facilities committee meeting
play

Facilities Committee Meeting Tuesday, January 7, 2020 1 2 - PowerPoint PPT Presentation

Facilities Committee Meeting Tuesday, January 7, 2020 1 2 Cheltenham Mission Statement Drawing on its cultural richness, creativity, and tradition of scholastic excellence, School District the Cheltenham School District strives to nurture


  1. Facilities Committee Meeting Tuesday, January 7, 2020 1

  2. 2

  3. Cheltenham Mission Statement Drawing on its cultural richness, creativity, and tradition of scholastic excellence, School District the Cheltenham School District strives to nurture each child through a wealth of academic endeavors and community partnerships that provide the skills and vision needed to lead a productive and meaningful life beyond our classroom walls. Mission & Vision Statement With a clear connection between the classroom and the world, the Cheltenham Vision School District will strive for excellence by: Statements 1. inspiring our students to develop principled and knowledgeable responses to the local, national, and global challenges of the 21st century; 2. actively engaging parents in their children’s intellectual, social, and moral education; 3. encouraging faculty and staff to continually broaden the web of connections between their academic disciplines and the world on which they depend; 4. stimulating dynamic leadership of building and district administrators; and 5. creating partnerships with community individuals, institutions, organizations, and businesses that model real-world connections for all students. 3

  4. High School CSD Building and ● The proposal for the structural inspection of the Auditorium exterior Maintenance wall, the company would not change the contract with changes provided by the school districts solicitor. We are in the process of Update finding another firm to complete the report. ● Our BMS ( Building Maintenance System ) lost connectivity throughout High School sections of the building. We have been working on this for the last month and have established many areas. This continues to be a work in progress. ● Updated Athletic banners have been installed in the Gym. 4

  5. Elkins Park CSD Building and ● The boiler has refractory that has collapsed and this will need to be Maintenance replaced. We are working on this with our contractor and awaiting a proposal. This was identified earlier in the year but no work was Update completed. This work is being completed by JCI at a cost of $9,164. There was a delay in getting the parts and this is now planned for next Elkins Park week. ● The water feed line on boiler 1 had a crack in the piping, CSD Maintenance made a temporary repair and we will plan the full repair in the coming weeks. 5

  6. Wyncote CSD Building and As reported at the December meeting we had concerns with our Glycol lines as we had ● lost volume in the pipework. There were no visible signs of this anywhere in the building Maintenance where it was being lost. ● At the time we had concerns that we may have an underground leak in the piping which Update runs from the boiler room to the cooling tower. Image attached. ● We had our contractor out and isolated the system from the building. The system was Wyncote filled up and we lost pressure immediately. This was indication that there is a leak in between the building and cooling tower. ● We needed to isolate the main building for the cooling tower to ensure we still provided heat for the building. This was completed. Our next challenge was ensuring the cooling tower coils don't freeze as if they crack we ● would be looking at a very large sum of money to repair. ● The cooling tower in construction did not have access saddles to drain the system. ● We needed to install 4 access saddles to the system, re-insulate and refill the tower with glycol. ● The cost for the access saddles, insulation, air bleeders was $7,975. ● The cost to add glycol to the tower to ensure it would not freeze was $4,200. ● After Christmas we will need to arrange for the underground pipe to be tested and locate the leak and make plans to have this repaired. I have spoken with Cara and we are investigating if this will be covered under our insurance. ● We currently have the situation resolved and heat in the building but need this to be repaired in time for when we need Air Conditioning. 6

  7. CSD Building and Maintenance Update Access Saddles Wyncote and Shut Off Valves. Insulation will be repaired. 7

  8. Glycol added to CSD Building and cooling towers to Maintenance prevent coil freezing. Shut off Update valves installed. Wyncote 8

  9. CSD Building and More Valves installed. Maintenance Insulation to be repaired. Update Wyncote 9

  10. Next step is to locate piping leak CSD Building and between tower and mechanical room location. Dependent on location a plan Maintenance will be provided on how best to fix the pipe leak Update Wyncote 10

  11. Glenside CSD Building and ● No updates. Maintenance Myers ● No Updates Update Cheltenham Elementary ● No Updates District Wide ● Reviewing BMS and HVAC Service contracts. ● Rectifying BMS Issues within our schools with our new BMS Contract. ● Summer project planning. ● Reviewing current custodial schedules, ordering procedures and planning for summer. ● Reviewing Service contracts that expire at the end of the school year. 11

  12. Elkins Park Air ● Elkins Park Currently only has minimal Air-Conditioning throughout the Conditioning building. ● This summer we installed 6 wall unit A/C units in the cafeteria and this Update provided great relief over the summer. ● The next few slides are proposals to install throughout the building. ● There is a need for power upgrades to achieve this. ● Due to the existing building conditions and possibility of construction at Elkins Park in the coming years, I feel this to be the best short term fix for resolve the Air conditioning issue until a decision in made in the coming years. 12

  13. Elkins Park Air Conditioning Update 13

  14. Elkins Park Air Conditioning Update 14

  15. Elkins Park Air Conditioning Update 15

  16. Elkins Park Air Conditioning Update 16

  17. CSD ● School Dude Maintenance Direct was re-installed and operational on Tuesday, September 3, 2019. School Dude ● All PM Schedules have been rolled out in the system. Update ● Facilities Direct training has been scheduled for the 28th of January. ● I am looking at bringing one elementary school online for all staff to report work orders as a trial. My hope is at the start of next years we will have all staff reporting work orders from each school. ● Still looking at educating all users to ensure we have productive data. ● I would say we are tracking ahead of where I thought we would be with the roll out of this program. 17

  18. CSD ● November 26th Totals School Dude Update 18

  19. CSD ● January 2nd Totals School Dude Update 19

  20. CSD School Dude Update 20

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend