Lo Long ng Ran Range ge Fac acilities ilities Plan lan FOL OLLOW-UP UP
School District No. 8 Slocan Valley Family of Schools WE Graham Elementary-Secondary School June 19, 2018
FOL OLLOW-UP UP School District No. 8 Slocan Valley Family of - - PowerPoint PPT Presentation
Lo Long ng Ran Range ge Fac acilities ilities Plan lan FOL OLLOW-UP UP School District No. 8 Slocan Valley Family of Schools WE Graham Elementary-Secondary School June 19, 2018 Whats Happened Since Fall 2017? September 2017
School District No. 8 Slocan Valley Family of Schools WE Graham Elementary-Secondary School June 19, 2018
Surplus Transfer to Local Capital
DESK, Wildflower & Board Office Transition
Disposal: Crawford Bay Hall Property Complete
Disposal: Creston Education Centre in Principle
MOE Response to 2018-2019 Capital Plan
Press Release: Sale of Properties
2019-2020 Capital Plan Submission to MOE
On May 3, 2016, advanced Draft 2 of its Facilities Plan by board motion;
Between May 4 and July 4, 2016, considered the closure of Winlaw Elementary School; and
was successful in securing Rural Education Enhancement Funding for 2017-2018 and subsequent school years;
Valley Family of Schools shall be status quo with no changes to school
$ 51,105
$ 98,122
$ 66,221
$ 18,116
$ 36,391
$110,000
$ 60,000
$159,262
$ 23,966
$125,000
$ 50,000
$ 42,569
$576,000
$557,179
$ 50,000
Central Education Centre (K-12)
LV Rogers Secondary (10-12) Hume Elementary (K-9)
Central Education Centre Third Floor
Central Education Centre Second Floor
570 Johnstone Road, Nelson
Central Education Centre Third Floor
content/uploads/2016/10/18- Apr-4-Property-Disposals.pdf
School, Nelson BC
Elementary School, Nelson BC
Salmo BC
Bay BC
1. 1.
Salmo mo Seco conda dary y Expansion pansion
2.
Blewett Elementary Expansion
3.
South Nelson Elementary Replacement
hat t is the Purpo pose se of the e Rural ral Educ ducation ation Enh nhancem ancement ent Fund nd?
communities (less than 15,000 population) for community viability and sustainability
funding supplements already in place
Program, and school districts should indicate through their capital plans
Education Enhancement Fund
20 40 60 80 100 120 140 11/12 12/13 13/14 14/15 15/16 16/17 17/18 18/19 19/20 20/21 21/22 22/23 23/24 24/25 25/26 26/27 27/28
Enrollment School Year
Winlaw Elementary Enrolment Projections STATUS QUO
Jun-18 Feb-16 Linear (Jun-18)
180 190 200 210 220 230 240 11/1212/1313/1414/1515/1616/1717/1818/1919/2020/2121/2222/2323/2424/2525/2626/2727/28
Enrollment School Year
Brent Kennedy Elementary Enrolment Projections STATUS QUO
Jun-18 Feb-16 Linear (Jun-18)
10 20 30 40 50 60 70 80 90 11/1212/1313/1414/1515/1616/1717/1818/1919/2020/2121/2222/2323/2424/2525/2626/2727/28
Enrollment School Year
WE Graham Elem-Sec Enrolment Projections STATUS QUO
Jun-18 Feb-16 Linear (Jun-18)
50 100 150 200 250 300 350 400 11/1212/1313/1414/1515/1616/1717/1818/1919/2020/2121/2222/2323/2424/2525/2626/2727/28
Enrollment School Year
Mount Sentinel Sec Enrolment Projections STATUS QUO
Jun-18 Feb-16 Linear (Jun-18)
0% 20% 40% 60% 80% 100% 120% 140% 11/12 12/13 13/14 14/15 15/16 16/17 17/18 18/19 19/20 20/21 21/22 22/23 23/24 24/25 25/26 26/27 27/28
Capacity Utilization School Year
Winlaw Elementary Capacity Utilization
Capacity Utilization
94% 96% 98% 100% 102% 104% 106% 108% 11/1212/1313/1414/1515/1616/1717/1818/1919/2020/2121/2222/2323/2424/2525/2626/2727/28
Capacity Utilization School Year
Brent Kennedy Elementary Capacity Utilization
Capacity Utilization
0% 5% 10% 15% 20% 25% 30% 35% 40% 11/12 12/13 13/14 14/15 15/16 16/17 17/18 18/19 19/20 20/21 21/22 22/23 23/24 24/25 25/26 26/27 27/28
Capacity Utilization School Year
WE Graham Elem-Sec Capacity Utilization
Capacity Utilization
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Year 11/1212/1313/1414/1515/1616/1717/1818/1919/2020/2121/2222/2323/2424/2525/2626/27
Capacity Utilization School Year
Mount Sentinel Sec Capacity Utilization
Capacity Utilization
106% 105% 35% 71% 73% 109% 106% 23% 72% 71% 119% 105% 20% 80% 74% 116% 105% 21% 76% 76% WI N LAW B REN T KEN N ED Y WE GRAHAM M OU N T SEN TI N EL TOTAL
CAPACITY UTILIZATION SCHOOL
SLOCAN SCHOOLS CAPACITY UTILIZATION
17/18 20/21 23/24 27/28
November 2014 February 2016 October 2017 June 2018 0% 10% 20% 30% 40% 50% 60% 70% 37% 15% 14% 11% 48% 25% 30% 31% 65% 45% 41% 32% 66% 59% 40% 31% FCI Site
FACILIT Y CONDITION INDEX: SLOCAN VALLEY
November 2014 February 2016 October 2017 June 2018
November 2014 February 2016 October 2017 June 2018
1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 5,000 Winlaw Brent Kennedy WE Graham Mount Sentinel 1,034 1,027 955 1,514 1,310 1,741 2,029 4,382 1,856 3,153 2,850 4,637 1,877 4,078 2,778 4,501 Costs ts (1000's 00's) Site
DEFERRED MAINTENANCE COSTS (1,000'S): SLOCAN VALLEY
November 2014 February 2016 October 2017 June 2018
Erickson staffs
gifted etc..)
upgrading facilities
the curriculum must be student- centred and flexible, and maintain a focus on literacy and math skills, while supporting deeper learning
has been redesigned to provide greater flexibility for teachers, while allowing space and time for students to develop their skills and explore their passions and interests.