Existing Building Energy Saving Ir Cary Chan Executive Director, - - PowerPoint PPT Presentation

existing building energy saving
SMART_READER_LITE
LIVE PREVIEW

Existing Building Energy Saving Ir Cary Chan Executive Director, - - PowerPoint PPT Presentation

Existing Building Energy Saving Ir Cary Chan Executive Director, HK Green Building Council Aviation industry 1981 1971 1969 1930s 1903 2 3 4 5 6 A big gap to fill 7 Convincing responses to your boss ! Deliver ! Implementation of


slide-1
SLIDE 1

Existing Building Energy Saving

Ir Cary Chan

Executive Director, HK Green Building Council

slide-2
SLIDE 2

2

Aviation industry

1903 1930s 1969 1981 1971

slide-3
SLIDE 3

3

slide-4
SLIDE 4

4

slide-5
SLIDE 5

5

slide-6
SLIDE 6

6

slide-7
SLIDE 7

7

A big gap to fill

slide-8
SLIDE 8

Convincing responses to your boss ! Deliver !

slide-9
SLIDE 9

E nergy Management Process

Implementation of energy management

DATABASE POLICY OBJECTIVE & TARGET ACTION PLAN AUDIT MEASUREMENT & VERIFICATION REVIEW MEETING & REPORT ANALYSIS

ACT PLAN

IMPLEMENTATION

DO CHE CK

Knowledge-based DIAGNOSIS (Retro-Cx) BENCHMARKING

slide-10
SLIDE 10

10

slide-11
SLIDE 11

Design parameters Load calculation System design Equipment selection T esting and commissioning

slide-12
SLIDE 12

Idea of ACT

  • Shop
  • Groups of representatives from buildings going through a retro-commissioning process
  • Buildings as living laboratories
  • HKGBC as facilitator
  • Learning from peers
  • Building up knowledge

Together

slide-13
SLIDE 13
slide-14
SLIDE 14

In participating in the ACT

  • Shop programme :
  • Actively supporting HK gov’s energy saving plan
  • Building up the competence for the industry on retro-

commissioning through

  • developing the data/knowledge base
  • developing a systematic approach for retro-commissioning
  • demonstrating the value of retro-commissioning
  • transferring the knowledge and skills to the industry
  • establishing a practical operation & management system
  • Promoting the adoption of best practices to the

industry

slide-15
SLIDE 15

Initial findings

slide-16
SLIDE 16

Different types of building, system design , age..

Bldg A Bldg B Bldg C Bldg D Bldg E Type Composite Hotel Composite (Podium+ T

  • wers)

Composite (Office +Education) Office (Industrial Building Renovation) Age (Yrs) 25 41 24 20 20 IFA (sqm) ~20,000 ~36,000 ~150,000 ~4,500 ~45,000 Chiller 4x320TR Water-Cooled (new) 4x180TR Water-cooled 4x190TR Air-cooled (new) 7x1000TR Water-cooled 2x400TR Water-cooled(Night) 1x150TR Air-cooled 1x150TR Air-cooled (new) 4x400TR Air-cooled Cooling T

  • wer

4 4 6+2 N/A N/A Control Differential Pressure Bypass Differential Pressure Bypass Differential Pressure Bypass Differential Pressure Bypass Differential Pressure Bypass Pumps 4+1 Water-cooled: 4 Air-cooled: 4+1 7+2 4+2 (Office T

  • wer)

2+1 4+1 Features Variable Speed Chiller 140TR Heat Pump for hot water Heat Exchanger for high rise office tower natural ventilation allowed Fresh air treated by FCU

slide-17
SLIDE 17

Availability of data and information varies !

slide-18
SLIDE 18

Approach a and Met etho hod

Has to consider :

  • Practicality
  • Minimum provision of instrument
  • Availability of data and information
slide-19
SLIDE 19

19

“ACT

  • Shop” – Data Analysis Method

(retro-Cx)

2.

Performance line evaluation

3.

Peak demand shedding

Outdoor Ambient Temperature Loading Valve Authority 24:00 Peak Demand 0:00

summer winter

Control Set-point

Re-tune:

  • Discharge valve
  • Double regulating

valve, etc.

Cooling Load %load

100%

Re-tune: 1. DTCHWS 2. DTA 3. DSP

2 3

1.1 1.2 1.3

6

Outdoor Ambient Temperature Cooling load

4. Set-point reset 1. Re-tune

1.1 Valve authority 1.2 Set-point 1.3 Equipment operation

4. DPWS 5. TAPP

,C

6. TAPP

,C T

slide-20
SLIDE 20

20

““ACT

  • Shop” – Data Analysis Method

(retro-Cx)

Bldg A Bldg B Bldg C Bldg D Bldg E

DTCHWsummer DTCHWwinter 5.0°C 2.5°C 5.0°C 3.2°C 5.0°C 3.0°C 2.5°C 0.75°C 3.4°C 2.0°C TCHWSsummer TCHWSwinter 7.8°C 10°C 7°C 11°C 8°C 9.5°C 9.5°C 14°C 8.5°C 10°C COP,CHsummer COP,Chwinter 6.3 13 3.3 3.4 5.3 4.2 3.2 2.9 1.6 2.5 EUI(Chiller) 60 kWh/m2/year 115 kWh/m2/year 88 kWh/m2/year 33 kWh/m2/year 48.3 kWh/m2/year

Low CO P Low DTCH W TCHWS reset at winter

slide-21
SLIDE 21

21

  • 1. Re-tune – Chiller Operation

Cooling Load/m2

Percentage of Full Load Ampere (%FLA) 3 Chillers Zone 2 Chillers Zone 1 Chiller Zone 100% Full Load

  • Good operation
  • Poor operation (high % full load ampere due to deterioration of chiller

capacity)

More FLA Less FLA Extra chiller

slide-22
SLIDE 22

22

  • 1. Re-tune – Chiller operation (cont’d)

% Full Load Ampere issue

0% 20% 40% 60% 80% 100% 20 40 60 80 100 120

Percentage of Full Load Amp Cooling Load Intensity

Bldg C

1 Chiller 2 Chiller 3 Chiller 4 Chiller 5 Chiller 0% 20% 40% 60% 80% 100% 20 40 60 80 100 120

Percentage of Full Load Amp Cooling Load Intensity

Bldg E

1 Chiller 2 Chiller 3 Chiller 4 Chiller

Extra chiller in operation Chiller

  • perate at

high % FLA

slide-23
SLIDE 23

23

  • 1. Re-tune – Chiller Operation (cont’d)

Delta T of Chilled Water issue

Delta T of Chilled Water 3 Chillers Zone 2 Chillers Zone 1 Chiller Zone Delta T of Chilled Water Design Value Cooling Load/m2

  • Good operation
  • Poor operation (narrow delta T due to excessive flow

through chillers or bypass pipe)

Large Delta -T Small Delta-T

slide-24
SLIDE 24

24

  • 1. Re-tune – Chiller Operation (cont’d)

Delta T of Chilled Water issue

0.0 1.0 2.0 3.0 4.0 5.0 6.0 20 40 60 80 100

Delta T of Chilled Water (°C) Cooling Load Intensity

Bldg B

1 WCC 0.5ACC + 0.5WCC

One chiller capacity but two pumps

0.0 1.0 2.0 3.0 4.0 5.0 6.0 20 40 60 80 100 120

Delta T of Chilled Water (°C) Cooling Load Intensity

Bldg E

1 Chiller 2 Chiller 3 Chiller 4 Chiller

Extra flow through chiller

0.0 1.0 2.0 3.0 4.0 5.0 6.0 20 40 60 80 100 120

Delta T of Chilled Water (°C) Cooling Load Intensity

Bldg C

1 Chiller 2 Chiller 3 Chiller 4 Chiller 5 Chiller

Extra flow through bypass pipe

slide-25
SLIDE 25

25

  • 1. Re-tune – Chiller Operation (cont’d)

%Bypass Flow issue

slide-26
SLIDE 26

26

  • 1. Re-tune – Chiller Operation (cont’d)

%Bypass Flow issue

0% 50% 100% 150% 200% 250% 20 40 60 80 100 120

Percentage of Bypass Flow Rate Cooling Load Intensity

Bldg C

1 Chiller 2 Chiller 3 Chiller 4 Chiller 5 Chiller

Extra flow through bypass pipe

slide-27
SLIDE 27

27

  • 2. Performance line evaluation

Using thermal & electricity performance line

Consumption/Load Intensity Outdoor T emperature COP keeps constant Consumption/Load Intensity Outdoor T emperature COP increases at part load Consumption/Load Intensity Outdoor T emperature COP decreases at part load

slide-28
SLIDE 28

28

  • 2. Performance line evaluation (cont’d)

Using Coefficient of Performance line

Cooling Load Intensity Coefficient of Performance (COP) COP = constant

slide-29
SLIDE 29
  • 2. Performance line evaluation (cont’d)

VSD Water-cooled 5 10 15 20 40 60 80 100 120 COP Cooling Load Intensity

Bldg A

CSD Water-cooled

  • 1

4 9 14 20 40 60 80 100 120 COP Cooling Load Intensity

Bldg C

CSD Air-cooled 2 4 6 8 10 12 14 20 40 60 80 100 120 COP Cooling Load Intensity

Bldg E

Note: Not sufficient data for Building B (No COP data),

CSD Air-cooled

  • 1

4 9 14 20 40 60 80 100 120 COP Cooling Load Intensity

Bldg D

new chiller Old Chiller VSD Air-cooled

slide-30
SLIDE 30

30

  • 1. Summary of Common Problems
  • n Chiller Plant Systems

Common Problems on Chiller Plant Systems Bld A Bld B Bld C Bld D Bld E Chillers Improper chiller sequencing  *    Serious chiller deterioration   Pumps (chilled water flow) Low/improper bypass valve setting      Deviation on chilled water flow rates across each chiller  Primary variable flow design but not fully in

  • peration

 N/A N/A N/A  Cooling towers High approach temp  N/A N/A

*One chiller is sufficient to provide cooling over a year

slide-31
SLIDE 31

31

  • 1. Summary of Re-tuning Work

Suggested Re-tuning Work Bld A Bld B Bld C Bld D Bld E Chillers Reduce chiller operation (N-1) to achieve higher

  • verall COP

*1

*2

 Increase Tcws  

*2

  • Max. demand shedding

     Pumps (chilled water flow) Re-tune bypass valve setting    Install differential pressure sensors at the critical path   Install VSD on the existing chilled water pumps N/A  

*2

N/A Cooling towers Reactive cooling tower (CT) optimisation N/A N/A  N/A 

*1 One chiller is sufficient to provide cooling over a year *2 Serious chiller deterioration  limited improvement

slide-32
SLIDE 32

32

  • 1. Saving Summary of Re-tuning Work

Suggested Re-tuning Work Bld A Bld B Bld C Bld D Bld E Chillers Reduce chiller operation (N-1) to achieve higher

  • verall COP

5-6% (Actual)

*1

3-5% (Potential)

*2

3-5% (Potential)

Increase Tcws

1-3% (Potential) 1-3% (Potential)

*2

1-3% (Potential)

  • Max. demand shedding

0-1% (Potential) 1-3% (Potential) 0-1% (Potential) 1-2% (Potential) 0-1% (Potential)

Pumps (chilled water flow) Re-tune bypass valve setting

1-3% (Potential) 1-3% (Potential) 1-3% (Potential)

Install differential pressure sensors at the critical path

1-3% (Potential) 1-3% (Potential)

Install VSD on the existing chilled water pumps

N/A 3-5% (Potential) 3-5% (Potential)

*2

N/A

Cooling towers Reactive cooling tower (CT) optimisation

N/A N/A

1-3% (Potential)

N/A

1-3% (Potential)

*1 One chiller is sufficient to provide cooling over a year *2 Serious chiller deterioration  limited improvement

slide-33
SLIDE 33

33

  • 1. Payback Summary of Re-tuning Work

Suggested Re-tuning Work Bld A Bld B Bld C Bld D Bld E Chillers Reduce chiller operation (N-1) to achieve higher

  • verall COP

<1 year *1 3-5 year *2 <1 year

Increase Tcws

<1 year <1 year *2 <1 year

  • Max. demand shedding

<1 year <1 year <1 year <1 year <1 year

Pumps (chilled water flow) Re-tune bypass valve setting

<1 year <1 year <1 year

Install differential pressure sensors at the critical path

<1 year <1 year

Install VSD on the existing chilled water pumps

N/A 3-5 year 3-5 year *2 N/A

Cooling towers Reactive cooling tower (CT) optimisation

N/A N/A <1 year N/A <1 year

*1 One chiller is sufficient to provide cooling over a year *2 Serious chiller deterioration  limited improvement

slide-34
SLIDE 34

34

slide-35
SLIDE 35

make the most out of the next Energy Audit

Review and identify improvements needed from last audit : Quality of measurement , methodology , robustness of data , value of data, readiness of building operators and REA..etc Learn where to focus Setting a foundation for the future : New requirements for data and information for future management, tracking and analysis ( for buildings, industry and government) Useful O&M manual Benchmarking Building capacity ( building provisions, knowledge , specially trained REA.. ) Central data center Setting up energy management systems

slide-36
SLIDE 36

Performance Assessment Development of KPI (Air conditioning)

slide-37
SLIDE 37

Performance Assessment - KPI benchmarking

slide-38
SLIDE 38

Performance Assessment -KPI benchmarking

slide-39
SLIDE 39

Performance Assessment - KPI benchmarking

slide-40
SLIDE 40

40

slide-41
SLIDE 41

Case Study: Problem in Air Handling Unit

slide-42
SLIDE 42

Always open Always close

Diagno nosi sis

Are our systems working?

slide-43
SLIDE 43

Hotels New Development Commercial Bldgs

Existing Bldg A 145 136 (50th%) 2011 2016

How do we compare with others?

Opportunities

Benchma marki king ng

slide-44
SLIDE 44

Long T g Term P Planni nning ng

Can we have a 10-year plan?

slide-45
SLIDE 45

Saving = 9,858kWh/year Saving Estimation

ANAL YSIS

How much can you save?

slide-46
SLIDE 46

Knowledge-Based Energy Management

Sensors

Analysis Useful Information Utilise Information

  • Facilitate Research
  • Implement Initiatives

Data Transmission

Data Bank BMS

Always close

Saving E g E stim imat atio ion M&V &V M Met ethod

  • d

Fau ault lt D Diag iagnosis Long T Term P Planni nning ng Oppor

  • rtunities

es

slide-47
SLIDE 47

Characteristic

Sources: Swire Properties Ltd

Action Research

slide-48
SLIDE 48

Difficulties

Lack of market drives

  • Not aware benefit
  • f using data

Software not user friendly

  • Proprietary product

High investment

  • Cost not directly

justified

  • Product upgrade
  • Staff training

Data missing

  • Massive data

transmission and storage problem

Inaccurate data

  • Sensor

malfunction/ improper location & error

Inconsistent data format

  • Bldg. Mgt. Systems

& power metering systems not interoperable

Lack of support

  • Not much demand

Inadequate hardware

  • Power meter / Flow

meter / DP sensors

  • n equipment/

system base

DATA F ACILITIE S BUSINE SS

Lack of Specification

  • There is no any

requirement and standards for reference

ACT-shop

Knowledge - Why Operating Data Not Commonly Used?

slide-49
SLIDE 49

Barriers

Collaboration issues within the Industry

Owner Designer Operator Contractor

  • Inadequate drives for knowledge

based management

  • Focus on project cost only
  • Lacks BMS/PMS/DMS expertise
  • Lacks O&M experiences
  • Shortage of construction time
  • Inadequate T&C and re-commissioning

concept

  • Focus on services reliability for tenants
  • Lack of interest and capabilities in

performance analysis

Manufacturer

  • Focus on functional operation needs only
  • Value of information management not

emphasis

  • Lacks of interest in O&M market
  • Emphasis on cost competitiveness

ACT-shop

slide-50
SLIDE 50

Output Input Efficiency =

Key Performance Indicators

DATA  INFORMATION

How Efficient is Our Plant?

slide-51
SLIDE 51

BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS BMS

Quality of Data

  • Accuracy
  • Right Form
  • Accessibility

Problems:

  • Missing data
  • Incorrect form of data
  • Huge data volume and scale
  • Incompetence in analysis

Technical Challenges

slide-52
SLIDE 52 . . .

Run to Life Retrofit Knowledge transfer Early Replacement House keeping General Practices & Regulatory Compliance Optimization

Continuous Improvement

Chiller Lighting Advanced Control Air-cool  Water-cool Lift Modernization Retro-Cx Metering Work with stakeholders Routine Inspection

Knowledge-Based Practice

Adopt Best Practice

Maintenance Requirement

Routine Maintenance Mandatory Audit O&M Manual

Basic Need

Saving ~17% Saving >24%

Transformation of the Current Industry

slide-53
SLIDE 53

Building Operator

  • Government
  • Private Sector

Services Provider

In-house Competence e-O&M Manual Develop & drive the products / services markets Saving Business knowledge Beyond Standard

  • Detailed databank
  • Develop competence within the

industry

  • Standardise energy analysing

method / format

  • Raise next energy audit standard
  • Robust benchmarking system

Industry

HKIE BSOMES ASHRAE RICS…

Education

VTC/IVE Universities

ACT SHOP

Establish Knowledge Sharing Platform

slide-54
SLIDE 54
slide-55
SLIDE 55

Analysis & Benchmarking (Opportunities?)

  • Fault detection

How Data Helps

  • Time series analysis
  • Expert rules

Tool

slide-56
SLIDE 56

Diagnosis (Any fault?)

  • Fault detection

How Data Helps

  • Time series analysis
  • Expert rules

Tool

slide-57
SLIDE 57

Case Study: Problem in Air Handling Unit

slide-58
SLIDE 58

Case Study: Problem in Air Handling Unit

Problem Verification

slide-59
SLIDE 59

Case Study: Problem in Air Handling Unit

After problem solving

slide-60
SLIDE 60

Re-tune (Implementation)

  • Optimise operation

How Data Helps

  • Engineering

Approach

Tool

slide-61
SLIDE 61

ΔT

ΔT , design = 5°C Data of ΔT high condensing differential temperature

Design Real Operation

Underflow 7°C

Any Deviation?

slide-62
SLIDE 62

Entering Cooling Tower Cooling Tower To BMS

P P

Flow con

collector collector

1m

Leaving Entering Cooling Tower Cooling Tower To BMS

P P

Flow con

collector collector

1m

Leaving Leaving

T T

to remove the flow-con:

  • higher water flow rate
  • lower condensation temperature
  • higher chiller efficiency

Underflow Increase pressure Reduce resistance

More consumption

lower 7°C 4.5°C

Problem Identification & Rectification

slide-63
SLIDE 63

kPa

Riser iser A B C D E F Criti ritica cal A l AHU 33.5 35.2 37.4 37.8 35.5 35.8 Targe arget 54 56 57 58 56 56

ΔP ΔP ΔP ΔP ΔP ΔP

Return Supply

Riser A Riser B Riser C Riser D Riser E Riser F

Design Real Operation Vs.

Any Deviation?

slide-64
SLIDE 64

Restricted by under-sized AUHs Renovation of under- sized AUHs A B C D E F

Original

85 110 95 95 100 100 Step 1 85 110 90 90 100 100 Step 2 75 110 80 80 80 80 Step 3 70 80 70 70 70 70

Summer time exercise Winter time ??

∆P reset

Over pressurized

Problem Identification & verification

slide-65
SLIDE 65
  • Saving Estimation

How Data Helps

  • Regression model +

BIN Method

Tool

Saving Estimation, Measurement & Verification “Conversion from IGV to VSD control”

slide-66
SLIDE 66

Retrofit – Saving Estimation

slide-67
SLIDE 67

Retrofit – Measurement & Verification

Manufacturer claimed saving cannot be identified Performance indicator to be verified against % loading at particular range of impact factor(s)

slide-68
SLIDE 68

Energy Management – Long term Plan

(Are we achieving our target?)

  • Energy management

reporting

How Data Helps

  • Cumulative frequency plot

Tool

slide-69
SLIDE 69

Buildings in HK account for:

90% Total Electricity Consumption

60% Greenhouse Gas Emission

Existing Buildings account for

90% of HK Building Stock

slide-70
SLIDE 70

Achievement and Target

slide-71
SLIDE 71

Cost and Benefit

slide-72
SLIDE 72

Database

slide-73
SLIDE 73

Measurement and Verification

Condition 1 Condition 2 Condition 3

Did it work?