Free Bridge Area Congestion Relief Study: Construction Feasibility - - PowerPoint PPT Presentation

free bridge area congestion relief study
SMART_READER_LITE
LIVE PREVIEW

Free Bridge Area Congestion Relief Study: Construction Feasibility - - PowerPoint PPT Presentation

Free Bridge Area Congestion Relief Study: Construction Feasibility Assessment Update & Estimates July 16, 2014 Charlottesville Albemarle Metropolitan Planning Organization (CAMPO) and The Thomas Jefferson Planning District Commission


slide-1
SLIDE 1

Free Bridge Area Congestion Relief Study:

Construction Feasibility Assessment Update & Estimates

July 16, 2014 Charlottesville Albemarle Metropolitan Planning Organization (CAMPO) and The Thomas Jefferson Planning District Commission

slide-2
SLIDE 2

Feasibility Assessment Update

Process

  • Refinement of alternatives through collaboration between RDA,

TJPDC staff, and stakeholders

  • Stakeholder input solicited via e‐mail and online survey forms
  • Concept drawings and Feasibility Analysis update to reflect the

refined alternatives

2

slide-3
SLIDE 3

Alternative A‐1

Free Bridge Overpass/Expressway The original Alternative A was split into A‐1 and A‐2. Alternative A‐1 only includes construction of an elevated structure that would route two lanes of US 250 east and west bound traffic over the intersections of US 250/20 and US 250/High Street. The existing intersections and bridge will remain below the flyover structure.

slide-4
SLIDE 4

Alternative A‐1

slide-5
SLIDE 5

Alternative A‐1 Evaluation Matrix

Free Bridge Overpass/Expressway

LOW MODERATE HIGH Property Impacts X Access Impacts X Utility Impacts X Park Impacts X Trail Impacts X Railroad Impacts X Maintenance of Traffic Impacts X Bridges X Floodway Influence X Drainage Structures i.e. Box Culvert, Stormwater Management Facilities X Earthwork/Terrain X Retaining Walls X Construction Feasibility X Expected Congestion Relief @ Free Bridge X Expected Cost X

slide-6
SLIDE 6

Alternative A‐2

Jug Handle/ Left turn elimination at US250 W and High Street Alternative A‐2 includes reconfiguring the US 250 and High Street intersection to eliminate left turn movements from west bound US 250. In this configuration traffic wanting to make a left turn would pass through the intersection and make a right at Landonia Circle. A new connector road would then join Landonia Circle to River Road where a traffic light would be installed.

slide-7
SLIDE 7

Alternative A‐2

slide-8
SLIDE 8

Alternative A‐2 Evaluation Matrix

Jug Handle/ Left turn elimination at US250 W and High Street

LOW MODERATE HIGH Property Impacts X Access Impacts X Utility Impacts X Park Impacts X Trail Impacts X Railroad Impacts X Maintenance of Traffic Impacts X Bridges X Floodway Influence X Drainage Structures i.e. Box Culvert, Stormwater Management Facilities X Earthwork/Terrain X Retaining Walls X Construction Feasibility X Expected Congestion Relief @ Free Bridge X Expected Cost X

slide-9
SLIDE 9

Alternative B

Park and Ride, and Bike/Pedestrian Connections This alternative includes a new park and ride lot located at the VDOT offices (VDOT way and Richmond Road) and a hard surface trail. The trail will run parallel to the Rivanna River and then cross the river on a new bike and pedestrian bridge in the vicinity of Riverview Park. The trail will provide the

  • pportunity for making connections further downstream along the river.
slide-10
SLIDE 10

Alternative B

slide-11
SLIDE 11

Alternative B

slide-12
SLIDE 12

Alternative B Evaluation Matrix

Park and Ride, and Bike/Pedestrian Connections

LOW MODERATE HIGH Property Impacts X Access Impacts X Utility Impacts X Park Impacts X Trail Impacts X Railroad Impacts X Maintenance of Traffic Impacts X Bridges X Floodway Influence X Drainage Structures i.e. Box Culvert, Stormwater Management Facilities X Earthwork X Retaining Walls X Construction Feasibility X Expected Congestion Relief @ Free Bridge X Expected Cost X

slide-13
SLIDE 13

Alternative D‐1 & D‐2

Rivanna River Parkway Alternative D‐1 includes construction of a new road linking Route 20 with Rio

  • Road. This new road would have two vehicle travel lanes with two bike lanes

(similar to the John Warner Parkway). The intersection with Route 20 would be aligned with an extension of Olympia Drive. In addition to adding a new 2 lane connection from Route 20 to Rio Road the project would also include widening Rio Road to 4 lanes from Pen Park Lane to the John Warner Parkway intersection. Alternative D‐2 is the same as D‐1 but considers improving Elk Drive through Darden Towe Park rather than constructing a road west of the Elks Lodge and the slated development for the land parcel south of the Lodge.

slide-14
SLIDE 14

Alternative D‐1 & D‐2

slide-15
SLIDE 15

Alternative D‐1 & D‐2

slide-16
SLIDE 16

Alternative D‐1

slide-17
SLIDE 17

Alternative D‐2

slide-18
SLIDE 18

Alternative D‐1 & D‐2 Evaluation Matrix

Rivanna River Parkway

LOW MODERATE HIGH Property Impacts X Access Impacts X Utility Impacts X Park Impacts X Trail Impacts X Railroad Impacts X Maintenance of Traffic Impacts X Bridges X Floodway Influence X Drainage Structures i.e. Box Culvert, Stormwater Management Facilities X Earthwork/Terrain X Retaining Walls X Construction Feasibility X Expected Congestion Relief @ Free Bridge X X Expected Cost X

slide-19
SLIDE 19

Alternative F

Increased Lane Capacity on Free Bridge This alternative increases the number of through traffic lanes between High Street and Route 20 to three lanes in each direction. Increasing the number of lanes requires removal of existing sidewalks on Free Bridge and relocating them to a dedicated bike and pedestrian crossing immediately down river of the existing span.

slide-20
SLIDE 20

Alternative F

slide-21
SLIDE 21

Alternative F Evaluation Matrix

Increased Lane Capacity on Free Bridge

LOW MODERATE HIGH Property Impacts X Access Impacts X Utility Impacts X Park Impacts X Trail Impacts X Railroad Impacts X Maintenance of Traffic Impacts X Bridges X Floodway Influence X Drainage Structures i.e. Box Culvert, Stormwater Management Facilities X Earthwork/Terrain X Retaining Walls X Construction Feasibility X Expected Congestion Relief @ Free Bridge X Expected Cost X

slide-22
SLIDE 22

Alternative G

South Pantops Drive Connector Bridge This alternative includes a new bridge connection between New House Drive/South Pantops Drive and East High Street. The bridge would be a two lane urban style bridge with appropriate bike and pedestrian facility

  • accommodations. Additional considerations include a new intersection at High

Street aligned with Willow Drive, a new intersection at New House Drive/South Pantops Drive, and improvements to South Pantops Drive through the shopping center.

slide-23
SLIDE 23

Alternative G

slide-24
SLIDE 24

Alternative G Evaluation Matrix

South Pantops Drive Connector Bridge

LOW MODERATE HIGH Property Impacts X Access Impacts X Utility Impacts X Park Impacts X Trail Impacts X Railroad Impacts X Maintenance of Traffic Impacts X Bridges X Floodway Influence X Drainage Structures i.e. Box Culvert, Stormwater Management Facilities X Earthwork/Terrain X Retaining Walls X Construction Feasibility X Expected Congestion Relief @ Free Bridge X Expected Cost X

slide-25
SLIDE 25

Alternative I

Intersection Improvements at US 250/Route 20 & High Street This alternative consists of intersection improvements that would improve side street turning movements in addition to a west bound right turn lane from US 250 to Route 20. Additional side street lanes would be added to allow the implementation of split phase light timing. These changes have the potential to reduce collisions and improve intersection efficiency.

slide-26
SLIDE 26

Alternative I

slide-27
SLIDE 27

Alternative I Evaluation Matrix

Intersection Improvements at US 250/Route 20 & High Street

LOW MODERATE HIGH Property Impacts X Access Impacts X Utility Impacts X Park Impacts X Trail Impacts X Railroad Impacts X Maintenance of Traffic Impacts X Bridges X Floodway Influence X Drainage Structures i.e. Box Culvert, Stormwater Management Facilities X Earthwork/Terrain X Retaining Walls X Construction Feasibility X Expected Congestion Relief @ Free Bridge X Expected Cost X

slide-28
SLIDE 28

Construction Feasibility Summary

LOW MODERATE HIGH Alternative A‐1

X

Alternative A‐2

X

Alternative B

X

Alternative D

X

Alternative F

X

Alternative G

X

Alternative I

X

slide-29
SLIDE 29

Expected Congestion Relief Summary

LOW MODERATE HIGH Alternative A‐1

X

Alternative A‐2

X

Alternative B

X

Alternative D

X X

Alternative F

X X

Alternative G

X

Alternative I

X

slide-30
SLIDE 30

Expected Cost Summary

LOW MODERATE HIGH Alternative A‐1

X

Alternative A‐2

X

Alternative B

X

Alternative D

X

Alternative F

X

Alternative G

X

Alternative I

X

slide-31
SLIDE 31

Summary

Construction Feasibility Congestion Relief Cost Alternative A‐1

LOW HIGH HIGH

Alternative A‐2

HIGH LOW LOW

Alternative B

MOD LOW LOW

Alternative D

MOD LOW/MOD HIGH

Alternative F

MOD MOD/HIGH MOD

Alternative G

HIGH LOW MOD

Alternative I

HIGH LOW LOW

slide-32
SLIDE 32

Questions?

slide-33
SLIDE 33

Estimates

Preliminary Engineering

  • Estimated as a percentage of the Construction Cost using a

sliding scale from 20% for a $5 million project to 10% for a $400 million project

33

slide-34
SLIDE 34

Estimates

Right of Way and Utilities

  • RDA Right of Way Staff researched assessed real estate values to

develop a price per square foot cost

  • The square feet of right of way required was measured off of the

concept drawings based on GIS information

  • A multiplier of 2.75 was used to account for temporary easements,

permanent easements, damages, and administrative costs.

  • Individual cost assessment was performed for parcels requiring

relocation/total take.

  • RDA Utility Staff used the VDOT Project Cost Estimating System (PCES)

to estimate utility relocation costs based on field reconnaissance and utility records research

34

slide-35
SLIDE 35

Estimates

Construction

  • RDA Engineering Staff determined whether VDOT’s PCES tool or

performing a quantity take‐off was the most appropriate method for each alternative

  • PCES is a parametric estimating tool developed by VDOT that estimates

construction cost using historical price data based on certain project characteristics and measurement inputs. It’s best suited for typical roadway widening projects or new roadway construction

  • On projects not deemed suitable for PCES, RDA staff calculated quantities
  • f major construction items and used unit prices from VDOT Construction

Division’s District Wide Averages published online. Percentages for incidentals (smaller items not able to be quantified with this level of design) and contingencies were added to arrive at a final construction estimate

35

slide-36
SLIDE 36

Alternative A‐1 Estimate

Free Bridge Overpass/Expressway Preliminary Engineering $13,791,000 Right of Way $7,000,344 Construction $120,453,482 Total $141,244,826

slide-37
SLIDE 37

Alternative A‐2 Estimate

Jug Handle/ Left turn elimination at US250 W and High Street Preliminary Engineering $823,855 Right of Way $4,508,527 Construction $3,744,793 Total $9,077,175

slide-38
SLIDE 38

Alternative B Estimate

Park and Ride, and Bike/Pedestrian Connections Stone Dust Trail Option Preliminary Engineering $1,337,635 Right of Way $487,226 Construction $7,565,070 Total $9,389,931

slide-39
SLIDE 39

Alternative B Estimate

Park and Ride, and Bike/Pedestrian Connections Asphalt Trail Option Preliminary Engineering $1,461,401 Right of Way $487,226 Construction $8,265,033 Total $10,213,660

slide-40
SLIDE 40

Alternative D‐1 Estimate

Rivanna River Parkway Preliminary Engineering $6,950,000 Right of Way $9,646,828 Construction $53,424,076 Total $70,020,904

slide-41
SLIDE 41

Alternative D‐2 Estimate

Rivanna River Parkway (using Elk Drive) Preliminary Engineering $6,750,000 Right of Way $9,386,604 Construction $51,905,393 Total $68,041,997

slide-42
SLIDE 42

Alternative F Estimate

Increased Lane Capacity on Free Bridge Preliminary Engineering $1,850,000 Right of Way $7,820,216 Construction $10,874,119 Total $20,544,335

slide-43
SLIDE 43

Alternative G Estimate

South Pantops Drive Connector Bridge Preliminary Engineering $2,740,000 Right of Way $6,098,514 Construction $18,267,565 Total $27,106,079

slide-44
SLIDE 44

Alternative I Estimate

Intersection Improvements at US 250/Route 20 & High Street Preliminary Engineering $1,063,712 Right of Way $942,437 Construction $5,414,294 Total $7,420,443

slide-45
SLIDE 45

Cost Summary

PE RW CN TOTAL Alternative A‐1

$13,791,000 $7,000,344 $120,453,482

$141,244,826

Alternative D‐1

$6,950,000 $9,646,828 $53,424,076

$70,020,904

Alternative D‐2

$6,750,000 $9,386,604 $51,905,393

$68,041,997

Alternative G

$2,740,000 $6,098,514 $18,267,565

$27,106,079

Alternative F

$1,850,000 $7,820,216 $10,874,119

$20,544,335

Alternative B ‐ Paved

$1,461,401 $487,226 $8,265,033

$10,213,660

Alternative B‐ Stone Dust

$1,337,635 $487,226 $7,565,070

$9,389,931

Alternative A‐2

$823,855 $4,508,527 $3,744,793

$9,077,175

Alternative I

$1,063,712 $942,437 $5,414,294

$7,420,443

slide-46
SLIDE 46

Next Steps

  • 1. TJPDC Staff will begin the process of running alternatives

through the Regional Ecological Framework tool and Travel Demand model

  • 2. Results of this process will be discussed at the next meeting in

September

  • 3. Stakeholders can expect information about how alternatives

would impact the natural environment and regional traffic conditions

  • 4. Final Report to be completed October 31, 2014

46

slide-47
SLIDE 47

Contact Information:

Wood Hudson Senior Environmental Planner Thomas Jefferson Planning District Commission (434) 979‐7310 whudson@tjpdc.org

Questions?