ESKAY CREEK PROJECT Golde den n Tria iang ngle, e, BC TSX.V: - - PowerPoint PPT Presentation

eskay creek project
SMART_READER_LITE
LIVE PREVIEW

ESKAY CREEK PROJECT Golde den n Tria iang ngle, e, BC TSX.V: - - PowerPoint PPT Presentation

ESKAY CREEK PROJECT Golde den n Tria iang ngle, e, BC TSX.V: SKE/OTCQX: SKREF Nove vembe ber r 2019 FORWARD LOOKING STATEMENTS Certain statements made and information contained herein may constitute forward looking information and


slide-1
SLIDE 1

Nove vembe ber r 2019

TSX.V: SKE/OTCQX: SKREF

ESKAY CREEK PROJECT

Golde den n Tria iang ngle, e, BC

slide-2
SLIDE 2

FORWARD LOOKING STATEMENTS

Certain statements made and information contained herein may constitute “forward looking information” and “forward looking statements” within the meaning of applicable Canadian and United States securities legislation, including, among

  • ther things, information with respect to this presentation. These statements and information are based on facts currently

available to the Company and there is no assurance that actual results will meet management’s expectations. Forward- looking statements and information may be identified by such terms as “anticipates”, “believes”, “targets”, “estimates”, “plans”, “expects”, “may”, “will”, “could” or “would”. Forward-looking statements and information contained herein are based

  • n certain factors and assumptions regarding, among other things, the estimation of mineral resources and reserves, the

realization of resource and reserve estimates, metal prices, taxation, the estimation, timing and amount of future exploration and development, capital and operating costs, the availability of financing, the receipt of regulatory approvals, environmental risks, title disputes and other matters. While the Company considers its assumptions to be reasonable as of the date hereof, forward-looking statements and information are not guarantees of future performance and readers should not place undue importance on such statements as actual events and results may differ materially from those described herein. The Company does not undertake to update any forward-looking statements or information except as may be required by applicable securities laws. The Qualified Person responsible for the technical information in this presentation is Paul Geddes P. Geo., Vice President of Exploration & Resource Development, who has approved the technical information included herein. Any reference to historical estimates and resources should not be relied upon.These are not current and a Q.P. has not done sufficient work to classify these historical estimate and Skeena Resources Limited is not treating the historical estimate as a current resource estimate.

2

slide-3
SLIDE 3

3

Don

  • n Si

Siem emen ens:

  • Mr. Siemens is an independent

financial advisor with over 30 years of experience as a Chartered Accountant. Mr. Siemens currently serves as Director and Audit Committee Chair for Arizona Mining Inc., Atlantic Gold Corp., Eros Resources Corp. and Hansa Resources Ltd.

Bor

  • rden

en R. Put utnam nam III III: Mr. Putnam is a professional

geologist with over 41 years of mineral industry experience, with a focus on exploration and asset evaluations. During the last 15 years Mr. Putnam has worked primarily as an analyst or advisor to several large investment funds in the US.

Is Isac Burstein urstein: Mr. Burstein is the Vice President of

Exploration & Business Development at Hochschild Mining PLC. Mr. Burstein has served Hochschild in various capacities including Vice President

  • f

Business Development, Manager for Project Evaluation, Exploration Manager for Mexico and Exploration Geologist.

Walt Walter er Coles Coles Jr Jr., Presid

esident, ent, CEO & Dir irect ector

  • r: Mr. Coles

has been CEO for several TSXV listed companies. Previously he was an analyst with Cadence Investment Partners and before that with UBS Investment Bank. Mr. Coles holds a B.A. in Economics from the University of Richmond.

Cr Craig ig Pa Parry, y, Chairm

Chairman: Mr. Parry is a geologist and has

served as CEO and President for several Australian and TSXV listed mining companies. He is currently the President & CEO of IsoEnergy Ltd., a co-founder and director of NexGen Energy Ltd and a Senior Advisor and founding- shareholder of EMR Capital.

And ndrew MacRi acRitchie, chie, CP

CPA, A, CA, CA, CF CFO & Co Corporat ate Secr ecreta etary: Mr. MacRitchie is a Chartered Public Accountant

who’s held management roles in several TSXV listed mining companies over his 16-year career. Mr. MacRitchie was previously with PricewaterhouseCoopers in the tax accounting

  • group. He is a graduate of University of British Columbia

Paul ul Geddes es, P. Ge

  • Geo. VP, Explo

lorat ation

  • n & Res

Resour

  • urce

Dev evel elop

  • pment

ent: Mr. Geddes has more than 20 years of

exploration and resource development experience. He was an instrumental member of the Rainy River Resources team prior to the Company’s takeover by New Gold in 2013.

Ke Kell lly Earle, le, B. Sc

  • Sc. Ge

Geol

  • l., CPIR

PIR . VP, Comm

Communi unicat ations ions:

  • Ms. Earle is an Investor Relations professional and a geologist

with 9 years of experience working with junior mining

  • companies. She received her B. Sc. Geol. from the University
  • f British Columbia and her CPIR from the Ivey School of

Business at Western University.

Jus ustin in Him Himmelri elrigh ght, B. Sc

Sc., M. Eng. VP, Sus Sustainab inabilit ility:

Mr. Himmelright has

  • ver

25 years

  • f

experience in environmental management and developing social license for natural resource projects. He is a graduate of University of British Columbia.

MANAGEMENT: DIRECTO TORS:

SKEENA TEAM

slide-4
SLIDE 4

PROPERTY LOCATIONS – BC’S GOLDEN TRIANGLE

4

slide-5
SLIDE 5

INFRASTRUCTURE IN THE GOLDEN TRIANGLE

  • Excellent

access to power & infrastructure:

  • Highway 37 paved north from

Smithers

  • New 287 kV power line
  • Forrest Kerr & McLymont Creek

Power Station within 17 km of Snip

  • Volcano

Creek Power Station within 10 km of Eskay Creek

  • Red Chris mine 25 km east of GJ
  • Opening of year-round ocean port

facilities in Stewart

  • Over

$2 billion invested in infrastructure

5

slide-6
SLIDE 6

6

  • Produced 3.3 mi

mill llion ion ounces

  • unces of
  • f

go gold ld & 160 60 mill million ion ou

  • unc

nces of

  • f silv

lver er at average grades of 45 45 g/ g/t Au Au & 2,22 224 g/t Ag Ag from 1994 to 2008

  • 2.2 million tonnes of ore mined

with cut-off grades of 15 g/t AuEq for mill ore and 30 g/t AuEq for direct shipping ore

  • Historical

database containing 7,881 drill holes totaling 706,904 metres (surface & underground)

  • Highest grade gold producer in the

world when in production

ESKAY CREEK HISTORY

slide-7
SLIDE 7

ESKAY CREEK OPTION TERMS

7

  • Option to Acquire from Barrick

secured in December 2017:

▪ $3.5

million exploration spend commitment

  • ver

3 years (complete)

▪ Purchase price of $10M plus bond

to post (total capped at $17.7M)

▪ Once exercised, Barrick has 12

months to exercise back-in right for 51% by paying Skeena 3x cumulative expenses, refunding $10M purchase price and 51% of bond

slide-8
SLIDE 8

8

PEA HIGHLIGHTS – NOVEMBER 2019

  • High-gra

rade de open-pit pit averaging ng 3.23 3 g/t Au, 78 g/t Ag (4.17 7 g/t AuEq) (dilut uted) d)

  • After-tax

tax NPV5%

5% of C$638M

8M (US$49 491M 1M) ) and 51% IRR at US$1,325/ 325/oz

  • z Au and US$16/o

6/oz z Ag

  • After-tax

tax payback k period d of 1. 1.2 years s

  • Pre-pr

productio duction n capita tal expendi nditures ures (CAPEX) ) of C$303M 3M (US$233M 233M)

  • After-tax

tax NPV:CAPEX EX Ratio of 2.1:1

  • Life of mine (“LOM”) average annual production of 236,000 oz Au,

5,812 12,00 ,000 0 oz Ag ( (306,000 000 oz A AuEq)

  • LOM all-in

n sustai ustaini ning ng costs ts (AISC) of C$983/ 83/oz z (US$75 757/o 7/oz) z) AuEq recovere ered

  • LOM cash

h costs ts of C$949/ 949/oz z (US$73 731/ 1/oz

  • z)

) AuEq recovered red

  • 6,850

0 tonne ne per day (TPD) mill and flot

  • tati

ation n plant t producing ducing saleable le concentra ntrate

1.

Exchange Rate (US$/C$) of 0.77

2.

Cash costs are inclusive of mining costs, processing costs, site G&A, treatment and refining charges and royalties

3.

AISC includes cash costs plus estimated corporate G&A, sustaining capital and closure costs

4.

Gold Equivalent (AuEq) calculated via the formula: Au (g/t) + [Ag (g/t) / 82.8]

306,000 6,000 oz AuE uEq q

Annua ual Producti uction

51%

After-tax tax IRR

C$638M 38M

After-tax tax NPV5%

5%

US$75 757/oz 7/oz

AISC (AuEq)

4.17 g/t AuE uEq

Open-pi pit t Average Grade

slide-9
SLIDE 9

9

Sensit nsitiv ivitie ties s to Commod mmodity ity Prices ces Lower Base Higher Case Case se Case

Gold Price ($US/oz) $1,200 $1,325 325 $1,500 Silver Price ($US/oz) $14 $16 $18 After-Tax NPV (5%)(C$M) $453 $638 $638 $878 After-Tax IRR (%) 40% 51% 63% After-Tax Payback (Years) 1.6 1.2 0.9 Average Annual After-Tax Free Cash Flow (Years 1-9)(C$M) $117 $147 $187

Proje

  • ject

ct Econo nomics ics

After-Tax NPV (5%)(C$M) $638 After-Tax IRR 51% After-Tax Payback Period (Years) 1.2 After-Tax NPV:CAPEX Ratio 2:1:1 Pre-Tax NPV (5%)(C$M) $993 Pre-Tax IRR 63% Pre-Tax Payback Period (Years) 1.1 Pre-Tax NPV:CAPEX Ratio 3:3:1 Average Annual After-Tax Free Cash Flow (Year 1-9 (C$M) $147 LOM After-Tax Free Cash Flow (C$M) $959

ECONOMICS & PRICE SENSITIVITY

slide-10
SLIDE 10

21A 22 22 21B 21C 21C HW HW NEX

2019 MINERAL RESOURCE ESTIMATE

10 10

Grade Contained Ounces Tonnes AuEq Au Ag AuEq Au Ag (000) g/t g/t g/t

  • z (000)
  • z (000)
  • z (000)

Indicated Mineral Resources Pit Constrained 12,711 6.0 4.5 117 2,455 1,818 47,791 Underground 819 8.2 6.4 139 218 169 3,657 Total Indicated 13,530 6.1 4.6 118 2,673 73 1,987 51,448 Inferred Mineral Resources Pit Constrained 13,557 2.8 2.2 42 1,230 984 18,455 Underground 295 8.2 7.1 82 78 68 778 Total Inferred 13,852 2.9 2.3 43 1,308 308 1,052 19,233

21C

Historical Stopes & Development 2019 Resource

  • Pit constrained resources are quoted at a 0.7 g/t AuEQ cut-off. Underground resources are quoted at a 5.0 g/t AuEQ cut-off.
  • AuEQ = Au (g/t) + {Ag (g/t) /75]
  • Mineral resources are not mineral reserves and do not have demonstrated economic viability. There is no certainty that all or any part of the mineral resources

estimated will be converted into mineral reserves.

  • Resources are reported in-situ and undiluted for both pit constrained and underground scenarios and are considered to have reasonable prospects for economic

extraction.

  • In accordance with NI 43-101 recommendations, the number of metric tonnes was rounded to the nearest thousand. Any discrepancies in the totals are due to

rounding effects.

  • Maximum pit depth 236 m, average 180 m
  • Strip ratio of 7.5:1

Pit Constrained Resources Underground Resources

slide-11
SLIDE 11

11 11

MINE DESIGN

  • Two main pits
  • North pit (21

Zones) with 4 phases

  • South pit (22 Zone)
  • Waste dumps
  • One main waste

dump

  • Limited backfilling
  • f pit

Waste Dump South Pit North Pit

slide-12
SLIDE 12

NEAR MINE UPSIDE POTENTIAL

12 12

21A 1A 21B 21C 21C NEX 109 22 22

OPEN

Footwall Feeders Exploration Potential Eskay Creek Depth Extension 22 Feeder Zone Depth Potential

2019 Resources Historical Stopes & Development Drillhole Intersections > 4.0 g/t AuEq >2.0 metres

21E 1E

slide-13
SLIDE 13

NEAR MINE UPSIDE POTENTIAL

13 13 SK-19-053

27.6 .61 g/t Au AuEq 9.40 40 m

SK-19-063:

314.0 .07 g/t Au AuEq 2.2 .21 m

SK-19-052

17.4 .49 g/t Au AuEq 7.5 .54 m

slide-14
SLIDE 14

0.0 1.0 2.0 3.0 4.0 5.0 6.0 0.0 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0

Averag age e Grades es (g/t) ) of Open-Pit Pit Developm elopment ent Projects jects World ldwide wide

OPEN-PIT COMPARISONS

14 14

Average ge Grades (g/t) ) of Open-Pi Pit t Develo lopmen ent Projec ects ts in North America a and Austr trali lia

  • Avg. Grade (g/t) – Reserves & Resources

North American and Australian Average Open-Pit Grade

Eska kay y Creek ek 4.34 g/t AuEq Open-Pit Pit

Worldwide Average Open-Pit Grade 1.50 g/t

Source: S&P Capital IQ

Eskay Creek ek 4.34 4 g/t AuEq Open en-Pi Pit

  • Avg. Grade (g/t) – Reserves & Resources

1.46 g/t

slide-15
SLIDE 15

MARKET CAPITALIZATION ($M CAD)

15 15

$1,683 $1,047 $825 $781 $673 $500 $403 $300 $277 $222 $213 $201 $112 $65 $65

Market et Cap ($M CAD)

Source: Agentis Capital, Oct 29, 2019

P/NAV

1.0x 0.9x 0.9x 0.8x 0.7x 0.6x 0.6x 0.6x 0.6x 0.6x 0.6x 0.5x 0.3x

  • SKE 0.1x

x NAV

P/NA NAV 0.1x

slide-16
SLIDE 16

$970 $684 $389 $360 $324 $310 $289 $233 33 $194 $161 $123 $113 $101 $74

INITIAL CAPEX (USD)

16 16

SKE $233 (USD SD $M)

LOM ANNUAL PRODUCTION

USD $M

337 330 306 6 259 218 198 190 124 120 116 98 97 95 79

LOM (koz AuEq Eq)

SKE +306 koz AuEq

Source: Argentis Capital, Oct.29, 2019

slide-17
SLIDE 17

AISC CURVE BENCHMARK

17 17

Eskay Creek LOM AISC

  • f US$757/oz (AuEq)

Produc ucti tion

  • n (%)

25 25 50 50 75 75 100 All All-In In-Sus Sustainin ining g Cost t ($/o /oz) 500 1,0 ,000 1,5 ,500 2,0 ,000 2,5 ,500 3,0 ,000

Source: S&P Global Market Intelligence; Based on reported/actual data where available

slide-18
SLIDE 18

SNIP GOLD PROJECT

  • 100% owned (acquired from

Barrick July 2017)

  • Hochschild Mining has option

to acquire 60%

  • Produced 1.

1.1 1 million ion ounce ces s of gold d at average age grade de of 27.5 .5 g/t from 1991 to 1999

  • 280,000 m of historical

surface & underground drilling

  • 8,435 m underground

development

  • Exploration & 200 Footwall

delineation drilling planned for H2 2019

18 18

Un Under erground d drill illin ing at Snip hole le UG17-001

slide-19
SLIDE 19

19 19

SNIP 200 FOOTWALL - SECTION 4660E

SKE 2016 Drillhole

16.2 .24 g/t Au Au 13.5 .50 m

slide-20
SLIDE 20
  • Skeena leveraged strong First Nations & government relationships to create the British

Columbia Regional Mining Alliance (BCRMA)

  • The BCRMA is a partnership between the Tahltan Central Government, the Nisga’a

Lisims Government, industry, AME BC & the provincial government to promote mining investment in the Golden Triangle of northwest BC

  • Industry partners selected to join the Alliance must focus on socially & environmentally

responsible resource development rooted in local partnerships

20 20

slide-21
SLIDE 21

SKEENA CAPITAL STRUCTURE

21 21

Capital al Struc ucture ture

Current Shares Outstanding 115,289,676 Market Capitalization (CAD$0.57) $65.7 Million 52 Week High $0.58 52 Week Low $0.27 Warrants (exp. March 2020 – June 2020, $0.90 – $1.00) 9,962,509 Options (exp. November 2019 – August 2024, $0.41 – $1.50) 11,502,000 Shares Fully Diluted 136,754,185 Strategic Ownership Hochschild Mining plc 6.5%

All figures as of Nov 6, 2019

  • Nov. 6, 2018 – Nov 6, 2019

Share Price - TSX.V: SKE

slide-22
SLIDE 22

22 22

Kelly Earle, Vice President Communications

info@skeenaresources.com +1 604 684 8725 Suite # 650 - 1021 West Hastings Street Vancouver, BC V6E 0C3 Canada

www.sk skeena enare resou sources es.c .com

  • m

TSX.V: SKE / OTCQX: SKREF / FRA: RXFB

slide-23
SLIDE 23

APPENDIX ESKAY CREEK PEA

23 23

slide-24
SLIDE 24

24 24

Assumptions

Gold Price (US$) $1,32 325 Silver Price (US$) $16 Exchange Rate (US$/C$) 0.77 Discount Rate 5% 5% Royalties 1% 1%

Processing

Processing Throughout (TPD) 6,850 50 Average Diluted Gold Grade (g/t) 3.23 Average Diluted Silver Grade (g/t) 78 78 Average Diluted Gold Equivalent Grade (g/t) 4.1 .17

Mining

Mine Life (Years) 8.6 Strip Ratio (Waste: Mineralization) 7.2 .2:1 :1 Total Tonnage Mined (kt) 175,2 ,270 Total Mineralized Material Mined (kt) 21,3 ,307

Production

Gold d Recover ery 91.1 .1% Silv lver er Recover ery 92.4 .4% LOM Gold d Product uctio ion n (koz) 2,022 LOM Silver er Product uction ion (koz) 49,8 ,872 LOM Gold d Equiv ivalen lent t Product uction ion (koz) 2,624 LOM Aver verage age Annu nual l Gold ld Product uction ion (koz) 236 LOM Aver verage age Annu nual l Silv lver er Product uction ion (koz) 5,812 LOM Aver verage age Annu nual l Gold ld Equiv ivalent alent Product uction ion (koz) 306

Contained Metals

Contained ained Gold d Ounces es (koz) 2,2 ,212 Contained ained Silver er Ounces es (koz) 53,4 ,404 Contained ained AuEq Eq Ounces es (koz) 2,857

Capital Expenditures

Pre-Production Capital Expenditures (C$M) $303 Sustaining Capital Expenditures (C$M) $27 Reclamation Cost (C$M) $52

Operating Costs

Mining Cost (C$/t Mined) $3.4 .44 Mining Cost (C$/t Milled) $26.3 .32 Processing Cost (C$/t Milled) $21.6 .64 G&A Cost (C$/t Milled) $6.0 .06 Total Operating Cost (C$/t Milled) $54.0 .03

Cash Costs and AISC

LOM Cash Cost (US$/oz

  • z Au) Net of Silv

lver er By By-Pr Produc duct $582 LOM Cash Cost (US$/ $/oz

  • z AuEq

Eq) Co-Pr Produ

  • duct

$73 731 LOM AISC C (US$ S$/oz

  • z Au) Net

t of Silv lver er By- Product uct $615 LOM AISC C (US$ S$/oz

  • z AuEq

Eq) Co-Produc duct $757

APPENDIX - DETAILED PARAMETERS & OUTPUTS

slide-25
SLIDE 25

25 25

APPENDIX - CAPITAL COSTS (C$M)

Cont

  • nting

ngenc ency Init itial al Sustaini staining LOM Tot

  • tal

Mine

Pre-Stripping $62 $62 Mining Equipment $14 $6 $20 Mine Capital $7 $3 $9 Sub-Total Mine $4 $83 $9 $91

Processing

Bulk Earthworks $7 $7 Processing $74 $7 $81 Reagents & Plant Services $7 $1 $8 Tailings & Water Treatment $19 $2 $21 Onsite Infrastructure $22 $2 $23 Sub-Total Processing $21 $129 $12 $141

Infrastructure

Power $13 $13 TSF, Water Supply & Treatment $2 $4 $6 Sub-Total Infrastructure $5 $15 $4 $19 Total Directs $226 $24 $250 Indirects $7 $27 $27 Total Directs + Indirects $253 $24 $277

Owner’s Costs

$4 $10 $10 Total excluding contingency $263 $24 $287

Project Contingency

$40 $3 $43 Sub-total including contingency $303 $27 $330 Closure $52 $52

Tot

  • tal

$303 $79 $382

slide-26
SLIDE 26

26 26

APPENDIX - FLOWSHEET & MASS BALANCE