Flying Colors How Teamwork and Technology Drove the Success of - - PowerPoint PPT Presentation

flying colors
SMART_READER_LITE
LIVE PREVIEW

Flying Colors How Teamwork and Technology Drove the Success of - - PowerPoint PPT Presentation

Flying Colors How Teamwork and Technology Drove the Success of Hinghams Route 3A Road Diet Pilot Program Corey OConnor, PE, Traffic & Safety Engineer Pamela Haznar, PE, Project Development Engineer David Giangrande, PE President


slide-1
SLIDE 1

Flying Colors

How Teamwork and Technology Drove the Success of Hingham’s Route 3A Road Diet Pilot Program

Corey O’Connor, PE, Traffic & Safety Engineer Pamela Haznar, PE, Project Development Engineer David Giangrande, PE President Design Consultants, Inc.

slide-2
SLIDE 2

Overview

2

  • Motivation
  • Dated existing conditions/geometry
  • Lack of multimodal equity
  • Safety and efficiency concerns
  • Problem
  • Needed to validate modeling & provide proof the lane reduction would work
  • Approach
  • Modeling
  • Real-Time testing
  • Pilot Study!
  • Goals
  • Validate models
  • Build Consensus (not necessarily unanimity)
  • Avoid unnecessary design/construction expense
slide-3
SLIDE 3

Agenda

  • Background & Process
  • Project Need
  • Modeling
  • Cooperation
  • Theory & Design
  • Execution
  • Results
  • Post-Program

3

slide-4
SLIDE 4

Background & Process

4

Hingham Harbor Nantasket Beach

slide-5
SLIDE 5

Background & Process

  • 2012: Community voices concerns on safety, speed, lack of connectivity
  • June 2013: MassDOT Road Safety Audit
  • October 2014: Hingham & Hull request a CTPS Corridor Study
  • April 2015: Hingham Town Meeting funds Engineering Services
  • February 2016: CTPS Study of 3A/GW Blvd Complete
  • 2016: Design Team begins work on 3A/Summer St alternatives
  • Spring 2017: Start of public discussion of plans (results of traffic analysis,

crash history and proposed pilot)

  • Summer 2017: Considered Pilot Road Diet; however, additional planning

and resources were required

  • Fall 2017-March 2018, working with Hull and Cohasset, the project was

refined: included Technical Discussions, Collaboration Efforts, Logistics' Planning- obtained state approvals, established Operational Review process

  • Summer 2018: Pilot Program implementation

5

slide-6
SLIDE 6

Need - Speeds

6

slide-7
SLIDE 7

Need - Crashes

7

slide-8
SLIDE 8

Need – Multimodal Access

Summer Street in the Residential Area

slide-9
SLIDE 9

Need

9

slide-10
SLIDE 10

Modeling – Proof of Concept

10

slide-11
SLIDE 11

Modeling – Simulation

Vissim Simulation Video (Eastbound)

11

slide-12
SLIDE 12

Modeling – Projections (Pilot Program)

Road Segment Existing (4-lane) in Seconds Potential (2-Lane) Difference in seconds Percent Difference Eastbound: From North St. to George Washington Blvd. 135.6 167.0 31.4 23.2% Westbound: From Washington George Blvd. to North St. 143.0 149.8 6.8 4.7%

Saturday Mid-day

Differences in Corridor Travel Time under Existing (4-lane) and Potential (2-Lane) Measured by computer Modeling

Travel Time

  • The computer modeling indicates that there is no significant increase in travel time.
  • Traffic counters and measuring devices will be installed during the proposed pilot to

quantity spillover traffic (alternate route traffic & spillover effects on other facilities and neighborhoods)

Capacity Results

12

slide-13
SLIDE 13

Cooperation

  • Public Safety (Cohasset, Hull & Hingham)
  • MassDOT

» Taunton District 5 (Maintenance, Traffic, Engineering, Project Management, etc.) » Boston Office (Traffic, Engineering, Project Managers, etc.)

  • Boston Region MPO

» CTPS (Central Transportation Planning Staff)-Authors of the original corridor study)

  • Metropolitan Area Planning Council (MAPC)
  • DCI (Design Consultants Inc.): Engineering firm hired by Hingham
  • Synchro 9 from Trafficware to build the corridor models to

evaluate the various alternatives being considered

  • SIDRA Intersection 7 software to evaluate the roundabout

alternatives.

  • Kittelson & Associates – MassDOT Consultant

» Vissim Analysis (Traffic modeling software & simulation)

13

slide-14
SLIDE 14

Cooperation

  • On November 20, 2017, and January 17, 2018 - Hingham

safety personnel meet with Hull and Cohasset safety personal.

  • Consensus - Safety officials from all three towns continue to

work together and will continue to meet and discuss.

  • Consensus - Continue to work to develop a more all-

encompassing evacuation plan

14

slide-15
SLIDE 15

Cooperation

The Access Permit between the Town of Hingham and MassDOT’s Highway Division that:

  • Established protocol for setup and takedown
  • Named responsible acencies and individuals
  • Identified thresholds for success or failure

15

Conditions of Access Permit

slide-16
SLIDE 16

Cooperation – Emergency Removal

slide-17
SLIDE 17

Cooperation – Capacity

17

WB direction summarized

Scenario when all beach traffic were to hit the George Washington Blvd and Rockland intersection at once Methodology:

  • Obtain the throughput traffic

point right after Rockland Street/GW Blvd intersection (please see below)

  • WB traffic entering the

network was increased to generate oversaturated conditions throughout the simulation

  • The data collection point

shown below was used to get the total number of vehicles that were able to go through the road diet section. Simulation Results:

  • 10 simulation run
  • WB throughput around

1,450 vehicles per hour per lane.

slide-18
SLIDE 18

Theory & Design

18

Pilot Layout Plan

slide-19
SLIDE 19

Theory & Design

Eastbound out of Rotary

19

slide-20
SLIDE 20

Execution

ITS Technologies

20 PTZ Camera Traffic Sensor Message Board Live Travel Time ITS Management Software

slide-21
SLIDE 21

Execution

Intelligent Transportation System (ITS)

21

slide-22
SLIDE 22

Execution

Traffic Counter Locations

22

slide-23
SLIDE 23

Execution

Data Collections

23

  • Pilot Installed
  • May 20 (Begin acclimation period)
  • Pilot Data
  • Thursday, July 12 (AM & PM)
  • Saturday, July 14 (10 am to 6 pm)
  • Pilot Removed
  • July 26 (Acclimation period)
  • Control Data
  • Thursday, August 9 (AM & PM)
  • Saturday, August 11 (10 am to 6 pm) – inclement weather
  • Saturday, August 18 (10 am to 6 pm)
slide-24
SLIDE 24

Results

  • Traffic Volume Changes
  • No measurable increase
  • Speed (Post-Pilot and Pilot Study Periods)
  • Reduction in average speed of 3.0-4.2 MPH for all peaks

and directions

  • Travel Time
  • Increased between 24 seconds and 48 seconds

24

slide-25
SLIDE 25

Results

  • Diversion
  • No major traffic shift to any of the 3 diversion routes
  • Bluetooth matches: 1000 vehicles on primary route and

approximately 100 on optional routes

  • Level of Service
  • No changes in the level of service due to volume increases
  • Crash Data
  • No reported accidents within the pilot study corridor

25

slide-26
SLIDE 26

Results

Drone View of Pilot Program – Video

26

slide-27
SLIDE 27

Post-Pilot Status (Spring 2019)

  • Outreach: Many meetings with communities,
  • rganizations
  • Town of Hull, Hingham 3A Task Force, etc.
  • 25% Design Submitted
  • Transportation Improvement Plan (TIP)
  • Preferred Project List

27

slide-28
SLIDE 28

Questions

slide-29
SLIDE 29

Thank You!

Roger Fernandes, Town of Hingham fernandesR@Hingham-MA.gov David Giangrande, Design Consultants, Inc. (DCI) dgiangrande@dci-ma.com Pamela Haznar, MassDOT pamela.haznar@dot.state.ma.us Corey O’Connor, MassDOT corey.oconnor@dot.state.ma.us

29