FNQROC Proposed amendments to FNQROC Development Manual (Water and - - PowerPoint PPT Presentation

fnqroc
SMART_READER_LITE
LIVE PREVIEW

FNQROC Proposed amendments to FNQROC Development Manual (Water and - - PowerPoint PPT Presentation

FNQROC Proposed amendments to FNQROC Development Manual (Water and Waste Water Sections only) Presented by: Darlene Irvine, FNQROC Executive Officer 1. Welcome and Introductions 2. Overview of amendments to the manual (Water and Sewer only)


slide-1
SLIDE 1

FNQROC

Proposed amendments to FNQROC Development Manual (Water and Waste Water Sections only)

Presented by: Darlene Irvine, FNQROC Executive Officer

slide-2
SLIDE 2
  • 1. Welcome and Introductions
  • 2. Overview of amendments to the manual

(Water and Sewer only)

  • 3. CTM Code presentation - CRC
  • 4. Focus in on areas / sections of interest
  • 5. Amendments to Standard Drawings
slide-3
SLIDE 3
  • Search function is included on the FNQROC website
  • New PDF versions will have hyperlinked table of contents
  • Removed ‘Operational Works’ to limit confusion and referred to Planning Act

definition of ‘development’ in the user guide.

slide-4
SLIDE 4
  • While we’ve recommended to link the operational checklist I believe this will

go as IDAS Form 6 does this.

  • Council may request (during the assessment) the digital ACAD file of the

water and sewerage reticulation drawings

slide-5
SLIDE 5
  • Documents to be provided prior to Pre-Start:
  • Copy of ‘For construction’ drawings
  • Pavement Design
  • As Constructed submission; included DWG file
  • Early plan sealing requests will only be considered for those stages of

development nominated in the development plan. Parts of a stage will not be considered for early plan approval.

  • Appendix P – reduced requirement for as constructed attributes and split

into compulsory and only required if differed to FNQROC specs

slide-6
SLIDE 6
  • Replaced reference to WSA with CTM Water Alliance Design and

Construction Code

  • CTM Code referenced in the manual
  • CRC only – changes to Average Daily consumption – from 500 to 400 L/EP/D
  • Adopted the Darcy-Weisback method over the Hazen-Williams method
  • Creek crossings included in design Criteria:
  • Ck crossings are to be in DICL or PE
  • Arborist report to assess the risk associated with trees within 10m either side of the

water main alignment.

  • New section for building over or near water infrastructure
  • Marker balls to be used where water reticulation is laid on non-standard

alignment

slide-7
SLIDE 7
  • All irrigation connections to councils water network must be completed by

council at the developers cost. (if permitted, an approved subcontractor with council supervision)

  • Pump Stations – at councils discretion - the provision of a three phase inlet

to allow the connection of a mobile generator unit.

  • Factory acceptance testing is to be undertaken and the designer is to

arrange a suitable time and date with Council for testing before the switchboard is installed at site.

  • Amendments made to CRC local government specific – D6.17 clause

removed.

slide-8
SLIDE 8
  • Incorporation of CTM
  • Vacuum and pressure sewer schemes are still considered unconventional

infrastructure

  • New section added for building over or near sewerage infrastructure
  • Amendments made to value in table 7.2, and 7.3
  • Property connections into maintenance shafts are not permitted unless in

circumstances approved by council

  • On-site sewerage – new clause – the min separation distance between on-

site facilities and water mains is to be 10 meters.

  • D7.16 General – new clause – where the calculated C1 value is less than 3.5

the pump operation mode is to be duty/assist. 3.5 and greater – is to be duty/standby – needs to be confirmed with Council.

slide-9
SLIDE 9
  • Well washers not required for CRC
  • The requirements of fencing of pump stations is to be confirmed with

council.

  • Standby generator is to be contained within a roof structure and wording to

include three phase inlet at council discretion.

  • We ask that the design of the pump station considers measures to prevent

damage from vandals and restrict un-authorised access

  • Factory acceptance testing with council before the switchboard is installed

at site.

  • Table 7.14 – pump motor drive design parameters have been amended, a

new item related to sizing of overflow pipe added and we’ve replaced Hazen Williams formula with Darcey-Weisbach formula

slide-10
SLIDE 10
  • Variable frequency drives should be considered for pump stations that

discharge into a common rising main.

  • Table 7.15 – replaced Hazen Williams formula with Darcey-Weisbach

formula

  • Appendix A – contains addendums to the CTM Code
  • Appendix B – contains addendums to WSA Code
  • Amendments to CRC local government specific – deleted clauses D7.13 and

D7.25

slide-11
SLIDE 11
  • CTM Alliance Water Service Design and Construction Code incorporated
  • Reference documents – WSA 2002 version of Dual Water Supply Systems
  • Included reference to a number of AS
  • Included stainless steel as a material
  • Clarification re ductile iron
  • Included the ability to use reglass material
slide-12
SLIDE 12
  • CTM Alliance incorporated
  • Included ability to use reglass in bedding
  • Included WSA construction tolerances
  • Appendix A – references to SEQ Standard drawings
  • CRC Local Government specific – delete clauses S6.03, S6.21, S6.23
slide-13
SLIDE 13
  • 43 standard drawings amended or new – available for viewing
slide-14
SLIDE 14
  • Reminder – we take submissions to amend the manual at any time – these

are collated for each review.

  • Submission on the proposed amendments are due 22 September –

d.irvine@fnqroc.qld.gov.au

  • Seeking legal advice to make the review process quicker and simpler.

Hand over to CRC re CTM code.