EVALUATION OF EFFECT OF PMP ESTIMATION ON PMF ESTIMATES Sagar - - PowerPoint PPT Presentation

evaluation of effect of pmp estimation on pmf estimates
SMART_READER_LITE
LIVE PREVIEW

EVALUATION OF EFFECT OF PMP ESTIMATION ON PMF ESTIMATES Sagar - - PowerPoint PPT Presentation

Third National Dam Safety Conference 16-17 February 2017, Roorkee EVALUATION OF EFFECT OF PMP ESTIMATION ON PMF ESTIMATES Sagar Rohidas Chavan and V. V. Srinivas Department of Civil Engineering Indian Institute of Science Introduction M ajor


slide-1
SLIDE 1

EVALUATION OF EFFECT OF PMP ESTIMATION ON PMF ESTIMATES

Sagar Rohidas Chavan and V. V. Srinivas

Department of Civil Engineering Indian Institute of Science

Third National Dam Safety Conference 16-17 February 2017, Roorkee

slide-2
SLIDE 2

M ajor Hydrologic Structures (e.g., dams which are located upstream

  • f thickly populated areas and/or nuclear

facilities)

2

Source: Electronic media

DESIGN FLOOD

PROBABLE M AXIM UM FLOOD (PM F)

DESIGN RAINF ALL

PROBABLE M AXIM UM PRECIPITATION (PM P)

Limiting case

PM P: greatest depth of precipitation for a given duration that is meteorologically possible for a watershed (WM O 1986, 2009)

Introduction

slide-3
SLIDE 3

PM P Estimation: HERSHFIELD M ETHOD; M UL TIFRACTAL APPROACH Rainfall-runoff relation: EQUIVALENT GEOM ORPHOLOGICAL INSTANTANEOUSUNIT HYDROGRAPH (E-GIUH) Dam break Analysis & Inundation map : HEC-RAS& HEC-Geo RAS

3

Paper Title: EVALUATION OF EFFECT OF PM P ESTIM ATION ON PM F ESTIM ATES

slide-4
SLIDE 4

 Frequency analysis of annual maximum precipitation records

4

Hershfield M ethod [Hershfield 1961, 1965]

4 6 8 10 12 14 16 18 2 4 6 8 10 12

Mean annual maximum 1-day precipitation (cm) Frequency Factor (Km)

 

 

 

 

 

t

env t t n m n

PMP t X k   

t-target location

       

1 1

1, ,

i i i M n m i n

X X k i N 

 

   

(or)

slide-5
SLIDE 5

ICWRCOE 2015 5

Chavan, S. R., and Srinivas, V. V. (2017), Regionalization based envelope curves for PM P estimation by Hershfield method. International Journal

  • f

Climatology, Wiley & Royal M eteorological Society, doi: 10.1002/ joc.4951

R

A is introduced to increase proximity

  • f

the envelope curve to points depicting sites having ‘low M AMP and high FF’ as well as ‘high M AMP and low FF’

+L +L +L L U

slide-6
SLIDE 6

 M ultifractal field : Precipitation intensity,  Properties at different temporal scales described using scale-

invariant M ultiplicative Cascade M odel

 Design Probable M aximum Precipitation (DPM P)

Pr > ∼

= 10 : codimension function

6

M ultifractal Approach (M A)

 

 

     

1 e e

c ln p ln ln T ln   

  L   

Scale ratio (Douglas and Barros (2003)

slide-7
SLIDE 7

7

Figure:Empirical PDF of showing hyperbolic falloff, indicating large influence of extreme events on tail probabilities

Test for presence of fractality in observed precipitation

slide-8
SLIDE 8

8

100 1,000 1 10 Aλ (mm10) Duration, τ (days)

Figure: Verification of scaling relationship

= 10

 

 

     

1 e e

c ln p ln ln T ln   

 

Intercept=B M axima of accumulated rainfall

L   

Scale ratio

: codimension function

Design Probable M aximum Precipitation (DPM P)

slide-9
SLIDE 9

Case S (km2) Ω n T (km) Ra Rb Rl 1 0.9 5 756 2172 4.99 5.00 2.73 2 4.5 4 152 988 5.77 5.02 2.82 3 9 4 74 694 4.85 4.18 2.15 4 22.5 3 29 432 6.68 5.39 3.45

 

1 1 0.78 0.07 0.48

( ) (hour ) where 3.29 (adimensional) 0.70 (hours)

t m k b l a a b l

t e GIUH t k k m R m R R R L k R R v

         

                                  

Modeling hydrological response of catchments using geomorphological concepts

slide-10
SLIDE 10

10

Time (hour)

20 40 60 80 100 0.035 0.07

Time (hour) GIUH (1/hour)

slide-11
SLIDE 11

11

Moussa (1996) derived the following formulations for n (number of sources) and T (total length of stream network)

Self-similarity properties of channel networks

 

n S S

10

  • 4

10

  • 3

10

  • 2

10

2

10

3

S/S0 n

10

  • 4

10

  • 3

10

  • 2

10

6

10

7

S/S0 T (km)

 

1 2 A

S T OE S S S

 

 

          

A typical channel network for S = SA

burnt_ASTER burnt_SRTM SRTM ASTER

slide-12
SLIDE 12

 Equivalent H-Sratios:  Scaling properties: , : Equivalent length of highest order stream (km) : Representative peak flow velocity in the catchment (km/ h)

1

2

ae

R

 

       

1 2

2

le

R

 

       

2

be

R

 

Equivalent GIUH  

0.78 1 0.07 0.48

0.5 0.5 1

E-GIUH ; where 3.29 0.70

2

t m k be le ae ae e be le

be le e le

t e R m R k k m R R L k R R v

R R S L OE S S R

       

                                     

  

slide-13
SLIDE 13

13 Time (hour) Time (hour)

20 40 60 80 100 0.035 0.07

Time (hour) GIUH (1/hour)

20 40 60 80 0.025 0.05

Time (hour) E-GIUH (1/hour) Figure: GIUHs and E-GIUHs constructed for stream networks

ASTER DEM based GIUH H SRTM DEM based GIUH

SRTM DEM based E-GIUH ASTER DEM based E-GIUH burnt _SRTM DEM based E-GIUH burnt _ASTER DEM based E-GIUH

slide-14
SLIDE 14

Catchment area : 2810 km2 Location: Gorur (near Hassan) in Cauvery river basin, Karnataka Dam features: Height: 58 m; Length: 4692 m Gross storage capacity: 964 M CM Spillway capacity: 3624.5 cumecs

Case study on Hemavathy dam

14

slide-15
SLIDE 15

SRTM DEM Daily Streamflow(1977 to 2011) Daily rainfall : 49 rain gauges (1970-2011)

  • Nine

major flood events for calibration of velocity

  • -index technique to determine

effective rainfall hyetographs (ERHs)

  • Areal

average PM P estimation (Thiessen polygon; Kriging)

15

Description of data and methodology

slide-16
SLIDE 16

Results

slide-17
SLIDE 17

Flow velocity corresponding to PM P

17

Range-1(i  35mm/ day) Range-2 (i >35 mm/ day)

Representative velocity v corresponding to each of the 9 major flood events in the catchment was estimated through calibration by genetic algorithm (GA)

slide-18
SLIDE 18

18

PM P estimates obtained based on HM and M A

200 400 600 800 1000

HM M A-100 M A-500 M A-1000

2-day PM P

y y y (mm)

200 400 600 800 1000

HM M A-100 M A-500 M A-1000

3-day PM P

y y y (mm)

slide-19
SLIDE 19

19

PM F hydrographs obtained based on HM and M A

Existing spillway capacity of the dam: 3,624.5 m3/s

0.0E+0 2.0E+3 4.0E+3 6.0E+3 8.0E+3 1.0E+4 1.2E+4 1.4E+4 1.6E+4 1.8E+4 50 100 150 PM F (m3/ s) Time (hours)

PM P duration = 2 days

0.0E+0 2.0E+3 4.0E+3 6.0E+3 8.0E+3 1.0E+4 1.2E+4 50 100 150 PM F (m 3/ s) Time (hours)

PMP duration = 3 days

PM P(HM )>> PM P(CWC)10,000 m3/ s >> PM P (M A)

slide-20
SLIDE 20

20

Table 2. Dam breach Data

Breach method Froehlich (2008) Top of dam elevation 894.81 m Breach bottom elevation 850 m Pool elevation at failure 894.1 m Pool volume at failure 1050.6 M m3 Failure mode Overtopping Dam Crest Width 2.44 m Slope of U/ S Dam face Z1 (H:V) 3:1 Slope of D/ S Dam face Z2 (H:V) 2:1 Water surface elevation that triggers failure 894.81 m Breach formation time (h) 4.05 Breach section side slopes (H:V) 1:1 Final bottom width of breach 270 m Final bottom elevation of breach 850 m Breach weir coefficient 2.6

slide-21
SLIDE 21

21

Average Breach Width Vw : water volume above the breach bottom at the time of failure which can be considered as volume of water in the reservoir at the time of failure (1050.6 M m3)

slide-22
SLIDE 22

ICWRCOE 2015 22

Breach Formation time Hb : Height of water above the breach bottom at the time of failure (Height of the dam=44.81 m)

slide-23
SLIDE 23

23

slide-24
SLIDE 24

HM M ultifractal

Inundation map corresponding to 2-day duration PM P

slide-25
SLIDE 25

ICWRCOE 2015 25

20000 40000 60000 80000 100000 750 800 850 900 950

DBA_hema_Hersh_2day Plan: Plan_25km_Hersh2day 2/17/2017

Main Channel Distance (m) Elevation (m) Legend EG Max WS WS Max WS Crit Max WS Ground Hema_25 1

maximum height/ depth of water reached during the flood event based on HM

20000 40000 60000 80000 100000 740 760 780 800 820 840 860 880 900

DBA_hema_MA_1000 Plan: Plan_25km_MA1000_2day 2/17/2017

Main Channel Distance (m) Elevation (m) Legend EG Max WS WS Max WS Crit Max WS Ground Hema_25 1

slide-26
SLIDE 26
  • Uncertainty in PM P & PM F estimates cannot be ignored in dam

break analysis studies.

  • Implications of the uncertainty on area inundated downstream of

dams is worth investigation

Conclusion

26

Acknowledgements

  • Directorate of Economics and statistics, Bangalore
  • Water Resources Development Organization (WRDO), Karnataka
  • Central Water Commission (CWC)
slide-27
SLIDE 27

Thank you

slide-28
SLIDE 28

Bernardara P., Schertzer D., Sauquet E., Tchiguirinskaia I, Lang M. (2008). The flood probability distribution tail: how heavy is it? Stochastic Environmental Research and Risk Assessment, 22(1): 107-122. Chavan, S. R., and Srinivas, V. V. (2015) Effect of DEM Source on Equivalent Horton-Strahler Ratio based GIUH for Catchments in Two Indian River Basins. Journal of Hydrology, Elsevier, Netherlands, 528 (1-4): 463-489. Chavan, S. R., and, Srinivas, V. V. (2016) An approach to assess impact of climate change on estimates of PMP and PMF, Proceedings of Second National Dam Safety Conference, IISc Bangalore, 12-13 January, 2016, pp.55-63. Chow, V. T., Maidment, D. R., and Mays, L. W. (1988). Applied hydrology. Mc-Graw Hill, New York. Douglas, E. M., and Barros, A. P. (2003) Probable Maximum Precipitation Estimation Using Multifractals: Application in the Eastern United States. Journal of Hydrometeorology, 4: 1012–1024. Gupta, V. K., Waymire, E., and Wang, C.T. (1980) A representation of an instantaneous unit hydrograph from geomorphology. Water Resources Research. 16(5): 855–862. Hubert, P., Tessier, Y., Lovejoy, S., Schertzer, D., Schmitt, F., Ladoy, P., Carbonnel, J.P., Violette, S., and Desurosne, I. (1993) Multifractals and extreme rainfall events. Geophysical Research Letters, 20(10): 931-934. Moussa, R. (2009) Definition of new equivalent indices of Horton-Strahler ratios for the derivation of the Geomorphological Instantaneous Unit Hydrograph. Water Resources Research, 45, W09406. DOI: 10.1029/2008WR007330. Rodríguez-Iturbe, I., and Valdés, J. B. (1979) The geomorphologic structure of hydrologic response. Water Resources Research, 15(6): 1409 – 1420. Rosso, R. (1984) Nash model relation to Horton order ratios. Water Resources Research, 20(7): 914 – 921. Swain, R. E., England, J. F., Bullard, K. L., and Raff, D. A. (2004) Hydrologic hazard curve estimating

  • procedures. Research report DSO-04-08, U.S. Department of Interior, Bureau of Reclamation.

World Meteorological Organization (2009) Manual on Estimation of Probable Maximum Precipitation (PMP). World Meterological Organization, WMO-No. 1045, Geneva, Switzerland.

References

28

slide-29
SLIDE 29

29

Event No. Effective Rainfall Hyetograph (ERH) (mm) Direct Runoff Hydrograph (DRH) (m3/s) 1 10.23, 9.87 159.20, 366.96, 93.65, 14.22, 7.98 2 8.52, 18.52 243.48, 351.70, 81.16, 50.99, 12.48, 11.78 3 5.51, 38.02, 16.45, 3.93 349.96, 697.85, 501.88, 300.37, 201.51, 70.41, 36.41 4 7.73, 29.89 232.38, 693.69, 88.44, 55.84 5 3.49, 62.28, 67.74, 51.03 375.29, 1275.01, 1644.40, 339.17, 269.85, 190.42, 172.73, 97.12, 81.17, 78.39, 78.04 6 9.78, 21.63 324.30, 458.53, 65.90, 5.20 7 36.19, 102.59 767.91, 2382.13, 567.09, 302.10, 121.40, 105.79, 40.93, 8.09 8 4.48, 13.14, 27.05, 8.52 202.90, 366.27, 730.46, 382.92, 72.15, 34.34, 8.33 9 17.19, 35.38, 27.10 366.27, 826.54, 805.02, 298.29, 174.47, 94.34, 57.93, 39.54

Table 2. Effective rainfall hyetograph (ERH) and direct runoff hydrograph(DRH) at 1-day interval for the selected 9 major historical flood events occurred in the catchment of Hemavathy dam.

slide-30
SLIDE 30

30

Figure 2. Self-similarity properties of the channel network

10

  • 2

10

1

10

2

S/S0 n

10

  • 2

10

5.3

10

5.5

10

5.7

10

5.9

S/S0 T (km)

slide-31
SLIDE 31

31