Environmental Impact Assessment (EIA) Crane Mountain Landfill Clay - - PowerPoint PPT Presentation

environmental impact assessment eia
SMART_READER_LITE
LIVE PREVIEW

Environmental Impact Assessment (EIA) Crane Mountain Landfill Clay - - PowerPoint PPT Presentation

Environmental Impact Assessment (EIA) Crane Mountain Landfill Clay and Aggregate Quarry Saint John, New Brunswick EIA Crane Mountain Clay and Aggregate Quarry Rationale / Need for the Undertaking; Engineering Assessment;


slide-1
SLIDE 1

Environmental Impact Assessment (EIA)

Crane Mountain Landfill Clay and Aggregate Quarry Saint John, New Brunswick

slide-2
SLIDE 2

EIA – Crane Mountain Clay and Aggregate Quarry

 Rationale / Need for the Undertaking;  Engineering Assessment;  Environmental Impact Assessment (EIA) Overview;  EIA – Valued Environmental Components;  Timeline + Next Steps; and  Questions.

slide-3
SLIDE 3

Need / Rationale For the Undertaking

 Secure and viable source of clayey material (liner) and aggregate (rock) until end of projected landfill life;  Nine landfill cells scheduled to be built between 2020 and 2048;  Reduction of sourcing uncertainty;  Reduction in construction costs; and  Advantages of a clay liner.

LANDFILL

slide-4
SLIDE 4

Site Location Plan

slide-5
SLIDE 5

Engineering Assessments

 Potential clay source on this property was known historically;  In Summer 2018, the potential clay source was assessed for:

  • Quality (properties such as hydraulic conductivity, % clay, % moisture, plasticity, etc.);
  • All lab tests show the material meets or exceeds required properties;
  • Quantity - sufficient amount to complete all liners for the projected landfill life;

 Bedrock on the site was also assessed (quality and quantity);

  • Bedrock can be processed and used for many materials in landfill construction:
  • i.e., gas venting layer, berm material, sub-base, road materials, etc.; and
  • Readily available on the site via existing access road and quarry faces.
slide-6
SLIDE 6

Environmental Impact Assessment (EIA) Overview

Regulatory Requirements

The proposed project is specified as an undertaking outlined in Schedule A of the New Brunswick Environmental Impact Assessment Regulation 87-83 under paragraph: (v): all enterprises, activities, projects, structure, works or programs affecting two hectares of more of bog, marsh, swamp or other wetland.

slide-7
SLIDE 7

Environmental Impact Assessment (EIA) Overview

EIA Methodology

  • 1. Valued Environmental Components (VEC);
  • 2. Boundaries + Methodology;
  • 3. Existing Environment;
  • 4. Potential Project Effects;
  • 5. Mitigation Measures; and
  • 6. Significant Residual Effects.
slide-8
SLIDE 8

EIA – Valued Environmental Components (VEC)

 Atmospheric Environment;  Groundwater;  Aquatic Environment;  Wildlife and Wildlife Habitat;  Wetlands and Vegetation;  Archeological and Heritage Areas;  Land Use; and  Effects of the Environment on the Project.

slide-9
SLIDE 9

Next Steps + Timeline

Work Component Month of Completion DRAFT EIA Report for FRSC Review December, 2018 Submission of EIA Report to NBDELG (EIA Registration) December, 2018 or January, 2019 Public Involvement January - July, 2019 GEMTEC Receipt of Technical Review Committee (TRC) March, 2019 GEMTEC Response to TRC Questions April, 2019 Required Additional Assessments (Rare Plant, Breeding Bird, Archeological) May - June, 2019 Round 2 TRC Review July, 2019 GEMTEC Response to TRC Questions September, 2019 Final Determination November, 2019

slide-10
SLIDE 10

QUESTIONS?

Marco Sivitilli, P.Eng. Jennifer Hachey, B.Sc.