Final Conference Final Scientific Progress What we have achieved - - PowerPoint PPT Presentation

final conference
SMART_READER_LITE
LIVE PREVIEW

Final Conference Final Scientific Progress What we have achieved - - PowerPoint PPT Presentation

IRIS Integrated European Industrial Risk Reduction System CP-IP 213968-2 Final Conference Final Scientific Progress What we have achieved Helmut Wenzel Vienna, March 2012 Innovation Highlights Integrated European Industrial Risk


slide-1
SLIDE 1

IRIS – Integrated European Industrial Risk Reduction System CP-IP 213968-2

Final Scientific Progress

Helmut Wenzel

Vienna, March 2012

Final Conference

What we have achieved

slide-2
SLIDE 2

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Innovation Highlights

Accumulated Energy Function for SHM (WP7) IRIS Risk Paradigm (WP6) Standard Degradation Curve (WP3) EQVIS simulation and crisis management platform (IT) Integrated Decision Support System (WP7) LCA safety assessments concept (after NJ202 Demo) Vibration mitigation equipment (AVA, WP2) New approach to tailing pond safety (WP4) Model based SHM system (WP5)

Results ready for industrial application

slide-3
SLIDE 3

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Virtual Doctor

Nerves Pain Data Virtual Pain

Basic Idea

slide-4
SLIDE 4

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Innovation Highlights

Accumulated Energy Function for SHM (WP7) IRIS Risk Paradigm (WP6) Standard Degradation Curve (WP3) EQVIS simulation and crisis management platform (IT) Integrated Decision Support System (WP7) LCA safety assessments concept (after NJ202 Demo) Vibration mitigation equipment (AVA, WP2) New approach to tailing pond safety (WP4) Model based SHM system (WP5)

Results ready for industrial application

slide-5
SLIDE 5

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Major Achievements

IRIS Damage Detection

Integration Normalization Environment

Temperature Radiation Added Loads Forced Input Strain

Accumulated Energy Function

Measurement Trend Analysis

Temperature Radiation Added Loads Forced Input Strain

slide-6
SLIDE 6

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Verification in the Field

Bridge S101, December 2008

slide-7
SLIDE 7

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management ETPIS, May 2010

slide-8
SLIDE 8

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management ETPIS, May 2010

slide-9
SLIDE 9

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Proof of Concept

Accumulated Energy Function

slide-10
SLIDE 10

IRIS – Integrated European Industrial Risk Reduction System CP-IP 213968-2

slide-11
SLIDE 11

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Checking period: 1997–now Risk Level: low

Undamaged

slide-12
SLIDE 12

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Innovation Highlights

Accumulated Energy Function for SHM (WP7) IRIS Risk Paradigm (WP6) Standard Degradation Curve (WP3) EQVIS simulation and crisis management platform (IT) Integrated Decision Support System (WP7) LCA safety assessments concept (after NJ202 Demo) Vibration mitigation equipment (AVA, WP2) New approach to tailing pond safety (WP4) Model based SHM system (WP5)

Results ready for industrial application

slide-13
SLIDE 13

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

The IRIS Risk Paradigm Time as additional Parameter

slide-14
SLIDE 14

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Innovation Highlights

Accumulated Energy Function for SHM (WP7) IRIS Risk Paradigm (WP6) Standard Degradation Curve (WP3) EQVIS simulation and crisis management platform (IT) Integrated Decision Support System (WP7) LCA safety assessments concept (after NJ202 Demo) Vibration mitigation equipment (AVA, WP2) New approach to tailing pond safety (WP4) Model based SHM system (WP5)

Results ready for industrial application

slide-15
SLIDE 15

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Comparative Structural Inspection

D.O.T. DISK DIN 1076 RVS 13.03.11

safe and operational (minor repair) safe and operational unsafe reduced safety and operability repair demanded safe and useable during repair safe − indicating reduced

  • perability

USA Netherlands Germany Austria

9 1 2 3 4 5 6 7 8 1,0 - 1,4 3,5 - 4,0 3,0 - 3,4 2,5 - 2,9 2,0 - 2,4 1,5 - 1,9 1 6 5 4 3 2 1 6 5 4 3 2

Japan Condition

A E D C B

International Harmonisation

WP7

Online Monitoring

slide-16
SLIDE 16

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Observed Service Life of structures

slide-17
SLIDE 17

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Innovation Highlights

Accumulated Energy Function for SHM (WP7) IRIS Risk Paradigm (WP6) Standard Degradation Curve (WP3) EQVIS simulation and crisis management platform (IT) Integrated Decision Support System (WP7) LCA safety assessments concept (after NJ202 Demo) Vibration mitigation equipment (AVA, WP2) New approach to tailing pond safety (WP4) Model based SHM system (WP5)

Results ready for industrial application

slide-18
SLIDE 18

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Timeline 07:30 07:37 Creating the Scenario Earthquake in EQvis

IRIS 2011 - Demonstration

slide-19
SLIDE 19

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Timeline 07:30 07:37 07:42 Scenarios finished and damages computed 08:04

IRIS 2011 - Demonstration

slide-20
SLIDE 20

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

The route of the Building Inspection Team

slide-21
SLIDE 21

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Overview of the route of the Building Inspection Team

slide-22
SLIDE 22

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Timeline 07:30 07:37 07:42 08:04 08:17 09:26 09:58 11:55 14:11 15:32

IRIS 2011 - Demonstration

The Bridge Inspection Team completes the measurements at bridge 3

slide-23
SLIDE 23

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Measurements at the Nuclear Power Plant in Paks

A big impact measurement has been performed to create an accurate soil map

slide-24
SLIDE 24

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Measurements at the Nuclear Power Plant in Paks

Deriving Dispersion Curves Computing soil profiles and soil maps Impact and Harmonic Measurements

slide-25
SLIDE 25

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Airplane Route

The situation has also been evaluated from plane and space!

slide-26
SLIDE 26

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Satellite Images

Satellite Images helped identifying the cloud and updating the scenario The satellite images were just a few hours old

slide-27
SLIDE 27

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Timeline 07:00 07:37 07:42 08:04 08:17 09:26 09:58 11:55 14:11 15:30 16:30

IRIS 2011 - Demonstration

slide-28
SLIDE 28

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Innovation Highlights

Accumulated Energy Function for SHM (WP7) IRIS Risk Paradigm (WP6) Standard Degradation Curve (WP3) EQVIS simulation and crisis management platform (IT) Integrated Decision Support System (WP7) LCA safety assessments concept (after NJ202 Demo) Vibration mitigation equipment (AVA, WP2) New approach to tailing pond safety (WP4) Model based SHM system (WP5)

Results ready for industrial application

slide-29
SLIDE 29

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management Current Practice, Thessaloniki, 30. 3. – 2. 4. 2009

My personal DSS

slide-30
SLIDE 30

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management Current Practice, Thessaloniki, 30. 3. – 2. 4. 2009

Normal Conditions

slide-31
SLIDE 31

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management Current Practice, Thessaloniki, 30. 3. – 2. 4. 2009

Hazard identified

slide-32
SLIDE 32

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management Current Practice, Thessaloniki, 30. 3. – 2. 4. 2009

Consequences

slide-33
SLIDE 33

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management Current Practice, Thessaloniki, 30. 3. – 2. 4. 2009

Impact

slide-34
SLIDE 34

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management Current Practice, Thessaloniki, 30. 3. – 2. 4. 2009

My personal DSS

Score A A A A C T S S S S E R V e s g V

s m m

= + + + + + + − + + + + + + ⋅ + ⋅ + ⋅ + ⋅ +

3 1 f 3 f 2 f 1 f av 2 9 f 3 f 2 f 1 f 1

w 7 w w 1000 , 5 , 2 , 1 1000  

weighting Achievement normalized Mega Factor Temperature Ambient and Environmental Conditions

slide-35
SLIDE 35

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management Current Practice, Thessaloniki, 30. 3. – 2. 4. 2009

Trend identified

10.000 20.000 30.000 40.000 50.000 60.000 70.000 1990 1995 2000 2005 2010 Jahr meters score runs

slide-36
SLIDE 36

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Cooling Towers

slide-37
SLIDE 37

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Cooling Towers

slide-38
SLIDE 38

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Innovation Highlights

Accumulated Energy Function for SHM (WP7) IRIS Risk Paradigm (WP6) Standard Degradation Curve (WP3) EQVIS simulation and crisis management platform (IT) Integrated Decision Support System (WP7) LCA safety assessments concept (after NJ202 Demo) Vibration mitigation equipment (AVA, WP2) New approach to tailing pond safety (WP4) Model based SHM system (WP5)

Results ready for industrial application

slide-39
SLIDE 39

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management Page

39

Lebenszykluskurve - Condition I ndex MA_022 S06- _090,836_0_MAS 30 2003 2048 2003 2008 2013 2018 2023 2028 2033 2038 2043 2048 Konzessionsdauer Erhaltungskonzept Lebenszykluskurve - Condition I ndex 6642/ 6642 Mürzbrücke St. Marein ( KSM 16) 30 1981 2101 1981 2001 2021 2041 2061 2081 2101 Konzessionsdauer Erhalt ungskonzept Lebenszykluskurve - Condition I ndex 111_R Tunnel Bruck 30 1987 2153 1987 2007 2027 2047 2067 2087 2107 2127 2147 Konzessionsdauer Erhalt ungskonzept
slide-40
SLIDE 40

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management Page

40 Total maintenance costs

  • individual (unblocked) & per structural type
slide-41
SLIDE 41

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management Page

41

Cost Optimization Results

Representative Example

slide-42
SLIDE 42

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management Page

42

slide-43
SLIDE 43

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Handover Value for var. Benefit scenarios

Ultimate Limit State Life Cycle – Analysis Period Evaluation Time-Frame

Salvage Area from Minimize Costs requirements

Ultimate Limit State Life Cycle – Analysis Period Evaluation Time-Frame

Salvage Area from Maximize Benefits requirements
slide-44
SLIDE 44

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Innovation Highlights

Accumulated Energy Function for SHM (WP7) IRIS Risk Paradigm (WP6) Standard Degradation Curve (WP3) EQVIS simulation and crisis management platform (IT) Integrated Decision Support System (WP7) LCA safety assessments concept (after NJ202 Demo) Vibration mitigation equipment (AVA, WP2) New approach to tailing pond safety (WP4) Model based SHM system (WP5)

Results ready for industrial application

slide-45
SLIDE 45

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

slide-46
SLIDE 46

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

slide-47
SLIDE 47

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Innovation Highlights

Accumulated Energy Function for SHM (WP7) IRIS Risk Paradigm (WP6) Standard Degradation Curve (WP3) EQVIS simulation and crisis management platform (IT) Integrated Decision Support System (WP7) LCA safety assessments concept (after NJ202 Demo) Vibration mitigation equipment (AVA, WP2) New approach to tailing pond safety (WP4) Model based SHM system (WP5)

Results ready for industrial application

slide-48
SLIDE 48

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Step 6. The LSIR at a given community is the weighted sum of NF/NPAR for the different scenarios with weights corresponding to the product of the probability of dam instability and the probability assigned to different breach scenarios, warning times and states-of- preparedness given that instability occurs.

ACTIVITY: DEFINITION OF INHERENT AND EMERGING RISKS

SUBTASK:

CONSEQUENCE MODELLING - VULNERABILITY OF PEOPLE AT RISK.

Schematic example of iso-risk contour lines of the LSIR

Note: for dynamic instability the emergency/evacuation should be considered as instant and the warning time equals the arrival time of the flow at the community. For static instability an anticipated emergency/evacuation is more likely and mutliple values of warning time should be considered with appropriately assigned probabilities.

slide-49
SLIDE 49

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

ACTIVITY: DEFINITION OF INHERENT AND EMERGING RISKS

SUBTASK:

CONSEQUENCE MODELLING - VULNERABILITY OF PEOPLE AT RISK.

slide-50
SLIDE 50

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

ACTIVITY: DEFINITION OF INHERENT AND EMERGING RISKS

SUBTASK:

CONSEQUENCE MODELLING - VULNERABILITY OF PEOPLE AT RISK. Consequences - Step 4: Vulnerability - buildings

Literature based. Depends on construction type. In the example unreinforced masonry buildings are used.

ground floor upper floor

slide-51
SLIDE 51

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Innovation Highlights

Accumulated Energy Function for SHM (WP7) IRIS Risk Paradigm (WP6) Standard Degradation Curve (WP3) EQVIS simulation and crisis management platform (IT) Integrated Decision Support System (WP7) LCA safety assessments concept (after NJ202 Demo) Vibration mitigation equipment (AVA, WP2) New approach to tailing pond safety (WP4) Model based SHM system (WP5)

Results ready for industrial application

slide-52
SLIDE 52

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

slide-53
SLIDE 53

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

slide-54
SLIDE 54

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

slide-55
SLIDE 55

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

slide-56
SLIDE 56

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Key Performance Figures Final

 59 Dissemination Meetings  18 EB Meetings  780+ Technical Meetings  3 General Assemblies  445 Work Documents  13 Demonstrations in Europe  2 International Demonstrations  Intl. Collaboration with USA, Japan, China, India  CEN Workshop 63 in Progress  Collaboration to 5 other FP7 Projects  311 Scientists involved in the IRIS work  12 National Projects triggered  19 PhD and Msc Theses

slide-57
SLIDE 57

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Work Document Structure

So far 445 Work Documents comprising: 35 Strategic Documents 25 Technology Documents 43 IT Documents 15 Demonstration Documents 7 Standardisation Documents 320 Administrative Documents

Assessment by Executive Board

slide-58
SLIDE 58

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Risk Management Project Management Natural Disasters Mayor Accidents W orkers Safety Environmental Disasters Energy Production Cross Coordination Fertilization Risk based Design and Operation SP6 SP1 SP2 SP3 SP4 SP5 SP8 1 year 2 year Project Schedule Sub-Projects 3 year 4 year Online Monitoring SP7 T8-9 T8-8 T8-7 T8-5 T8-4 T8-3 T8-2 T8-1 T7-12 T7- 1 1 T7-10 T7-9 T7-8 T7-7 T7-6 T7-5 T7-4 T7-2 T7-1 T6-6 T5-4 T5-3 T5-1 T5-2 T4-4 T4-3 T4-2 T4-1 T3-6 T3-5 T3-4 T3-3 T3-2 T2-4 T3-1 T2-3 T2-1 T1-4 T1-2 T1-3 T1-1 T6-5 T6-4 T6-3 T6-1 T6-2 T2-2 T7-3 T8-6

Character of Large Collaboration

slide-59
SLIDE 59

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Demonstrations

 WP3 Demo at S101  WP1 Demo at NPP Kozloduy  WP2 Demo at DOW Stade  WP4 Demo in Mosny Pond Poland  WP5 Demo Block C at RWE Neurath Plant  International Demo in the US at New Jersey 202  International Demo in Taiwan at the Gi Lu Bridge  IRIS 2011 in Hungary, large demonstration and exercise!  WP3 Demo at A1-W4  WP3 Demo at S6  WP3 Demo at EGNATIA  WP1 Demo at JRC  WP2 Demo at DOW Stade (modified)  WP4 Demo in Rovinari, Romania  WP5 Demo Bypass at RWE Neurath Plant

Assessment by Executive Board

slide-60
SLIDE 60

Integrated European Industrial Risk Reduction System CP-IP 213968-2

Project Management

Overall Assessment

 The results are good and the objectives are met  The work is in time and of good quality  The scientific and technical performance is excellent  Exploitation prospects are excellent  The Consortium has been very well balanced and motivated  Benefits are expected for everyone  The European Dimension is satisfied  Integration aspects are well represented  No more risk of a failure  The economic potential is visible

IRIS Success Story !

Assessment by Executive Board