Flexible Infrastructure Qualification World Maritime Technology - - PowerPoint PPT Presentation

flexible infrastructure
SMART_READER_LITE
LIVE PREVIEW

Flexible Infrastructure Qualification World Maritime Technology - - PowerPoint PPT Presentation

Flexible Infrastructure Qualification World Maritime Technology Conference November, 2015 Agenda Project Background/Overview Technical Approach Shock Testing Review Next Steps 2 Team Members Ingalls Shipbuilding Project


slide-1
SLIDE 1

Flexible Infrastructure Qualification

November, 2015

World Maritime Technology Conference

slide-2
SLIDE 2

Agenda

  • Project Background/Overview
  • Technical Approach
  • Shock Testing Review
  • Next Steps

2

slide-3
SLIDE 3

Team Members

  • Ingalls Shipbuilding – Project Lead

– Sean Murphy, Sara Trawick, Davida Cunningham, Adam McDowell, Ron McClellan, John Walks

  • Newport News Shipbuilding

– Glenn Dorsey, Don Slack, Matt Tilley

  • NTS

– Mike Poslusny

  • Hilti

– Jessica Galassie

  • SCRA

– Mary Saady, Project Manager

  • NASSCO

– Dan Sfiligoi, Project Technical Representative

3

slide-4
SLIDE 4

What Is Flexible Infrastructure/Benefits

  • Flexible Infrastructure is a system of

systems that will provide capabilities for rapid space changes without the use of “hot work”. Benefits:

  • Maximizes time for technology

development prior to equipment installation during construction outfitting

  • Eliminates cost and schedule impacts

associated with the traditional conflicts from re-work and change orders during new construction

  • Eases compartment reconfiguration to

support changing missions and lifecycle refresh of electronic components

4

slide-5
SLIDE 5

Flexible Infrastructure Design Elements

  • Deck Track System

– 3 heights for various applications

  • 12” – high track
  • 9” – mid track
  • 6” – low track
  • Bulkhead Track System
  • Overhead Track System
  • Portable Stanchions and Bulkheads
  • Under Deck Ventilation

– Used with 12” Deck Track System and overhead track

  • Flexible Lighting
  • Flexible Power

5

Design elements can be individually integrated

slide-6
SLIDE 6

FI Component Overview

6

OVERHEAD TRACK SYSTEM BULKHEAD TRACK SYSTEM DECK TRACK SYSTEM

SHIP STRUCTURE DECK TRACK WELDED STUD TRACK FITTING EQUIPMENT ENCLOSURE SHIP STRUCTURE DECK TRACK WELDED STUD TRACK FITTING EQUIPMENT ENCLOSURE MEDIUM DUTY FITTINGS LIGHT DUTY FITTING

PORTABLE STANCHIONS ATTACH TO OVERHEAD TRACK WITH A STEEL SLIP JOINT MOUNTED TO THE OVERHEAD TRACK.

Bulkhead Track

slide-7
SLIDE 7

Goals

  • The project goals are to:

– Qualify all structural elements of FI to demonstrate compliance with shock and vibration requirements of Navy surface combatants and amphibious assault ships – Qualify as many non-structural elements of FI to the same shock and vibration requirements as budget allows

  • Project is success driven
  • Assumes timely approval of test procedures by NAVSEA
  • Assumes passing of all tested flexible infrastructure elements
  • Assumes timely approval and qualification of test results by NAVSEA

7

slide-8
SLIDE 8

Key Elements of Test

  • Test Classification and Details
  • Test Specimens
  • Acceptance Criteria

8

slide-9
SLIDE 9

Shock Qualification

  • Previous FI qualification for Carrier

Gallery Deck installation

– Carrier Gallery Deck qualification requires a test at 8-10 Hz

  • Most of our possible FI installation

locations are deck mounted.

– Require a qualification test at 25 Hz (Covers deck mounted requirements for all Surface Combatants and Amphibs)

  • Some bulkheads are hull mounted.

(Main Watertight Bulkheads, 40 Foot Bulkhead)

– Require a qualification test above 37 Hz

9

Hull, Deck, & Shell Mounting Locations per NAVSEA 0908-LP-000-3010 Rev. A and MIL-S-901D

slide-10
SLIDE 10

Test Classification and Details

Test Specification, Classification and Details

  • Applicable Specification: MIL-S-901D
  • Test Category: Heavy Weight
  • Mounting Locations: Deck
  • Shipboard Mounting Plane Represented During Test: Back Mounted or

Overhead

  • Mounting Orientation of item relative to ship’s fore-and-aft axis: Vertical

Axis Specified

10

slide-11
SLIDE 11

Shock Testing

  • Two barges were tested

– Five pedestals, bulkhead track setups – Overhead track setup

  • Five shots, per MIL-S-901D, with one to simulate a rotation of the
  • verhead track
  • Testing took place at NTS in Rustburg, VA the week of July 6-10, 2015

11

slide-12
SLIDE 12

Pedestal Layout on Barges

Barge 1 Barge 2

slide-13
SLIDE 13

Example: Pedestal 1, Side 4 – Before Shots

slide-14
SLIDE 14

Pedestal 1, Side 4 – After Shots

slide-15
SLIDE 15

General Failure Criteria

  • Deformation or twisting of mount or attachment method is not considered

a failure.

  • For overhead track, the following instances are considered failures:

– Dummy mass separation from the track – Light duty fitting separation from the track – Shearing of the bolts or studs – Any breakage of flat bar

  • For bulkhead track, the following instances are considered failures:

– Dummy mass separation from the track – Saddle nut separation from the track – Shearing of the bolts or studs

  • Slippage of the saddle nuts of one inch or less on vertical track pieces

shall not be considered a failure.

slide-16
SLIDE 16

Test Summary

  • Five barge shots performed and various distances
  • The majority of the components survived
slide-17
SLIDE 17

Bulkhead track failures

  • Bulkhead track with dummy

masses that failed

  • All dummy masses failed by

detaching itself from the track.

slide-18
SLIDE 18

Stud and Track failures

slide-19
SLIDE 19

Pipe Hanger Failure

slide-20
SLIDE 20

Next Steps

  • Have a working session and shock brief with Tech Warrant Holders

– Discuss testing

  • Results
  • Qualification Process
  • Development of the Vibration Test Procedure
  • Vibration Testing
  • Report Generation (both Shock and Vibration)
  • Implementation plan for ships

20