 Cost (m£) 25 20 15 10 5 0 1 2 1 2 1 2 1 2 1 2 1 2 1 2 3 t. 3 t. 2 t. 3 t. 2 t. 2 t. 1 t. 120 MW t. 150 MW t. 180 MW t. 240 MW t. 300 MW t. 360 MW t. Data Platform & plant cost (m£) EEC cost (m£) Losses cost (m£) Mainenance cost (m£) Transformer rating (MW) Number of transformers Wind profile index 5

  6. One, two or three transformers (MTTR 15.5 months) Test 1 Technology AC Voltage (kV) (All) Wind generation (MW) 400 MW 70 60 50 40 Cost (m£) 30 20 10 0 1 2 1 2 1 2 1 2 1 2 1 2 1 2 3 t. 3 t. 2 t. 3 t. 2 t. 2 t. 1 t. 120 MW t. 150 MW t. 180 MW t. 240 MW t. 300 MW t. 360 MW t. Data Platform & plant cost (m£) EEC cost (m£) Losses cost (m£) Mainenance cost (m£) Transformer rating (MW) Number of transformers Wind profile index 6

  7. Break-even MTTR for Transformers MTTR Energy cost (£/MWh) (months) Substation 50 75 100 solution 1x360 MW < 6.5 < 4.5 < 3.2 2x180 MW < 15.5 < 10.5 < 8 2x240 MW < 23.5 < 15.5 < 11.5 3x150 MW < 34 < 23 < 17.5 3x180 MW - - - 7

  8. Conclusion • For cost (value) of wind energy of £75/MWh and MTTR above 4.5 months (£100/MWh and 3.2 months), N-1 justified for AC solutions 8

  9. Cable system design: Number of cables 1 or 2 cables MTTR and cost of energy that favour N-1 over N-0 9

  10. N-1 versus N-0 (MTTR 2 months) Test 1 Technology AC Voltage (kV) 220 kV Wind generation (MW) 280 MW Transformer rating (MW) 135 MW t. Number of transformers 2 t. 160 140 120 100 Cost (m£) 80 60 40 20 0 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 c. 2 c. 1 c. 2 c. 1 c. 2 c. 1 c. 2 c. 278 MW 278 MW 274 MW 266 MW 500 mm² 500 mm² 500 mm² 500 mm² 25 km 50 km 75 km 100 km Data Platform & plant cost (m£) Cables cost (m£) MVArs cost (m£) EEC cost (m£) Losses cost (m£) Mainenance cost (m£) Cable length (km) Cable size (mm²) Cable capability (MW) Number of cables Wind profile index 10

  11. N-1 versus N-0 (MTTR 8.5 months) Test 1 Technology AC Voltage (kV) 220 kV Wind generation (MW) 280 MW Transformer rating (MW) 135 MW t. Number of transformers 2 t. 160 140 120 100 Cost (m£) 80 60 40 20 0 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 c. 2 c. 1 c. 2 c. 1 c. 2 c. 1 c. 2 c. 278 MW 278 MW 274 MW 266 MW 500 mm² 500 mm² 500 mm² 500 mm² 25 km 50 km 75 km 100 km Data Platform & plant cost (m£) Cables cost (m£) MVArs cost (m£) EEC cost (m£) Losses cost (m£) Mainenance cost (m£) Cable length (km) Cable size (mm²) Cable capability (MW) Number of cables Wind profile index 11

  12. N-1 versus N-0 (MTTR 9 months) Test 1 Technology AC Voltage (kV) 220 kV Wind generation (MW) 280 MW Transformer rating (MW) 135 MW t. Number of transformers 2 t. 160 140 120 100 Cost (m£) 80 60 40 20 0 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 c. 2 c. 1 c. 2 c. 1 c. 2 c. 1 c. 2 c. 278 MW 278 MW 274 MW 266 MW 500 mm² 500 mm² 500 mm² 500 mm² 25 km 50 km 75 km 100 km Data Platform & plant cost (m£) Cables cost (m£) MVArs cost (m£) EEC cost (m£) Losses cost (m£) Mainenance cost (m£) Cable length (km) Cable size (mm²) Cable capability (MW) Number of cables Wind profile index 12

  13. N-1 versus N-0 (MTTR 9.5 months) Test 1 Technology AC Voltage (kV) 220 kV Wind generation (MW) 280 MW Transformer rating (MW) 135 MW t. Number of transformers 2 t. 160 140 120 100 Cost (m£) 80 60 40 20 0 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 c. 2 c. 1 c. 2 c. 1 c. 2 c. 1 c. 2 c. 278 MW 278 MW 274 MW 266 MW 500 mm² 500 mm² 500 mm² 500 mm² 25 km 50 km 75 km 100 km Data Platform & plant cost (m£) Cables cost (m£) MVArs cost (m£) EEC cost (m£) Losses cost (m£) Mainenance cost (m£) Cable length (km) Cable size (mm²) Cable capability (MW) Number of cables Wind profile index 13

  14. N-1 v. N-0 (MTTR 10 months) Test 1 Technology AC Voltage (kV) 220 kV Wind generation (MW) 280 MW Transformer rating (MW) 135 MW t. Number of transformers 2 t. 180 160 140 120 Cost (m£) 100 80 60 40 20 0 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 c. 2 c. 1 c. 2 c. 1 c. 2 c. 1 c. 2 c. 278 MW 278 MW 274 MW 266 MW 500 mm² 500 mm² 500 mm² 500 mm² 25 km 50 km 75 km 100 km Data Platform & plant cost (m£) Cables cost (m£) MVArs cost (m£) EEC cost (m£) Losses cost (m£) Mainenance cost (m£) Cable length (km) Cable size (mm²) Cable capability (MW) Number of cables Wind profile index 14

  15. N-1 versus N-0 (energy cost 230£/MWh) Test 1 Technology AC Voltage (kV) 220 kV Wind generation (MW) 280 MW Transformer rating (MW) 135 MW t. Number of transformers 2 t. 200 180 160 140 120 Cost (m£) 100 80 60 40 20 0 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 c. 2 c. 1 c. 2 c. 1 c. 2 c. 1 c. 2 c. 278 MW 278 MW 274 MW 266 MW 500 mm² 500 mm² 500 mm² 500 mm² 25 km 50 km 75 km 100 km Data Platform & plant cost (m£) Cables cost (m£) MVArs cost (m£) EEC cost (m£) Losses cost (m£) Mainenance cost (m£) Cable length (km) Cable size (mm²) Cable capability (MW) Number of cables Wind profile index 15

  16. N-1 versus N-0 (energy cost 240£/MWh) Test 1 Technology AC Voltage (kV) 220 kV Wind generation (MW) 280 MW Transformer rating (MW) 135 MW t. Number of transformers 2 t. 200 180 160 140 Cost (m£) 120 100 80 60 40 20 0 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 c. 2 c. 1 c. 2 c. 1 c. 2 c. 1 c. 2 c. 278 MW 278 MW 274 MW 266 MW 500 mm² 500 mm² 500 mm² 500 mm² 25 km 50 km 75 km 100 km Data Platform & plant cost (m£) Cables cost (m£) MVArs cost (m£) EEC cost (m£) Losses cost (m£) Mainenance cost (m£) Cable length (km) Cable size (mm²) Cable capability (MW) Number of cables Wind profile index 16

  17. N-1 versus N-0 (energy cost 250£/MWh) Test 1 Technology AC Voltage (kV) 220 kV Wind generation (MW) 280 MW Transformer rating (MW) 135 MW t. Number of transformers 2 t. 200 180 160 140 Cost (m£) 120 100 80 60 40 20 0 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 c. 2 c. 1 c. 2 c. 1 c. 2 c. 1 c. 2 c. 278 MW 278 MW 274 MW 266 MW 500 mm² 500 mm² 500 mm² 500 mm² 25 km 50 km 75 km 100 km Data Platform & plant cost (m£) Cables cost (m£) MVArs cost (m£) EEC cost (m£) Losses cost (m£) Mainenance cost (m£) Cable length (km) Cable size (mm²) Cable capability (MW) Number of cables Wind profile index 17

  18. 1 or 2 Cables: summary Length MTTR Energy cost • Break-even km months £/MWh parameters are in red 25 13 50 50 14.5 50 75 16 50 100 18 50 25 8.5 75 50 9 75 75 9.5 75 100 10 75 25 6 100 50 6 100 75 6.5 100 100 7 100 25 2 230 50 2 240 75 2 240 100 2 250 18

  19. 19 Cable Redundancy Analysis

  20. N-1 versus N-0 (MTTR 2 months) Test 1 Technology AC Voltage (kV) 220 kV Wind generation (MW) 350 MW Transformer rating (MW 170 MW t. Number of transformers 2 t. Cable length (km) 25 km 80 70 60 50 Cost (m£) 40 30 20 10 0 1 2 1 2 1 2 2 c. 1 c. 2 c. 278 MW 334 MW 500 mm² 800 mm² Data Platform & plant cost (m£) Cables cost (m£) MVArs cost (m£) EEC cost (m£) Losses cost (m£) Mainenance cost (m£) Cable size (mm²) Cable capability (MW) Number of cables Wind profile index 20

  21. N-1 versus N-0 (MTTR 6.5 months) Test 1 Technology AC Voltage (kV) 220 kV Wind generation (MW) 350 MW Transformer rating (MW 170 MW t. Number of transformers 2 t. Cable length (km) 25 km 80 70 60 50 Cost (m£) 40 30 20 10 0 1 2 1 2 1 2 2 c. 1 c. 2 c. 278 MW 334 MW 500 mm² 800 mm² Data Platform & plant cost (m£) Cables cost (m£) MVArs cost (m£) EEC cost (m£) Losses cost (m£) Mainenance cost (m£) Cable size (mm²) Cable capability (MW) Number of cables Wind profile index 21

  22. N-1 versus N-0 (MTTR 7.5 months) Test 1 Technology AC Voltage (kV) 220 kV Wind generation (MW) 350 MW Transformer rating (MW 170 MW t. Number of transformers 2 t. Cable length (km) 25 km 80 70 60 50 Cost (m£) 40 30 20 10 0 1 2 1 2 1 2 2 c. 1 c. 2 c. 278 MW 334 MW 500 mm² 800 mm² Data Platform & plant cost (m£) Cables cost (m£) MVArs cost (m£) EEC cost (m£) Losses cost (m£) Mainenance cost (m£) Cable size (mm²) Cable capability (MW) Number of cables Wind profile index 22

  23. 23 1 circuit of 220kV or 2 circuits of 132kV 350 MW Wind Farm Case Study

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend