erie attica
play

Erie Attica Bridge and Trail Project Public Informational Meeting - PowerPoint PPT Presentation

Erie Attica Bridge and Trail Project Public Informational Meeting Monday, January 23, 2012 Village of Avon Introductions Village of Avon NYS Office of Parks, Recreation & Historic Preservation (NYSOPRHP) NYS Department of


  1. Erie – Attica Bridge and Trail Project Public Informational Meeting Monday, January 23, 2012 Village of Avon

  2. Introductions Village of Avon NYS Office of Parks, Recreation & Historic Preservation (NYSOPRHP) NYS Department of Transportation Project Advisory Committee Consultant – Fisher Associates

  3. Public Informational Meeting Goals Present the Trail and Bridge Project Scope Obtain Public Input – Objectives of the Project – Design Alternatives – Alignment Alternatives Input received will be considered and will serve to revise the Design Report

  4. Project Objectives Provide a recreational trail link between the Genesee Valley Greenway & Village of Avon Preserve the abandoned railroad corridor for public transportation Utilize the historic RR bridge over the Genesee River as part of the trail system

  5. Project Objectives Provide an ADA compliant trail surface Construct a new span over Farmers Road Provide parking and trailhead access for trail users. Construct all trail components and amenities in the most cost-effective manner

  6. Limits of Project Horseshoe Boulevard Genesee Valley Greenway Western limit – Genesee Valley Greenway Eastern limit – Horseshoe Boulevard

  7. Trail Users Railroad Corridor Pedestrians Bicycles Horses Snowmobiles Livingston Industrial Complex Pedestrians Bicycles

  8. Project Scope Former railroad Railroad Corridor corridor begins at the Greenway Provide 10’ wide trail with 2’ shoulders Approximate length of 5,600’ Surface needs to be ADA compliant – firm, stable, slip resistant

  9. Project Scope Ramp up from Genesee Valley Greenway Begin 10’ Wide Trail

  10. Project Scope Continue 10’ Wide Trail

  11. Project Scope The trail will be routed around abutments of three former bridges

  12. Project Scope A new culvert will be installed for the stream crossing

  13. Project Scope Continue 10’ Wide Trail

  14. Project Scope Existing Truss Bridge The existing railroad truss bridge over the Genesee River is eligible for listing on the National Register. The span is approx. 220’ including a short approach span at the west end.

  15. Project Scope A new timber Existing Truss Bridge deck and rail are proposed. The timber deck will be 10’ or 11’ wide depending on project cost.

  16. Existing Truss Bridge

  17. Existing Truss Bridge

  18. Project Scope New Bridge over The new bridge Farmers Road over Farmers Road is a span of approx. 35’.

  19. Project Scope New Bridge over A new timber Farmers Road deck and rail are proposed. The timber deck will be 10’ or 11’ wide depending on project cost.

  20. Farmers road Bridge

  21. Farmers road Bridge

  22. Project Scope Trail from Bridges The trail ramps down east of Farmers Road bridge to Trail from the parking area Bridges

  23. Project Scope Parking Area The parking area will serve vehicles and horse trailers. Surface will be Trail from Bridges gravel or asphalt depending on project costs

  24. Project Scope Two options for trail alignment connecting to Horseshoe Boulevard in the Livingston Industrial Complex North of the Pond and South of the Pond

  25. Project Scope Trail North of Pond The trail begins at the parking area and travels along the northerly edge of the pond and is about 1,100’ in length .

  26. Project Scope The trail will be 10’ Trail North of Pond wide with 2’ shoulders. The trail surface will be either asphalt or stone dust depending on project cost.

  27. Project Scope Trail South of Pond The trail begins at the parking area and travels along the northerly edge of the pond and is about 1,400 ’ in length . Spillway

  28. Project Scope The trail will be 8’ Trail South of Pond wide with 2’ shoulders due to constraints. The trail surface will be either asphalt or stone dust. The trail will span the pond spillway with a system of drainage pipes.

  29. Project Cost Bridge Estimate → $ 450,000 Parking Lot Estimate → $ 112,000 Trail Estimate → $ 400,000 $ 962,000

  30. Schedule Project Initiation → August 2011 Submit Draft Design Report → December 2011 Public Info Meeting No. 1 → January 23, 2012 Revise Draft Design Report for Public Comment → February 2012 Final Design Report → March 2012 Design Approval → April 2012 Final Design → April 2012-August 2012 Bid & Award Project→ October 2012 Construction Complete → October 2013

  31. Questions/Comments Comment Sheet Contact Fisher Associates – Roseann Schmid, Project Manager – rschmid@fisherassoc.com – (585) 334-1310 ext. 295 – Carl Ast, Assistant Project Manager – cast@fisherassoc.com – (585) 334-1310 ext. 259 Contact Village: Chris Quinlan, Village Treasurer – quinlan@frontiernet.net – (585) 226-8118

  32. End Of Presentation

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend