SLIDE 1
From NW 89 Court to SR 826 (Palmetto Expressway FDOT FPN. No: - - PowerPoint PPT Presentation
From NW 89 Court to SR 826 (Palmetto Expressway FDOT FPN. No: - - PowerPoint PPT Presentation
From NW 89 Court to SR 826 (Palmetto Expressway FDOT FPN. No: 251185-1-52-01, 405665-1-52-01 NW 25 Street-West & Viaduct Construction Purpose The purpose of this project is to improve the flow of traffic on NW 25 Street and facilitate the
SLIDE 2
SLIDE 3
Location Map NW 25 Street-West & Viaduct Construction
BEGIN PROJECT NW 89 CT. END PROJECT SR 826 NW 25th Street NW 82nd Ave. NW 87th Ave. SR 826 N
SLIDE 4
NW 25 Street-West & Viaduct Construction
Project Background:
PD&E began in 1991 and was completed in 1997 Design Phase began in 2000 and was completed in 2007 Due to High Cost of Construction Project Was Split in two
segments (East Segment From Palmetto Expressway to NW 67 Ave, and West Segment From NW 89 Ct to Palmetto Expressway)
Construction of East Segment is Ongoing and Is Expected to be
Completed in Summer 2011
SLIDE 5
NW 25 Street-West & Viaduct Construction
Proposed Improvements:
Reconstruct NW 25 Street at Grade (New Drainage, Lighting,
Signals (NW 87 Ave, NW 84 Ave, NW 82 Ave and NW 79 Ave), Landscape and ADA compliance at all Intersection)
Widening NW 25 St. from its existing configuration of five lanes
undivided to six lanes divided with wide medians.
Construct Final Segment of Viaduct Structure over NW 25
Street for truck traffic (T>15%) from NW 82 Ave. to Palmetto (SR 826)
Total Project Length 1.206 Miles
SLIDE 6
NW 25 Street-West & Viaduct Construction
From 89 Ct to West of NW 82 Ave, BEGIN PROJECT NW 89 CT. NW 25th Street
SLIDE 7
NW 25 Street-West Viaduct Construction
From NW 82 Ave to SR 826 Palmetto, END PROJECT SR 826 NW 25th Street Proposed Viaduct
SLIDE 8
Typical Roadway Section Looking East at NW 87 Ave.
SLIDE 9
Typical Viaduct Section At NW 82 Ave.
SLIDE 10
Project Benefits:
Project Benefits:
Separation of Cargo Truck and Commuter Traffic Reduced Travel Time Direct Connection to MIA Cargo Area From NW 82 Ave Increased Turning Radius on major intersection
SLIDE 11
NW 25 Street-West & Viaduct Construction
Project Issue:
Plans were Updated in 2010 to Comply With Current FDOT
Criteria
All Plan Have Been Updated and Funding is in place to begin
construction
Final Plans Shall be submitted to the Department March 2011 Plans to Tallahassee in April 2011 Plan Letting is scheduled for July 2011 Expected Construction Duration is 1250 days or 3.5 years
SLIDE 12
NW 25 Street-West & Viaduct Construction
Funding:
Cost is estimated at $70.3 Million ($44.3 roadway + $26.0
viaduct)
No Private-Private Partnership Traditional Bid Build No Stimulus Fund / Project does have ACNH Federal Funds
SLIDE 13
NW 25 Street-East Construction Update
Project Update:
Project is currently close to 90% complete Viaduct Substructure is 100% Viaduct Super-structure
- all structural steel is in place
- 36 deck pours remain to be competed