Fi Finder nders s Res esou
- urces
ces Li Limit ited ed
ASX Inves estor
- r Day Feb
Fi Finder nders s Res esou ources ces Li Limit ited ed ASX - - PowerPoint PPT Presentation
Fi Finder nders s Res esou ources ces Li Limit ited ed ASX Inves estor or Day Feb ebrua uary y 24 2011 Disclaimer claimer This presentation (Presentation) has been prepared by Finders Resources Limited (Finders) based on
2
This presentation (Presentation) has been prepared by Finders Resources Limited (Finders) based on information available to it and from third party sources. By retaining this Presentation, you (the Recipient) acknowledge and represent to Finders that you have read, understood and accepted the terms of this Important
This Presentation does not purport to contain all the information that a prospective investor may require in connection with any potential investment in Finders. You should not treat the contents of this Presentation, or any information provided in connection with it, as financial advice, financial product advice or advice relating to legal, taxation or investment matters. No representation or warranty is made by Finders or any of its advisers, agents or employees as to the accuracy, completeness or reasonableness of the information contained in this Presentation or provided in connection with it. No information contained in this Presentation or any other written or oral communication in connection with it is, or shall be relied upon as, a promise or representation and no representation or warranty is made as to the accuracy or attainability of any estimates, forecasts or projections set out in this Presentation. No liability will attach to Finders with respect to any such information, estimates, forecasts or projections. Finders does not accept responsibility or liability for any loss or damage suffered or incurred by you or any other person or entity however caused (including, without limitation, negligence) relating in any way to this Presentation including, without limitation, the information contained in or provided in connection with it, any errors or
Finders does not accept any responsibility to inform you of any matter arising or coming to Finders' notice after the date of this Presentation which may affect any matter referred to in this Presentation. Any liability of Finders, their advisers, agents and employees to you or to any other person or entity arising out of this Presentation including pursuant to the Australian Securities and Investments Commission Act 2001, Corporations Act 2001, Part IVA or V (including sections 51AA, 51AB, 51AC, 52 or 53) of the Trade Practices Act 1974 or any corresponding provision of any state or territory legislation, or similar provision under any applicable law is, to the maximum extent permitted by law, expressly disclaimed and excluded. The distribution of this Presentation may be restricted by law in certain jurisdictions. Recipients and any other persons who come into possession of this Presentation must inform themselves about, and observe any such restrictions. Future matters: This Presentation contains reference to certain intentions, expectations, future plans, strategy and prospects of Finders. Those intentions, expectations, future plans, strategy and prospects may or may not be achieved. They are based on certain assumptions, which may not be met or on which views may differ and may be affected by known and unknown risks. The performance and operations of Finders may be influenced by a number of factors, many of which are outside the control of Finders. No representation or warranty, express or implied, is made by Finders, or any of its directors, officers, employees, advisers or agents that any intentions, expectations
Given the risks and uncertainties that may cause Finders' actual future results, performance or achievements to be materially different from those expected, planned
that the actual results, performance or achievements will be as expected, planned or intended.
2.0 3.0 4.0 5.0 6.0 7.0 8.0
1,000 1,500 2,000 2,500 3,000 TLM SBR EXS TGS RXM FND ABY SWN DML CDU SFR EQN CGG PNA JML SRL OZL Cu Equiv Grade % EV / t Contained Cu Eq (AUD $) EV / Reserves (Blue) or Resources (Green) Cu Eq grade 3
Producers average $2000 EV/t Cu Eq “Darlings” average $1400 EV/t Cu Eq Finders is poised for value increase (currently ~$500/t Cu Reserves)
4
Robust t Economic ics At the Wetar ar Copper r Project
De De-Ris isked ed Transition tion to to Product uction ion
Experience rienced d Managem gemen ent t With Strong g Community nity Relati tions
Further her Grow
h Pot Potenti tial al With Pipeline line Gold & Silver ver Project
Attrac tractiv ive e Valuat ation ion
High margin copper operations and potential gold-silver pipeline project
5
Capit ital al Structure ture
(2 Dec 10) Ordinary shares (ASX + AIM) 272m Share Price A$0.48 Market Capitalisation ~A$130m Options (Unlisted) 5.6m Convertible Notes (conversion 2012, 12%, $0.36 par) US$1.5m Cash ~A$14m
Quality shareholder base with major support from expert institutional investors
Shareholder eholder Register er
Resource Capital Fund 10.5% (12.6% diluted) Straits Resources Ltd 11.1% Acorn Capital Ltd 10.4% Taurus Resources 10.0% Lujeta Pty Ltd 5.7% Directors/Staff 8.0%
6
World class mineral province with some of the world‟s largest operating mines
Ojolali lali Gold-Silv ilver er Project ect Wetar Copper er Project ect
Heap leach/SX EW copper cathode
7
Staged Expansion to 23,000 tpa utilising Whim Creek plant
8
The tonnes and grades are stated to a number of significant digits reflecting the confidence of the estimate. Since each number and total is rounded individually the columns and rows in the above table may not show exact sums or weighted averages of the reported tonnes and grades.
(0.5% Cu Cut-off) Category Tonnes (m) Grade % Cu Contained Copper (kt) Kali Kuning Pit Proved 4.91 2.5 123 Probable 0.85 2.2 19 Sub- Total 5.76 2.5 142 Lerokis Pit Proved 2.05 2.4 49 Probable 0.37 2.3 9 Sub- Total 2.42 2.4 58 Combined Proved 6.96 2.5 172 Probable 1.22 2.2 28 Total 8.18 2.5 205
9
ect locati tion
r Billit iton
ect deve velop lopmen ent now
ican antly tly de-ris isked. ed.
aiting ing mining ing permit t approvals als, , and clarif ificat ation ion of jurisdic dicti tion n
ver r land adminis istra trati tion:
r mining ng activit vities ies
conversion forest classified as bushland and open ground
Project ect Ove vervie view
10 10
Demonstration Plant Stage 2: 23,000 tpa Stage 1: 7,000 tpa
e:
scale heaps
testable in column tests
finance
led DFS optimis isat atio ion: n:
schedule being made
proven Indonesian contractors
items identified
existing demonstration plant
mine operations
adjoining valley
Stage 1 completion
Stage 1
Staged development path de-risks the transition to full-scale production
11 11
Operational demonstration plant has enabled resolution of all technical issues prior to full scale production
Stage 2 expansion Stage 1 expansion
12 12
Prefeasibility Studies Complete Demonstration Plant (17mths operation) Complete Environmental Permit Approval (AMDAL) Complete Definitive Feasibility Study Complete Detailed Engineering – Stage 1 Complete Mine Development Permit Target – Q1 2011 Detailed Engineering – Stage 2 Target – early Q2 2011 Project Financing Target – Mandate Q1 2011 Project Financing Target – Close Q2 2011 Stage 1 Production Target – Q1 2012 Construction Completion Stage 2 Target – Q4 2012 Stage 2 Production Target – Q1 2013
Timing*
* Subject to all required permitting, bank finance & no forestry moratorium
13 13
Notes: 1. Ore Reserves includes 0.2mt of Inferred Resources within the pit shell. 2. Stage 1 funding reflects increase in capacity from 5,000 to 7,000 tpa cathode 3. Stage 1 & 2 funding estimate includes Working Capital
Ore Reserves 8.4mt (1) Output 23,000 tpa Strip Ratio (LOM) 1:1 Initial Mine Life 8.7 years Average Copper Grade (LOM) 2.5% Average Recovery (LOM) 71% Average Operating Cost (LOM) U$1.00/lb Total Cathode Production 146,000t Stage 1 Stage 2 to 7,000tpa to 23,000tpa Total Funding Requirement U$118 million(3) Stage 1 (before contingency) Stage 2 ~U$25 million(2) ~U$93 million Stage 2 capex key opportunities : optimising earthworks schedule reducing indirect costs. Copper er Price Sensiti tivit vity – Based on DFS DFS Summary
Wetar Copper Project Pre-tax NPV (US$m)
$0 $100 $200 $300 $400 $5,000 $6,000 $7,000 $8,000 Copper price (US$/tonne)
14 14
Meron Potential size 0.5- 1.5mt @ 1-3% Cu Ilwaki 8 drill holes in gold cap only Pantai Merah Identified Au-barite sand One hole in copper Batu Duri 9 drill holes, incl 10m @ 4.5% Cu
15 15
Project ect Ove vervie view (FND 72% with option
%)
16 16
silver mineralized system in the highly prospective Sumatran gold belt.
Inferred resource at Jambi prospect, excellent metallurgy, and high grade feeder structures open at depth.
high grade gold and silver shoots, and variable leach response requires additional drilling to bring to resource status.
targets with strong surface showings of Au and Ag from surface trenching and soil geochemistry.
potential
Cut off Indicated Inferred Total Contained Au g/t Mt Au g/t Mt Au g/t Mt Au g/t Au koz Ag koz 0.3 5.9 0.85 0.67 0.8 6.5 0.8 175 1,000 0.5 3.72 1.1 0.36 1.1 4.09 1.1 145 670
Jambi Resource Estimate
17 17
resources to support a viable start-up mining operation.
Finders
splays, jogs, kinks forming high potential target structures.
discoveries
and silver rich shoots- on-going metallurgical test work focused on floatation.
with strong surface showings of Au and Ag from surface trenching and soil geochemistry. Recent Tambang Drill intercepts [
Wetar Copper –Driving to development
News flow :
Mining Permit, Shipping Whim Creek Debt financing; Forestry Clearance; BOD to proceed Resource upgrade at Meron
Ojolali –Potential Growth Driver
News flow :
Metallurgical results, surface trench sampling Planning for major drill program
18 18
19 19
20 20
Dr Russell l Fountain ain (Chairman)
Over 40 years of international experience in all aspects of mineral exploration, project feasibility and development of mining projects involving copper, gold, nickel and mineral sands. Previous senior positions include President, Phelps Dodge Exploration Corporation; Exploration Manager, Nord Pacific Ltd and Chief Geologist, CSR Minerals.
Dr Chris Farmer er (Managing Director)
19 years of international experience in all aspects of exploration, with an emphasis on international joint ventures and business development. Previous positions include VP Australasia and Chief Geologist, Phelps Dodge Exploration Corporation; and Senior Geologist with both Highlands Gold (Indonesia) Pty Ltd and Billiton Indonesia BV working at the Lebong Tandai and Wetar gold mines.
Rob Thomson
(Director – Development)
Over 30 years of Australian and international mining experience. He has worked on 5 Asian development projects in the last 13 years including GM Development, Chatree Gold Mine in Thailand and Project Director, Sepon Gold Mine in
2006 to 2008.
James Wentwor
(Finance Director)
More than 17 years of finance and investment experience with a focus on mining and mining services in Australia and internationally. Areas covered included principal investment, debt and equity raising, mergers and acquisitions and project and structured finance at CHAMP Ventures, Macquarie Bank, Goldman Sachs and Lehman Brothers.
Stephen hen de Belle e (Non-exec. Director)
Closely involved with the start-up and operation of iron ore, coal, base metals, gold and petroleum projects and companies, and has particular expertise in the development and financing of projects in the resources and infrastructure sectors both in Australia and overseas. He is currently managing director of a geothermal and power technology company.
Steve e Lonergan gan (Non-exec. Director)
commercial lawyer based in Sydney with more than 25 years experience in the Australian and international mining industry, having been General Counsel of Pancontinental Mining Group, a partner at Baker & McKenzie Sydney, and General Counsel and Company Secretary of Savage Resources Limited. Mr Lonergan is currently General Counsel and Company Secretary of CBH Resources Limited.
Quinn n Roussel (Non-exec. Director)
Principal of Resource Capital Funds (RCF), a mining-focussed private equity firm. Prior to joining RCF in 2006, he was Director of Business Development at one of RCF‟s portfolio companies in China. He has also worked as an engineer in both mining and the oil & gas industries.
Management team with significant Indonesian experience in mine operations and government relations
21 21
installation.
22 22
SX-EW technology is used to produce ~22% of the world‟s copper production
23 23
grade).
content.
parameters.
neutralisation plant now retrofitted.
detailed design.
Demonstration plant delivering LME grade A cathode
Succes essful ful Demons nstrat ration ion Plant Cumulati lative e Copper Recover ery
70 50 30 10 Copper Recovery % 6 12 18 Months Heap 3 Model Heap 3 Actual Heap 2 Model Heap 2 Actual
24 24
Existing Demonstration Plant & Stage 1 Operations Stage 2 Expansion Plant & Operations
25 25
26 26
Identified logistical issues resolved through demonstration plant experience
27 27
The information in this report that relates to exploration potential, mineral resource and ore reserve estimation is the responsibility of Dr Russell Fountain. Dr Fountain is a Director of Finders and a Fellow of the Australian Institute of Geoscientists. Dr Fountain has sufficient experience that is relevant to the styles of mineralisation and types of deposits under consideration and to the activity that he is undertaking to qualify as Competent Person in the 2004 Edition of the „Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves‟ (JORC Code) and as a Qualified Person as defined in the AIM
samples was undertaken by the ITS laboratory in Jakarta. ITS is one of the world‟s largest product and commodity testing, inspection and certification
control and reporting.