Existing Building Energy Saving
Ir Cary Chan
Executive Director, HK Green Building Council
Existing Building Energy Saving Ir Cary Chan Executive Director, - - PowerPoint PPT Presentation
Existing Building Energy Saving Ir Cary Chan Executive Director, HK Green Building Council Aviation industry 1981 1971 1969 1930s 1903 2 3 4 5 6 A big gap to fill 7 Convincing responses to your boss ! Deliver ! Implementation of
Ir Cary Chan
Executive Director, HK Green Building Council
2
1903 1930s 1969 1981 1971
3
4
5
6
7
A big gap to fill
Convincing responses to your boss ! Deliver !
E nergy Management Process
DATABASE POLICY OBJECTIVE & TARGET ACTION PLAN AUDIT MEASUREMENT & VERIFICATION REVIEW MEETING & REPORT ANALYSIS
ACT PLAN
IMPLEMENTATION
DO CHE CK
Knowledge-based DIAGNOSIS (Retro-Cx) BENCHMARKING
10
Design parameters Load calculation System design Equipment selection T esting and commissioning
Idea of ACT
In participating in the ACT
commissioning through
industry
Initial findings
Different types of building, system design , age..
Bldg A Bldg B Bldg C Bldg D Bldg E Type Composite Hotel Composite (Podium+ T
Composite (Office +Education) Office (Industrial Building Renovation) Age (Yrs) 25 41 24 20 20 IFA (sqm) ~20,000 ~36,000 ~150,000 ~4,500 ~45,000 Chiller 4x320TR Water-Cooled (new) 4x180TR Water-cooled 4x190TR Air-cooled (new) 7x1000TR Water-cooled 2x400TR Water-cooled(Night) 1x150TR Air-cooled 1x150TR Air-cooled (new) 4x400TR Air-cooled Cooling T
4 4 6+2 N/A N/A Control Differential Pressure Bypass Differential Pressure Bypass Differential Pressure Bypass Differential Pressure Bypass Differential Pressure Bypass Pumps 4+1 Water-cooled: 4 Air-cooled: 4+1 7+2 4+2 (Office T
2+1 4+1 Features Variable Speed Chiller 140TR Heat Pump for hot water Heat Exchanger for high rise office tower natural ventilation allowed Fresh air treated by FCU
.
Availability of data and information varies !
Approach a and Met etho hod
Has to consider :
19
“ACT
(retro-Cx)
2.
Performance line evaluation
3.
Peak demand shedding
Outdoor Ambient Temperature Loading Valve Authority 24:00 Peak Demand 0:00
summer winter
Control Set-point
Re-tune:
valve, etc.
Cooling Load %load
100%
Re-tune: 1. DTCHWS 2. DTA 3. DSP
2 3
1.1 1.2 1.3
6
Outdoor Ambient Temperature Cooling load
4. Set-point reset 1. Re-tune
1.1 Valve authority 1.2 Set-point 1.3 Equipment operation
4. DPWS 5. TAPP
,C
6. TAPP
,C T
20
““ACT
(retro-Cx)
Bldg A Bldg B Bldg C Bldg D Bldg E
DTCHWsummer DTCHWwinter 5.0°C 2.5°C 5.0°C 3.2°C 5.0°C 3.0°C 2.5°C 0.75°C 3.4°C 2.0°C TCHWSsummer TCHWSwinter 7.8°C 10°C 7°C 11°C 8°C 9.5°C 9.5°C 14°C 8.5°C 10°C COP,CHsummer COP,Chwinter 6.3 13 3.3 3.4 5.3 4.2 3.2 2.9 1.6 2.5 EUI(Chiller) 60 kWh/m2/year 115 kWh/m2/year 88 kWh/m2/year 33 kWh/m2/year 48.3 kWh/m2/year
Low CO P Low DTCH W TCHWS reset at winter
21
Cooling Load/m2
Percentage of Full Load Ampere (%FLA) 3 Chillers Zone 2 Chillers Zone 1 Chiller Zone 100% Full Load
capacity)
More FLA Less FLA Extra chiller
22
% Full Load Ampere issue
0% 20% 40% 60% 80% 100% 20 40 60 80 100 120
Percentage of Full Load Amp Cooling Load Intensity
Bldg C
1 Chiller 2 Chiller 3 Chiller 4 Chiller 5 Chiller 0% 20% 40% 60% 80% 100% 20 40 60 80 100 120
Percentage of Full Load Amp Cooling Load Intensity
Bldg E
1 Chiller 2 Chiller 3 Chiller 4 Chiller
Extra chiller in operation Chiller
high % FLA
23
Delta T of Chilled Water issue
Delta T of Chilled Water 3 Chillers Zone 2 Chillers Zone 1 Chiller Zone Delta T of Chilled Water Design Value Cooling Load/m2
through chillers or bypass pipe)
Large Delta -T Small Delta-T
24
Delta T of Chilled Water issue
0.0 1.0 2.0 3.0 4.0 5.0 6.0 20 40 60 80 100
Delta T of Chilled Water (°C) Cooling Load Intensity
Bldg B
1 WCC 0.5ACC + 0.5WCC
One chiller capacity but two pumps
0.0 1.0 2.0 3.0 4.0 5.0 6.0 20 40 60 80 100 120
Delta T of Chilled Water (°C) Cooling Load Intensity
Bldg E
1 Chiller 2 Chiller 3 Chiller 4 Chiller
Extra flow through chiller
0.0 1.0 2.0 3.0 4.0 5.0 6.0 20 40 60 80 100 120
Delta T of Chilled Water (°C) Cooling Load Intensity
Bldg C
1 Chiller 2 Chiller 3 Chiller 4 Chiller 5 Chiller
Extra flow through bypass pipe
25
%Bypass Flow issue
26
%Bypass Flow issue
0% 50% 100% 150% 200% 250% 20 40 60 80 100 120
Percentage of Bypass Flow Rate Cooling Load Intensity
Bldg C
1 Chiller 2 Chiller 3 Chiller 4 Chiller 5 Chiller
Extra flow through bypass pipe
27
Using thermal & electricity performance line
Consumption/Load Intensity Outdoor T emperature COP keeps constant Consumption/Load Intensity Outdoor T emperature COP increases at part load Consumption/Load Intensity Outdoor T emperature COP decreases at part load
28
Using Coefficient of Performance line
Cooling Load Intensity Coefficient of Performance (COP) COP = constant
VSD Water-cooled 5 10 15 20 40 60 80 100 120 COP Cooling Load Intensity
Bldg A
CSD Water-cooled
4 9 14 20 40 60 80 100 120 COP Cooling Load Intensity
Bldg C
CSD Air-cooled 2 4 6 8 10 12 14 20 40 60 80 100 120 COP Cooling Load Intensity
Bldg E
Note: Not sufficient data for Building B (No COP data),
CSD Air-cooled
4 9 14 20 40 60 80 100 120 COP Cooling Load Intensity
Bldg D
new chiller Old Chiller VSD Air-cooled
30
Common Problems on Chiller Plant Systems Bld A Bld B Bld C Bld D Bld E Chillers Improper chiller sequencing * Serious chiller deterioration Pumps (chilled water flow) Low/improper bypass valve setting Deviation on chilled water flow rates across each chiller Primary variable flow design but not fully in
N/A N/A N/A Cooling towers High approach temp N/A N/A
*One chiller is sufficient to provide cooling over a year
31
Suggested Re-tuning Work Bld A Bld B Bld C Bld D Bld E Chillers Reduce chiller operation (N-1) to achieve higher
*1
*2
Increase Tcws
*2
Pumps (chilled water flow) Re-tune bypass valve setting Install differential pressure sensors at the critical path Install VSD on the existing chilled water pumps N/A
*2
N/A Cooling towers Reactive cooling tower (CT) optimisation N/A N/A N/A
*1 One chiller is sufficient to provide cooling over a year *2 Serious chiller deterioration limited improvement
32
Suggested Re-tuning Work Bld A Bld B Bld C Bld D Bld E Chillers Reduce chiller operation (N-1) to achieve higher
5-6% (Actual)
*1
3-5% (Potential)
*2
3-5% (Potential)
Increase Tcws
1-3% (Potential) 1-3% (Potential)
*2
1-3% (Potential)
0-1% (Potential) 1-3% (Potential) 0-1% (Potential) 1-2% (Potential) 0-1% (Potential)
Pumps (chilled water flow) Re-tune bypass valve setting
1-3% (Potential) 1-3% (Potential) 1-3% (Potential)
Install differential pressure sensors at the critical path
1-3% (Potential) 1-3% (Potential)
Install VSD on the existing chilled water pumps
N/A 3-5% (Potential) 3-5% (Potential)
*2
N/A
Cooling towers Reactive cooling tower (CT) optimisation
N/A N/A
1-3% (Potential)
N/A
1-3% (Potential)
*1 One chiller is sufficient to provide cooling over a year *2 Serious chiller deterioration limited improvement
33
Suggested Re-tuning Work Bld A Bld B Bld C Bld D Bld E Chillers Reduce chiller operation (N-1) to achieve higher
<1 year *1 3-5 year *2 <1 year
Increase Tcws
<1 year <1 year *2 <1 year
<1 year <1 year <1 year <1 year <1 year
Pumps (chilled water flow) Re-tune bypass valve setting
<1 year <1 year <1 year
Install differential pressure sensors at the critical path
<1 year <1 year
Install VSD on the existing chilled water pumps
N/A 3-5 year 3-5 year *2 N/A
Cooling towers Reactive cooling tower (CT) optimisation
N/A N/A <1 year N/A <1 year
*1 One chiller is sufficient to provide cooling over a year *2 Serious chiller deterioration limited improvement
34
Review and identify improvements needed from last audit : Quality of measurement , methodology , robustness of data , value of data, readiness of building operators and REA..etc Learn where to focus Setting a foundation for the future : New requirements for data and information for future management, tracking and analysis ( for buildings, industry and government) Useful O&M manual Benchmarking Building capacity ( building provisions, knowledge , specially trained REA.. ) Central data center Setting up energy management systems
40
Case Study: Problem in Air Handling Unit
Always open Always close
Diagno nosi sis
Are our systems working?
Hotels New Development Commercial Bldgs
Existing Bldg A 145 136 (50th%) 2011 2016
How do we compare with others?
Opportunities
Benchma marki king ng
Long T g Term P Planni nning ng
Can we have a 10-year plan?
Saving = 9,858kWh/year Saving Estimation
ANAL YSIS
How much can you save?
Knowledge-Based Energy Management
Sensors
Analysis Useful Information Utilise Information
Data Transmission
Data Bank BMS
Always close
Saving E g E stim imat atio ion M&V &V M Met ethod
Fau ault lt D Diag iagnosis Long T Term P Planni nning ng Oppor
es
Characteristic
Sources: Swire Properties Ltd
Action Research
Lack of market drives
Software not user friendly
High investment
justified
Data missing
transmission and storage problem
Inaccurate data
malfunction/ improper location & error
Inconsistent data format
& power metering systems not interoperable
Lack of support
Inadequate hardware
meter / DP sensors
system base
DATA F ACILITIE S BUSINE SS
Lack of Specification
requirement and standards for reference
ACT-shop
Knowledge - Why Operating Data Not Commonly Used?
Collaboration issues within the Industry
Owner Designer Operator Contractor
based management
concept
performance analysis
Manufacturer
emphasis
ACT-shop
Key Performance Indicators
DATA INFORMATION
How Efficient is Our Plant?
BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS
Quality of Data
Problems:
Technical Challenges
Run to Life Retrofit Knowledge transfer Early Replacement House keeping General Practices & Regulatory Compliance Optimization
Continuous Improvement
Chiller Lighting Advanced Control Air-cool Water-cool Lift Modernization Retro-Cx Metering Work with stakeholders Routine Inspection
Knowledge-Based Practice
Adopt Best Practice
Maintenance Requirement
Routine Maintenance Mandatory Audit O&M Manual
Basic Need
Saving ~17% Saving >24%
Transformation of the Current Industry
Building Operator
Services Provider
In-house Competence e-O&M Manual Develop & drive the products / services markets Saving Business knowledge Beyond Standard
industry
method / format
Industry
HKIE BSOMES ASHRAE RICS…
Education
VTC/IVE Universities
ACT SHOP
Establish Knowledge Sharing Platform
Analysis & Benchmarking (Opportunities?)
How Data Helps
Tool
Diagnosis (Any fault?)
How Data Helps
Tool
Case Study: Problem in Air Handling Unit
Case Study: Problem in Air Handling Unit
Problem Verification
Case Study: Problem in Air Handling Unit
After problem solving
Re-tune (Implementation)
How Data Helps
Approach
Tool
ΔT
ΔT , design = 5°C Data of ΔT high condensing differential temperature
Design Real Operation
Underflow 7°C
Any Deviation?
Entering Cooling Tower Cooling Tower To BMS
P P
Flow con
collector collector
1m
Leaving Entering Cooling Tower Cooling Tower To BMS
P P
Flow con
collector collector
1m
Leaving Leaving
T T
to remove the flow-con:
Underflow Increase pressure Reduce resistance
More consumption
lower 7°C 4.5°C
Problem Identification & Rectification
kPa
Riser iser A B C D E F Criti ritica cal A l AHU 33.5 35.2 37.4 37.8 35.5 35.8 Targe arget 54 56 57 58 56 56
ΔP ΔP ΔP ΔP ΔP ΔP
Return Supply
Riser A Riser B Riser C Riser D Riser E Riser F
Design Real Operation Vs.
Any Deviation?
Restricted by under-sized AUHs Renovation of under- sized AUHs A B C D E F
Original
85 110 95 95 100 100 Step 1 85 110 90 90 100 100 Step 2 75 110 80 80 80 80 Step 3 70 80 70 70 70 70
Summer time exercise Winter time ??
∆P reset
Over pressurized
Problem Identification & verification
How Data Helps
BIN Method
Tool
Saving Estimation, Measurement & Verification “Conversion from IGV to VSD control”
Manufacturer claimed saving cannot be identified Performance indicator to be verified against % loading at particular range of impact factor(s)
Energy Management – Long term Plan
(Are we achieving our target?)
reporting
How Data Helps
Tool
Buildings in HK account for:
Measurement and Verification
Condition 1 Condition 2 Condition 3