Facilities Update (as required by Policy 4:150 Facility Management and Building Programs) May 13, 2019 Presentation Overview Deferred Maintenance Plan (9/4/18) Our Buildings Another Year Older FY19 Construction Timeline


slide-1
SLIDE 1

Facilities Update

(as required by Policy 4:150 – Facility Management and Building Programs)

May 13, 2019

slide-2
SLIDE 2

Presentation Overview

2

  • Deferred Maintenance Plan (9/4/18)
  • Our Buildings – Another Year Older
  • FY19 Construction Timeline
  • Facility Updates
  • Roofing
  • Elementary Air Conditioning
  • Wheatland Academy
  • Crouse Education Center
  • Energy Management Initiatives
  • Next Steps
slide-3
SLIDE 3

Goal for Deferred Maintenance Plan

3

  • Reduce deferred maintenance projects as fast as possible
  • Focus on building envelope, heating/cooling, and safety
  • Ensure quality work through manageable pace
  • Proactively maintaining existing projects
  • Use available resources from
  • Capital Outlay Account
  • Developer Contributions
  • Sale of Property
  • Prior Year Fund Balance
slide-4
SLIDE 4

Buildings Another Year Older

4

2018-19 School Year: 20 Years: Gombert Kendall Crouse Education Center 2019-20 School Year: 90 Years: Indian Plains 40 Years: Clow 30 Years McCarty Spring Brook 20 Years: Builta Welch Young Still 10 Years: Metea Valley

slide-5
SLIDE 5

Projects Start Date Substantial Completion Phase IV – Elementary A. C. Special 10/1/17 8/10/18 Flat Roof Replacement @ Graham Scheduled 6/12/18 8/10/18 2018 Masonry Restoration @ 3 Schools Scheduled 6/12/18 8/10/18 2018 Hardscape Projects @ 6 Schools Scheduled 6/12/18 8/10/18 Vinyl tile replacement @ WVHS Scheduled 6/12/18 8/10/18 Cabling & Security Camera replacement @ NVHS & WVHS Scheduled 3/1/18 10/1/18 Varsity Softball Fence Replacement @ WVHS Scheduled 12/1/18 3/1/19 Phase V – Elementary A. C. Special 12/1/18 8/2/19 BAS Replacement @ Birkett Deferred 2/20/19 6/30/19

FY 19 Construction Timeline

5

slide-6
SLIDE 6

Projects Start Date Substantial Completion Classroom Lock Modifications @ 34 Schools Special 5/14/19 9/27/19 Asphalt Repair @ Wheatland Scheduled 5/27/19 8/2/19 Resilient Gym Floor Installation @ Wheatland Scheduled 5/27/19 8/2/19 Upgrade Fire alarm @ White Eagle Deferred 6/10/19 6/30/19 Slope roof replacement @ Fischer & Graham Deferred 6/10/19 8/3/19 2019 Hardscape Projects @ 4 Schools Deferred 6/10/19 8/3/19 2019 Masonry Restoration @ Fischer & 7 Schools Deferred 6/10/19 8/3/19 Gym Flooring & Bleacher Improvements @ WVHS Deferred 5/28/19 8/12/19

FY 19 Construction Timeline

6

slide-7
SLIDE 7

Varsity Softball Field Fence at WVHS

7

slide-8
SLIDE 8

Roof Expenses

8 $705,200 $592,500 $399,869 $641,200 $786,459 $1,478,800 $424,686 $547,500 $1,919,885 $1,811,868 $137,894 $223,620 $127,911 $102,214 $205,455 $126,867 $208,415

$0 $500,000 $1,000,000 $1,500,000 $2,000,000 $2,500,000

2011-12 2012-13 2013-14 2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 EMG yearly Ave.

Roof Repairs Roofing Replacement

slide-9
SLIDE 9

Flat Roof Repairs/Replacement

9

slide-10
SLIDE 10

Elementary Air Conditioning

10

  • Began installing air conditioning in phases 5 years ago
  • Funding from delayed state payments
  • By August 2019 the project will have installed air conditioning in all of our large elementary

classrooms

  • $3.3 million needed to complete finish the project (LMC area)

Brookdale Brooks

slide-11
SLIDE 11

Wheatland Academy

11

  • South classrooms have been

painted

  • MPR and new staff offices

constructed in lower level

  • Gym Renovation has begun

(8/1/19 completion date)

  • North classrooms & Organic Life
  • ffices (8/5/19 completion date)
slide-12
SLIDE 12

Wheatland Academy

South Classroom South Classroom Hallway

12

slide-13
SLIDE 13

Wheatland Academy

Lower Level Offices Gym Painting Begins

13

slide-14
SLIDE 14

CROUSE EDUCATION CENTER

14

slide-15
SLIDE 15

Energy Management Initiatives

  • 1st year participation in the EnerNOC Demand Response

Incentive Program (ComEd territory only) results in the district receiving $52,600. This year anticipate receiving over $72,000. (Fischer, Granger, Still, MVHS & WVHS)

  • Transitioning outside lighting to LED.
  • Evaluating a proposal for installation of solar panels at MVHS.

(Power Purchase Agreement)

15

slide-16
SLIDE 16

Next Steps

  • Prioritize capital improvement and other district needs based
  • n the following hierarchy:

1. Safety Related Items 2. Approved Curriculum Related needs 3. Necessary Repairs 4. State required Life Safety Projects (building code changes) 5. Aesthetic

  • Explore grant and other cost savings opportunities