gate 3 constraint report results overview
play

Gate 3 Constraint Report Results Overview Customer Connections - PowerPoint PPT Presentation

Gate 3 Constraint Report Results Overview Customer Connections Forum 16 April 2013 Introduction Studies for the Gate 3 constraint reports have been completed following the publication of a final tie-break decision by the SEM Committee.


  1. Gate 3 Constraint Report Results Overview Customer Connections Forum 16 April 2013

  2. Introduction • Studies for the Gate 3 constraint reports have been completed following the publication of a final tie-break decision by the SEM Committee. • High-level results are available. • There are some general trends that have been observed in the results. • Work is now in progress to produce and issue the detailed Gate 3 constraint reports. 2

  3. Assumptions 3

  4. Scenarios • Two scenarios covered: – 33% uptake of Gate 3 • This is achieved by derating all Gate 3 projects to 33% of their MEC. – 100% uptake of Gate 3 • The build-out rate is the same for both scenarios. 4

  5. Build-out rate • A methodology was developed in conjunction with IWEA to take account of factors other than shallow connection leadtimes. • The data was based on survey responses from Gate 3 developers (70% response rate) • Methodology takes account of: – planning permission status – location with respect to environmentally designated areas – project size – shallow connection leadtime • Pre-Gate 3 is assumed to connect as per their target connection dates 5

  6. Build-out rate: 100% Gate 3 8000 1306 Projects without 7000 1122 Large projects planning take an 1012 with planning extra 2 years 6000 assumed to connect ~4 years Installed Wind Capacity (MW) 5000 from offer 961 3999 839 3545 3385 acceptance 4000 1662 1369 3000 761 607 466 333 553 2000 45 2564 2564 2564 2564 2564 2112 2116 1000 1934 0 2013 2014 2015 2016 2017 2018 2019 2020 Year Pre Gate 3 Gate 3 Northern Ireland 6

  7. Build-out rate: 33% Gate 3 8000 7000 6000 Average installation rate in Ireland of ~275MW/year Installed Wind Capacity (MW) 5000 1306 1122 1012 4000 961 839 1320 1170 1117 3000 549 452 761 607 553 154 110 2000 15 2564 2564 2564 2564 2564 2112 2116 1000 1934 0 2013 2014 2015 2016 2017 2018 2019 2020 Year Pre Gate 3 Gate 3 Northern Ireland 7

  8. Northern Ireland • We have an All- Island model based on SONI’s wind and network build out data. • There is a consultation in Northern Ireland on their connection process. • Northern Ireland constraint reports are not being published at this stage. 8

  9. Interconnection • We don’t model imports. • Both Moyle and EWIC export capacities are derated by 20% to account for trading imperfections etc. • The model will export to avoid curtailment up to 80% of the interconnectors’ capacity. This will be included in the reports. • The Moyle export capacity reduces from 250MW Interconnector Export Capacity to 80MW in 2017. 600 500 400 300 200 100 0 9 2013 2014 2015 2016 2017 2018 2019 2020 EWIC Moyle

  10. Operational rules SNSP Limit 80% 75% • SNSP limit increases from 70% 65% 60% 50% to 75% over study period. 55% 50% 45% • Reserve (POR) is modelled. 40% 2013 2014 2015 2016 2017 2018 2019 2020 • Regional constraints modelled: – At least 2 sets in Dublin until 2016 (inclusive) – At least one set on in Cork during the daytime until 2018 (inclusive) • System constraints modelled: – 5 set rule in Ireland at all times + Sealrock and Peats – 3 sets in Northern Ireland before NS2, 2 sets afterwards 10

  11. High level results 11

  12. Overall 33% Gate 3 results 18% 16% Reduction as a % of available energy 14% 12% 10% 8% 6% 4% 2% 0% 2014 2015 2016 2017 2018 2019 2020 2021 Combined Curtailment and Constraint Curtailment Constraint 12

  13. Overall 100% Gate 3 results 18% 16% Reduction as a % of available energy 14% 12% 10% 8% 6% 4% 2% 0% 2014 2015 2016 2017 2018 2019 2020 2021 Combined Curtailment and Constraint Curtailment Constraint 13

  14. Comparison with PGOR results 20% 18% 16% Comparable results to the 14% PGORs with explainable 12% differences e.g. the wind’s build-out rate 10% 8% 6% 4% 2% 0% 2014 2015 2016 2017 2018 2019 2020 2021 100% Gate 3: G3CR 100% Gate 3: PGOR 33% Gate 3: G3CR 33% Gate 3: PGOR 14

  15. Detailed results 15

  16. Interconnection results • The model assumes that the interconnectors can be used to export wind up to the interconnector’s derated capacity. • This wind would otherwise be curtailed. • The following slides provide some perspective on how the interconnector exports are influencing results. 16

  17. Interconnection results: 33% Gate 3 1200 This corresponds 1000 to ~2% of total wind production Exports (GWh) 800 Curtailment would be of the 600 order of 4% without exports 400 200 0 2014 2015 2016 2017 2018 2019 2020 2021 EWIC Moyle 17

  18. Interconnection results: 100% Gate 3 1200 This corresponds to ~6% of total wind production 1000 Curtailment would be of the 800 Exports (GWh) order of 17-18% without exports 600 in this scenario 400 200 0 2014 2015 2016 2017 2018 2019 2020 2021 EWIC Moyle 18

  19. Detailed results • The following slides focus on parts of the network that have high levels of constraints for some individual windfarms. • Individual windfarms with high constraints are mainly located in: – Donegal – Southwest (110kV and 220kV) – Mayo 19

  20. Donegal constraints • Donegal is a constraint group today. • Contingencies on lines south of Cathaleen’s Fall affect all nodes in Donegal. • It was assumed that these constraints would migrate northward as uprates were completed. 20

  21. Donegal constraints 62MW 47MW 91MW 8MW 85MW Pre-RIDP 1-5% 105MW 660MW in total 15MW 97MW 120MW 32MW

  22. Donegal constraints • Our studies indicate that the constraint group may not get smaller. • We believe curtailment may be binding before constraints bind. • For example, it may take 450MW of Donegal wind to trigger constraints but curtailment could bind at 400MW. • The constraints are relieved when RIDP is implemented (assumed to be 2020). 22

  23. 110kV Southwest constraints • Some constraints appear in the Southwest 110kV system in 2013/14 coinciding with wind connecting in North Kerry / West Limerick. • These constraints are relieved when the wind on temporary connections transition to the 220kV system for their permanent connection in 2015. • We didn’t see this as a constraint group based on the Constraint Group criteria. 23

  24. North Kerry/West Limerick 110kV constraints Athea, Dromada, 8-12% Moving the Southwest The main binding Trien temporary constraint is Tarbert- Clahane 6-8% connections to their Trien 110kV line permanent overloading for the 179MW loss of Clashavoon- connection on the 220kV system Clonkeen 110kV 52MW 537MW in total alleviates these on this section of Clahane-Tralee 110kV constraints 92MW 110kV can also overload for the loss of Tarbert- Trien 110kV but this 23MW happens less often 191MW 24

  25. 220kV Southwest constraints • The Southwest becomes a constraint group when the 220kV stations are built. • Non-firm wind is constrained before other wind. • Constraints become relatively high once all the Gate 3 wind connects in 2018 and before the Southwest reinforcements are completed in 2019. 25

  26. Southwest 220kV constraints The loss of The completion of an Moneypoint- G3 Non-firm 4-14% additional HV line in Kilpaddoge 220kV the Southwest is G3 Partially-firm 8% overloads Tarbert- required to alleviate Prospect 220kV. this constraint group. 900 MW in total 261MW 270MW 370MW • Indicative route for the purposes of this presentation 26

  27. Mayo constraints • Relatively high constraints begin appearing in 2016 when a large amount of wind is assumed to connect on the 110kV system. • The constraints are relieved in 2018 when it is assumed that the Castlebar-Moy 110kV line is completed. • Constraints appear to be largely driven by uprate outages. 27

  28. West 110kV constraints 30MW Constraints are A combination of uprate reduced once 198MW lines are uprated outages and and Castlebar- high amounts of Moy 110kV is wind connecting 6MW 35MW on the 110kV built 77MW system drive constraints in this area. The loss of Sligo, Cunghill, ~13% Glenree Bellacorrick- Castlebar 110kV Bellacorrick, 5-13% overloading Tawnaghmore, Moy Moy-Glenree 110kV line is the most common • Indicative route for the purposes of this presentation constraint. 28

  29. Sensitivity studies • We carried out some sensitivity studies to try and answer some questions that we anticipated might be asked: – What are the underlying constraints if curtailment is removed? – Discrepancy between study results and curtailment that is currently experienced – Impact of restricted coal running (Moneypoint has a min gen of 99MW per set) 29

  30. How would imports effect curtailment? • We modelled a 2013 case with flat-out imports on both interconnectors. • There is ~340MW more wind in the 2013 case compared to today’s wind but the results should give some insight into how imports could effect curtailment and go some way toward explaining how curtailment levels today compare to results from our base case. • The results indicate curtailment in the order of 4- 5% compared to <0.5% in the 2013 base case. 30

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend