FDOT District 5 Clyde Morris Boulevard (SR 483) from south of - - PowerPoint PPT Presentation

fdot district 5 clyde morris boulevard sr 483
SMART_READER_LITE
LIVE PREVIEW

FDOT District 5 Clyde Morris Boulevard (SR 483) from south of - - PowerPoint PPT Presentation

FDOT District 5 Clyde Morris Boulevard (SR 483) from south of Beville Rd (SR 400) to north of International Speedway Blvd (US 92/SR 600) FPID: 408178-1-32-01 Volusia County MPO BPAC Meeting January 13, 2010 Project Implementation PD&E


slide-1
SLIDE 1

Clyde Morris Boulevard (SR 483)

from south of Beville Rd (SR 400) to north of International Speedway Blvd (US 92/SR 600)

Volusia County MPO BPAC Meeting January 13, 2010

FDOT District 5

FPID: 408178-1-32-01

slide-2
SLIDE 2

Project Implementation

Final Design Right of Way Construct Project PD&E Study

slide-3
SLIDE 3

SR 483 Design Phase

  • Detailed Engineering
  • Define:

– Right of Way Needs – Anticipated Construction Costs

  • Continue:

– Local Agency and Stakeholder Involvement – Public Involvement

slide-4
SLIDE 4

SR 483 – Project Limits

Project Limit Project Limit

slide-5
SLIDE 5

Project Need - Safety

slide-6
SLIDE 6

SR 483 PD&E Study Proposed Typical Section

Width of sidewalk adjusted to demand of pedestrian use near the educational institutions:

  • Continuous 5 foot sidewalks to be constructed at outer edge of pavement on both

sides of roadway.

  • Eight foot sidewalk on west side of roadway between Hancock Blvd to Richard

Petty Blvd.

  • Eight foot sidewalk on east side of roadway between Richard Petty Blvd to US

92/SR 600.

slide-7
SLIDE 7

Preferred Alternative

Estimated Project Cost

  • Construction

$ 33,700,000

  • Engineering, CEI

$ 6,750,000

  • Utility Relocation

$ 4,700,000

  • Right-of-Way

$ 15,000,000 Total $ 60,150,000

slide-8
SLIDE 8

Volusia County MPO Bicycle/Pedestrian Feasibility Study

Completed in 2008 Analyzed 3 alternatives:

  • Option A ‐ 5‐ft wide concrete sidewalk
  • Option B ‐ 10‐ft wide concrete sidewalk
  • Option C ‐ 12‐ft wide asphalt multi‐use trail
slide-9
SLIDE 9

Volusia County MPO Bicycle/Pedestrian Feasibility Study

slide-10
SLIDE 10

Questions?

Brenda Young Design Project Manager 719 S. Woodland Boulevard Deland, Florida 32720 386-943-5645 brenda.young@dot.state.fl.us