IRIS – Integrated European Industrial Risk Reduction System CP-IP 213968-2
Final Scientific Progress
Helmut Wenzel
Vienna, March 2012
Final Conference
What we have achieved
Final Conference Final Scientific Progress What we have achieved - - PowerPoint PPT Presentation
IRIS Integrated European Industrial Risk Reduction System CP-IP 213968-2 Final Conference Final Scientific Progress What we have achieved Helmut Wenzel Vienna, March 2012 Innovation Highlights Integrated European Industrial Risk
IRIS – Integrated European Industrial Risk Reduction System CP-IP 213968-2
Helmut Wenzel
Vienna, March 2012
What we have achieved
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Innovation Highlights
Accumulated Energy Function for SHM (WP7) IRIS Risk Paradigm (WP6) Standard Degradation Curve (WP3) EQVIS simulation and crisis management platform (IT) Integrated Decision Support System (WP7) LCA safety assessments concept (after NJ202 Demo) Vibration mitigation equipment (AVA, WP2) New approach to tailing pond safety (WP4) Model based SHM system (WP5)
Results ready for industrial application
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Virtual Doctor
Nerves Pain Data Virtual Pain
Basic Idea
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Innovation Highlights
Accumulated Energy Function for SHM (WP7) IRIS Risk Paradigm (WP6) Standard Degradation Curve (WP3) EQVIS simulation and crisis management platform (IT) Integrated Decision Support System (WP7) LCA safety assessments concept (after NJ202 Demo) Vibration mitigation equipment (AVA, WP2) New approach to tailing pond safety (WP4) Model based SHM system (WP5)
Results ready for industrial application
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Major Achievements
IRIS Damage Detection
Integration Normalization Environment
Temperature Radiation Added Loads Forced Input Strain
Accumulated Energy Function
Measurement Trend Analysis
Temperature Radiation Added Loads Forced Input Strain
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Verification in the Field
Bridge S101, December 2008
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management ETPIS, May 2010
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management ETPIS, May 2010
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Proof of Concept
Accumulated Energy Function
IRIS – Integrated European Industrial Risk Reduction System CP-IP 213968-2
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Checking period: 1997–now Risk Level: low
Undamaged
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Innovation Highlights
Accumulated Energy Function for SHM (WP7) IRIS Risk Paradigm (WP6) Standard Degradation Curve (WP3) EQVIS simulation and crisis management platform (IT) Integrated Decision Support System (WP7) LCA safety assessments concept (after NJ202 Demo) Vibration mitigation equipment (AVA, WP2) New approach to tailing pond safety (WP4) Model based SHM system (WP5)
Results ready for industrial application
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
The IRIS Risk Paradigm Time as additional Parameter
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Innovation Highlights
Accumulated Energy Function for SHM (WP7) IRIS Risk Paradigm (WP6) Standard Degradation Curve (WP3) EQVIS simulation and crisis management platform (IT) Integrated Decision Support System (WP7) LCA safety assessments concept (after NJ202 Demo) Vibration mitigation equipment (AVA, WP2) New approach to tailing pond safety (WP4) Model based SHM system (WP5)
Results ready for industrial application
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Comparative Structural Inspection
D.O.T. DISK DIN 1076 RVS 13.03.11
safe and operational (minor repair) safe and operational unsafe reduced safety and operability repair demanded safe and useable during repair safe − indicating reduced
USA Netherlands Germany Austria
9 1 2 3 4 5 6 7 8 1,0 - 1,4 3,5 - 4,0 3,0 - 3,4 2,5 - 2,9 2,0 - 2,4 1,5 - 1,9 1 6 5 4 3 2 1 6 5 4 3 2
Japan Condition
A E D C B
International Harmonisation
WP7
Online Monitoring
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Observed Service Life of structures
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Innovation Highlights
Accumulated Energy Function for SHM (WP7) IRIS Risk Paradigm (WP6) Standard Degradation Curve (WP3) EQVIS simulation and crisis management platform (IT) Integrated Decision Support System (WP7) LCA safety assessments concept (after NJ202 Demo) Vibration mitigation equipment (AVA, WP2) New approach to tailing pond safety (WP4) Model based SHM system (WP5)
Results ready for industrial application
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Timeline 07:30 07:37 Creating the Scenario Earthquake in EQvis
IRIS 2011 - Demonstration
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Timeline 07:30 07:37 07:42 Scenarios finished and damages computed 08:04
IRIS 2011 - Demonstration
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
The route of the Building Inspection Team
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Overview of the route of the Building Inspection Team
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Timeline 07:30 07:37 07:42 08:04 08:17 09:26 09:58 11:55 14:11 15:32
IRIS 2011 - Demonstration
The Bridge Inspection Team completes the measurements at bridge 3
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Measurements at the Nuclear Power Plant in Paks
A big impact measurement has been performed to create an accurate soil map
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Measurements at the Nuclear Power Plant in Paks
Deriving Dispersion Curves Computing soil profiles and soil maps Impact and Harmonic Measurements
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Airplane Route
The situation has also been evaluated from plane and space!
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Satellite Images
Satellite Images helped identifying the cloud and updating the scenario The satellite images were just a few hours old
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Timeline 07:00 07:37 07:42 08:04 08:17 09:26 09:58 11:55 14:11 15:30 16:30
IRIS 2011 - Demonstration
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Innovation Highlights
Accumulated Energy Function for SHM (WP7) IRIS Risk Paradigm (WP6) Standard Degradation Curve (WP3) EQVIS simulation and crisis management platform (IT) Integrated Decision Support System (WP7) LCA safety assessments concept (after NJ202 Demo) Vibration mitigation equipment (AVA, WP2) New approach to tailing pond safety (WP4) Model based SHM system (WP5)
Results ready for industrial application
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management Current Practice, Thessaloniki, 30. 3. – 2. 4. 2009
My personal DSS
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management Current Practice, Thessaloniki, 30. 3. – 2. 4. 2009
Normal Conditions
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management Current Practice, Thessaloniki, 30. 3. – 2. 4. 2009
Hazard identified
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management Current Practice, Thessaloniki, 30. 3. – 2. 4. 2009
Consequences
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management Current Practice, Thessaloniki, 30. 3. – 2. 4. 2009
Impact
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management Current Practice, Thessaloniki, 30. 3. – 2. 4. 2009
My personal DSS
Score A A A A C T S S S S E R V e s g V
s m m
= + + + + + + − + + + + + + ⋅ + ⋅ + ⋅ + ⋅ +
3 1 f 3 f 2 f 1 f av 2 9 f 3 f 2 f 1 f 1
w 7 w w 1000 , 5 , 2 , 1 1000
weighting Achievement normalized Mega Factor Temperature Ambient and Environmental Conditions
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management Current Practice, Thessaloniki, 30. 3. – 2. 4. 2009
Trend identified
10.000 20.000 30.000 40.000 50.000 60.000 70.000 1990 1995 2000 2005 2010 Jahr meters score runs
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Cooling Towers
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Cooling Towers
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Innovation Highlights
Accumulated Energy Function for SHM (WP7) IRIS Risk Paradigm (WP6) Standard Degradation Curve (WP3) EQVIS simulation and crisis management platform (IT) Integrated Decision Support System (WP7) LCA safety assessments concept (after NJ202 Demo) Vibration mitigation equipment (AVA, WP2) New approach to tailing pond safety (WP4) Model based SHM system (WP5)
Results ready for industrial application
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management Page
39
Lebenszykluskurve - Condition I ndex MA_022 S06- _090,836_0_MAS 30 2003 2048 2003 2008 2013 2018 2023 2028 2033 2038 2043 2048 Konzessionsdauer Erhaltungskonzept Lebenszykluskurve - Condition I ndex 6642/ 6642 Mürzbrücke St. Marein ( KSM 16) 30 1981 2101 1981 2001 2021 2041 2061 2081 2101 Konzessionsdauer Erhalt ungskonzept Lebenszykluskurve - Condition I ndex 111_R Tunnel Bruck 30 1987 2153 1987 2007 2027 2047 2067 2087 2107 2127 2147 Konzessionsdauer Erhalt ungskonzeptIntegrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management Page
40 Total maintenance costs
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management Page
41
Cost Optimization Results
Representative Example
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management Page
42
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Handover Value for var. Benefit scenarios
Ultimate Limit State Life Cycle – Analysis Period Evaluation Time-Frame
Salvage Area from Minimize Costs requirementsUltimate Limit State Life Cycle – Analysis Period Evaluation Time-Frame
Salvage Area from Maximize Benefits requirementsIntegrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Innovation Highlights
Accumulated Energy Function for SHM (WP7) IRIS Risk Paradigm (WP6) Standard Degradation Curve (WP3) EQVIS simulation and crisis management platform (IT) Integrated Decision Support System (WP7) LCA safety assessments concept (after NJ202 Demo) Vibration mitigation equipment (AVA, WP2) New approach to tailing pond safety (WP4) Model based SHM system (WP5)
Results ready for industrial application
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Innovation Highlights
Accumulated Energy Function for SHM (WP7) IRIS Risk Paradigm (WP6) Standard Degradation Curve (WP3) EQVIS simulation and crisis management platform (IT) Integrated Decision Support System (WP7) LCA safety assessments concept (after NJ202 Demo) Vibration mitigation equipment (AVA, WP2) New approach to tailing pond safety (WP4) Model based SHM system (WP5)
Results ready for industrial application
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Step 6. The LSIR at a given community is the weighted sum of NF/NPAR for the different scenarios with weights corresponding to the product of the probability of dam instability and the probability assigned to different breach scenarios, warning times and states-of- preparedness given that instability occurs.
ACTIVITY: DEFINITION OF INHERENT AND EMERGING RISKS
SUBTASK:
CONSEQUENCE MODELLING - VULNERABILITY OF PEOPLE AT RISK.
Schematic example of iso-risk contour lines of the LSIR
Note: for dynamic instability the emergency/evacuation should be considered as instant and the warning time equals the arrival time of the flow at the community. For static instability an anticipated emergency/evacuation is more likely and mutliple values of warning time should be considered with appropriately assigned probabilities.
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
ACTIVITY: DEFINITION OF INHERENT AND EMERGING RISKS
SUBTASK:
CONSEQUENCE MODELLING - VULNERABILITY OF PEOPLE AT RISK.
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
ACTIVITY: DEFINITION OF INHERENT AND EMERGING RISKS
SUBTASK:
CONSEQUENCE MODELLING - VULNERABILITY OF PEOPLE AT RISK. Consequences - Step 4: Vulnerability - buildings
Literature based. Depends on construction type. In the example unreinforced masonry buildings are used.
ground floor upper floor
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Innovation Highlights
Accumulated Energy Function for SHM (WP7) IRIS Risk Paradigm (WP6) Standard Degradation Curve (WP3) EQVIS simulation and crisis management platform (IT) Integrated Decision Support System (WP7) LCA safety assessments concept (after NJ202 Demo) Vibration mitigation equipment (AVA, WP2) New approach to tailing pond safety (WP4) Model based SHM system (WP5)
Results ready for industrial application
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Key Performance Figures Final
59 Dissemination Meetings 18 EB Meetings 780+ Technical Meetings 3 General Assemblies 445 Work Documents 13 Demonstrations in Europe 2 International Demonstrations Intl. Collaboration with USA, Japan, China, India CEN Workshop 63 in Progress Collaboration to 5 other FP7 Projects 311 Scientists involved in the IRIS work 12 National Projects triggered 19 PhD and Msc Theses
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Work Document Structure
So far 445 Work Documents comprising: 35 Strategic Documents 25 Technology Documents 43 IT Documents 15 Demonstration Documents 7 Standardisation Documents 320 Administrative Documents
Assessment by Executive Board
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Risk Management Project Management Natural Disasters Mayor Accidents W orkers Safety Environmental Disasters Energy Production Cross Coordination Fertilization Risk based Design and Operation SP6 SP1 SP2 SP3 SP4 SP5 SP8 1 year 2 year Project Schedule Sub-Projects 3 year 4 year Online Monitoring SP7 T8-9 T8-8 T8-7 T8-5 T8-4 T8-3 T8-2 T8-1 T7-12 T7- 1 1 T7-10 T7-9 T7-8 T7-7 T7-6 T7-5 T7-4 T7-2 T7-1 T6-6 T5-4 T5-3 T5-1 T5-2 T4-4 T4-3 T4-2 T4-1 T3-6 T3-5 T3-4 T3-3 T3-2 T2-4 T3-1 T2-3 T2-1 T1-4 T1-2 T1-3 T1-1 T6-5 T6-4 T6-3 T6-1 T6-2 T2-2 T7-3 T8-6Character of Large Collaboration
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Demonstrations
WP3 Demo at S101 WP1 Demo at NPP Kozloduy WP2 Demo at DOW Stade WP4 Demo in Mosny Pond Poland WP5 Demo Block C at RWE Neurath Plant International Demo in the US at New Jersey 202 International Demo in Taiwan at the Gi Lu Bridge IRIS 2011 in Hungary, large demonstration and exercise! WP3 Demo at A1-W4 WP3 Demo at S6 WP3 Demo at EGNATIA WP1 Demo at JRC WP2 Demo at DOW Stade (modified) WP4 Demo in Rovinari, Romania WP5 Demo Bypass at RWE Neurath Plant
Assessment by Executive Board
Integrated European Industrial Risk Reduction System CP-IP 213968-2
Project Management
Overall Assessment
The results are good and the objectives are met The work is in time and of good quality The scientific and technical performance is excellent Exploitation prospects are excellent The Consortium has been very well balanced and motivated Benefits are expected for everyone The European Dimension is satisfied Integration aspects are well represented No more risk of a failure The economic potential is visible
Assessment by Executive Board