Gate 3 Constraint Report Results Overview Customer Connections - - PowerPoint PPT Presentation
Gate 3 Constraint Report Results Overview Customer Connections - - PowerPoint PPT Presentation
Gate 3 Constraint Report Results Overview Customer Connections Forum 16 April 2013 Introduction Studies for the Gate 3 constraint reports have been completed following the publication of a final tie-break decision by the SEM Committee.
Introduction
- Studies for the Gate 3 constraint
reports have been completed following the publication of a final tie-break decision by the SEM Committee.
- High-level results are available.
- There are some general trends
that have been observed in the results.
- Work is now in progress to produce
and issue the detailed Gate 3 constraint reports.
2
Assumptions
3
Scenarios
- Two scenarios covered:
– 33% uptake of Gate 3
- This is achieved by derating all Gate 3
projects to 33% of their MEC. – 100% uptake of Gate 3
- The build-out rate is the same for both
scenarios.
4
Build-out rate
- A methodology was developed in conjunction with
IWEA to take account of factors other than shallow connection leadtimes.
- The data was based on survey responses from Gate
3 developers (70% response rate)
- Methodology takes account of:
– planning permission status – location with respect to environmentally designated areas – project size – shallow connection leadtime
- Pre-Gate 3 is assumed to connect as per their
target connection dates
5
1934 2112 2116 2564 2564 2564 2564 2564 45 333 466 1369 1662 3385 3545 3999 553 607 761 839 961 1012 1122 1306 1000 2000 3000 4000 5000 6000 7000 8000 2013 2014 2015 2016 2017 2018 2019 2020 Installed Wind Capacity (MW) Year Pre Gate 3 Gate 3 Northern Ireland
Build-out rate: 100% Gate 3
6
Large projects with planning assumed to connect ~4 years from offer acceptance Projects without planning take an extra 2 years
1934 2112 2116 2564 2564 2564 2564 2564 15 110 154 452 549 1117 1170 1320 553 607 761 839 961 1012 1122 1306 1000 2000 3000 4000 5000 6000 7000 8000 2013 2014 2015 2016 2017 2018 2019 2020 Installed Wind Capacity (MW) Year Pre Gate 3 Gate 3 Northern Ireland
Build-out rate: 33% Gate 3
7
Average installation rate in Ireland of ~275MW/year
Northern Ireland
8
- We have an All-Island model based on SONI’s
wind and network build out data.
- There is a consultation in Northern Ireland on
their connection process.
- Northern Ireland constraint reports are not being
published at this stage.
Interconnection
- We don’t model imports.
- Both Moyle and EWIC export capacities are
derated by 20% to account for trading imperfections etc.
- The model will export to avoid curtailment up to
80% of the interconnectors’ capacity. This will be included in the reports.
- The Moyle export capacity reduces from 250MW
to 80MW in 2017.
9
100 200 300 400 500 600 2013 2014 2015 2016 2017 2018 2019 2020
Interconnector Export Capacity
EWIC Moyle
Operational rules
- SNSP limit increases from
50% to 75% over study period.
- Reserve (POR) is modelled.
- Regional constraints modelled:
– At least 2 sets in Dublin until 2016 (inclusive) – At least one set on in Cork during the daytime until 2018 (inclusive)
- System constraints modelled:
– 5 set rule in Ireland at all times + Sealrock and Peats – 3 sets in Northern Ireland before NS2, 2 sets afterwards
10
40% 45% 50% 55% 60% 65% 70% 75% 80% 2013 2014 2015 2016 2017 2018 2019 2020
SNSP Limit
High level results
11
Overall 33% Gate 3 results
12
0% 2% 4% 6% 8% 10% 12% 14% 16% 18% 2014 2015 2016 2017 2018 2019 2020 2021 Reduction as a % of available energy Combined Curtailment and Constraint Curtailment Constraint
Overall 100% Gate 3 results
13
0% 2% 4% 6% 8% 10% 12% 14% 16% 18% 2014 2015 2016 2017 2018 2019 2020 2021 Reduction as a % of available energy Combined Curtailment and Constraint Curtailment Constraint
Comparison with PGOR results
14
0% 2% 4% 6% 8% 10% 12% 14% 16% 18% 20% 2014 2015 2016 2017 2018 2019 2020 2021 100% Gate 3: G3CR 100% Gate 3: PGOR 33% Gate 3: G3CR 33% Gate 3: PGOR Comparable results to the PGORs with explainable differences e.g. the wind’s build-out rate
Detailed results
15
Interconnection results
- The model assumes that the interconnectors can
be used to export wind up to the interconnector’s derated capacity.
- This wind would otherwise be curtailed.
- The following slides provide some perspective
- n how the interconnector exports are
influencing results.
16
200 400 600 800 1000 1200 2014 2015 2016 2017 2018 2019 2020 2021 Exports (GWh) EWIC Moyle
Interconnection results: 33% Gate 3
17
This corresponds to ~2% of total wind production Curtailment would be of the
- rder of 4%
without exports
200 400 600 800 1000 1200 2014 2015 2016 2017 2018 2019 2020 2021 Exports (GWh) EWIC Moyle
Interconnection results: 100% Gate 3
18
This corresponds to ~6% of total wind production Curtailment would be of the
- rder of 17-18%
without exports in this scenario
Detailed results
- The following slides focus on parts of the
network that have high levels of constraints for some individual windfarms.
- Individual windfarms with high constraints are
mainly located in: – Donegal – Southwest (110kV and 220kV) – Mayo
19
Donegal constraints
- Donegal is a constraint group today.
- Contingencies on lines south of Cathaleen’s Fall affect all nodes
in Donegal.
- It was assumed that these constraints would migrate northward
as uprates were completed.
20
Donegal constraints
32MW 97MW 15MW 120MW 91MW 85MW 62MW 47MW 105MW 8MW
Pre-RIDP 1-5%
660MW in total
Donegal constraints
- Our studies indicate that the constraint group may not get
smaller.
- We believe curtailment may be binding before constraints bind.
- For example, it may take 450MW of Donegal wind to trigger
constraints but curtailment could bind at 400MW.
- The constraints are relieved when RIDP is implemented
(assumed to be 2020).
22
110kV Southwest constraints
- Some constraints appear in the Southwest
110kV system in 2013/14 coinciding with wind connecting in North Kerry / West Limerick.
- These constraints are relieved when the wind on
temporary connections transition to the 220kV system for their permanent connection in 2015.
- We didn’t see this as a constraint group based
- n the Constraint Group criteria.
23
North Kerry/West Limerick 110kV constraints
24
191MW 23MW 92MW 52MW 179MW
The main binding constraint is Tarbert- Trien 110kV line
- verloading for the
loss of Clashavoon- Clonkeen 110kV Clahane-Tralee 110kV can also overload for the loss of Tarbert- Trien 110kV but this happens less often Moving the Southwest temporary connections to their permanent connection on the 220kV system alleviates these constraints
Athea, Dromada, Trien 8-12% Clahane 6-8%
537MW in total
- n this section of
110kV
220kV Southwest constraints
- The Southwest becomes a constraint group
when the 220kV stations are built.
- Non-firm wind is constrained before other wind.
- Constraints become relatively high once all the
Gate 3 wind connects in 2018 and before the Southwest reinforcements are completed in 2019.
25
Southwest 220kV constraints
26
261MW 270MW 370MW The loss of Moneypoint- Kilpaddoge 220kV
- verloads Tarbert-
Prospect 220kV. The completion of an additional HV line in the Southwest is required to alleviate this constraint group.
G3 Non-firm 4-14% G3 Partially-firm 8%
900 MW in total
- Indicative route for the
purposes of this presentation
Mayo constraints
- Relatively high constraints begin appearing in
2016 when a large amount of wind is assumed to connect on the 110kV system.
- The constraints are relieved in 2018 when it is
assumed that the Castlebar-Moy 110kV line is completed.
- Constraints appear to be largely driven by
uprate outages.
27
West 110kV constraints
28
198MW 30MW 6MW 77MW A combination
- f uprate
- utages and
high amounts of wind connecting
- n the 110kV
system drive constraints in this area. Constraints are reduced once lines are uprated and Castlebar- Moy 110kV is built The loss of Bellacorrick- Castlebar 110kV
- verloading
Moy-Glenree 110kV line is the most common constraint.
Sligo, Cunghill, Glenree ~13% Bellacorrick, Tawnaghmore, Moy 5-13%
35MW
- Indicative route for the
purposes of this presentation
Sensitivity studies
- We carried out some sensitivity studies to try
and answer some questions that we anticipated might be asked:
– What are the underlying constraints if curtailment is removed? – Discrepancy between study results and curtailment that is currently experienced – Impact of restricted coal running (Moneypoint has a min gen of 99MW per set)
29
How would imports effect curtailment?
- We modelled a 2013 case with flat-out imports
- n both interconnectors.
- There is ~340MW more wind in the 2013 case
compared to today’s wind but the results should give some insight into how imports could effect curtailment and go some way toward explaining how curtailment levels today compare to results from our base case.
- The results indicate curtailment in the order of 4-
5% compared to <0.5% in the 2013 base case.
30
Effect of Moneypoint not running
- A sensitivity case was studied to investigate the
effect that not running Moneypoint would have
- n curtailment.
- Bearing in mind that there are minimum
generation requirements on the system, not running Moneypoint can act to increase curtailment since its sets have relatively low min gens.
- Results indicate if CCGTs are ran in place of
Moneypoint, overall curtailment increases by~1% in the 2020 33% Gate 3 case.
31
Minimised curtailment
- Another sensitivity case was studied to
investigate the underlying constraints on the system if curtailment was minimised.
- Curtailment was minimised by artificially
increasing interconnection
- Results indicate overall constraints in this case
are <1% for the 100% Gate scenario in 2020
32
Observations on constraint results
- Average levels are low for all years.
- There are some nodes that will have high
constraints: – During uprate outages – Until uprates or new builds are delivered – Inside a constraint group
33
Observations on curtailment results
- High levels of curtailment if all of Gate 3
connects.
- Low levels of curtailment in the 33% Gate 3 case
assuming: – Exporting of excess wind on the EWIC and Moyle – DS3 can deliver 75% SNSP – No additional operational constraints to those modelled in the study
34
Overall 33% Gate 3 results
35
0% 2% 4% 6% 8% 10% 12% 14% 16% 18% 2014 2015 2016 2017 2018 2019 2020 2021 Reduction as a % of available energy Combined Curtailment and Constraint Curtailment Constraint
Overall 100% Gate 3 results
36
0% 2% 4% 6% 8% 10% 12% 14% 16% 18% 2014 2015 2016 2017 2018 2019 2020 2021 Reduction as a % of available energy Combined Curtailment and Constraint Curtailment Constraint