FOLLY ROAD MULTI-USE PATH Ellis Creek to Prescott Street October 2018 CONTENTS Review Alternatives Challenges Areas of Interest Decision Matrix Recommendation REVIEW FUNDING SEGMENT OPTIONS $ 9.450M $2.675M Cost of Sidewalk Cost of


  1. FOLLY ROAD MULTI-USE PATH Ellis Creek to Prescott Street October 2018

  2. CONTENTS Review Alternatives Challenges Areas of Interest Decision Matrix Recommendation

  3. REVIEW FUNDING SEGMENT OPTIONS $ 9.450M $2.675M Cost of Sidewalk Cost of Shared-Use Section Roads Length Completion Path TOTAL TARGETED + TOTAL AVAILABLE AVAILABLE FUNDS FUNDS 1 Ellis Creek to Prescott Street 6,800’ $ 2.3M $ 5.3M Prescott Street to George L. 2 1,800’ $ 1.0M $ 2.2M Griffith Boulevard George L. Griffith Blvd to 3 2,050’ ---- $ 1.6M SEGMENT 1 Grimball/Fort Johnson Road Grimball/Fort Johnson Road 4 3,600’ ---- $ 2.5M to Rafeal Lane MOST MOST Rafeal Lane to Sol Legare 5 8,800’ $ 2.3M $ 4.3M Road traffic accidents business Total 23,050’ $ 9.7M $ 15.9M (2015-2017) density WHAT WE’VE DONE Grant application for funding 2 nd 2 nd • Defined first priority • population household Completed existing condition survey • density density Developed alternatives •

  4. A L T 5’ Sidewalk 1 5’ 12’ ~2’ ~3.5’ curb & sidewalk bike lane travel lane gutter A L T 8’ Sidewalk 2 12’ 8’ ~2’ ~3.5’ curb & sidewalk bike lane travel lane ALTERNATIVES gutter A L T Multi-Use Path 3 + Bike Lane 12’ 5’ 12’ ~2 ~3.5’ curb & multi-use path planting bike lane travel lane gutter A L T Multi-Use Path, 4 No Bike Lane 12’ 5’ ~2’ 12’ ROW Line curb & planting travel lane multi-use path gutter

  5. CHALLENGES

  6. RIGHT-OF-WAY Before 1962 Folly Road was two • lanes with a 50’ ROW, then SCDOT expanded to a ~70’ ROW Generally 35’ feet along the west • side of Folly Road 32.5’ pavement • 1.5’ curb & gutter • Approximate cost of ROW purchase • = $40/sq ft

  7. UTILITIES/STORMWATER Utility poles are a major challenge • along the corridor for each alternative There will not be a significant impact • on below ground utilities Telephone pedestals, gas • monuments, backflow preventers would need to be relocated Existing site drainage would be • impacted for 3 businesses Eliminating existing bike lane • requires upgrades to Folly Road drainage system

  8. MONUMENTS/SIGNAGE Most businesses along Folly Road • have signs that are typically at ROW edge Signs are expensive and difficult • to relocate Relocation Costs: • Monuments signs: $10,000 • Post signs: $5,900 • Traffic signs: $500 •

  9. SEGMENT 1 Areas of Interest Ellis Creek to Prescott Street Sumter’s Doctor’s Landing Care Live Oak 4 1 Roadside Seafood 2 3

  10. SEGMENT 1 Doctor’s Care Ellis Creek to Prescott Street Doctor’s Care 1

  11. A L T 5’ Sidewalk Doctor’s Care 1 5’ Sidewalk Existing Conditions

  12. A L T 8’ Sidewalk Doctor’s Care 2 8’ Sidewalk Existing Conditions

  13. A L T Multi-Use Path + Bike Lane Doctor’s Care 3 Multi-Use Path + Bike Lane Existing Conditions

  14. A L T Multi-Use Path, No Bike Lane Doctor’s Care 4 Multi-Use Path, No Bike Lane Existing Conditions

  15. SEGMENT 1 Live Oak Tree Ellis Creek to Prescott Street Live Oak 2

  16. A L T 5’ Sidewalk Live Oak Tree 1 5’ Sidewalk Existing Conditions

  17. A L T 8’ Sidewalk Live Oak Tree 2 8’ Sidewalk Existing Conditions

  18. A L T Multi-Use Path + Bike Lane Live Oak Tree 3 Multi-Use Path + Bike Lane Existing Conditions

  19. A L T Multi-Use Path, No Bike Lane Live Oak Tree 4 Multi-Use Path, No Bike Lane Existing Conditions

  20. SEGMENT 1 Roadside Seafood Ellis Creek to Prescott Street Roadside Seafood 3

  21. A L T 5’ Sidewalk Roadside Seafood 1 5’ Sidewalk Existing Conditions

  22. A L T 8’ Sidewalk Roadside Seafood 2 8’ Sidewalk Existing Conditions

  23. A L T Multi-Use Path + Bike Lane Roadside Seafood 3 Multi-Use Path + Bike Lane Existing Conditions

  24. A L T Multi-Use Path, No Bike Lane Roadside Seafood 4 Multi-Use Path, No Bike Lane Existing Conditions

  25. SEGMENT 1 Sumter’s Landing Ellis Creek to Prescott Street Sumter’s Landing 4

  26. A L T 5’ Sidewalk Sumter’s Landing 1 5’ Sidewalk Existing Conditions

  27. A L T 8’ Sidewalk Sumter’s Landing 2 8’ Sidewalk Existing Conditions

  28. A L T Multi-Use Path + Bike Lane Sumter’s Landing 3 Multi-Use Path + Bike Lane Existing Conditions

  29. A L T Multi-Use Path, No Bike Lane Sumter’s Landing 4 Multi-Use Path, No Bike Lane Existing Conditions

  30. DECISION MATRIX CHALLENGE UTILITIES/ COST MONUMENTS/ ROW STORMWATER ESTIMATE SIGNAGE SEGMENT 1 A L T Ellis Creek to Prescott Street 1 5’ Sidewalk A L T RISK PROFILE 8’ Sidewalk 2 HIGH LIKELIHOOD A L T Multi-Use Path MEDIUM 3 + Bike Lane LOW A L T Multi-Use Path 4 LOW No Bike Lane MEDIUM HIGH IMPACT TO COSTS

  31. DECISION MATRIX CHALLENGE UTILITIES/ COST MONUMENTS/ ROW STORMWATER ESTIMATE SIGNAGE SEGMENT 1 A L T Ellis Creek to Prescott Street $ 978,162 1 5’ Sidewalk A L T RISK PROFILE 8’ Sidewalk $ 1,425,196 2 HIGH LIKELIHOOD A L T Multi-Use Path MEDIUM $ 3,294,520 3 + Bike Lane LOW A L T Multi-Use Path $ 4,006,201 4 LOW No Bike Lane MEDIUM HIGH IMPACT TO COSTS

  32. RECOMMENDATION A L T 8’ Sidewalk 2 12’ 8’ ~2’ ~3.5’ curb & sidewalk bike lane travel lane gutter

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.