energy audit methodology
play

Energy Audit Methodology of Electrical Systems Programme on - PowerPoint PPT Presentation

Energy Audit Methodology of Electrical Systems Programme on Energy Conservation in Foundry Industry E Nand Gopal The Energy and Resources Institute 11 th August 2014 Contents Energy monitoring and auditing Introduction to electrical systems


  1. Energy Audit Methodology of Electrical Systems Programme on Energy Conservation in Foundry Industry E Nand Gopal The Energy and Resources Institute 11 th August 2014

  2. Contents Energy monitoring and auditing Introduction to electrical systems Electricity billing Power factor improvement Maximum demand control Electric motors Air compressors Pumps Lighting system Instruments for energy audit 2

  3. Energy monitoring and auditing Measure Data Result Action Analyze Information 3

  4. Energy monitoring and auditing Energy management (EM) Judicious & effective use of Strategy of adjustment & energy to maximise profit optimising energy usage Energy audit (EA) Systematic approach for Quantifies energy usage at decision making for EM user divisions 4

  5. Need for energy audit Three major expenses consist of energy, labour and material The energy cost reduction Identify energy conservation technologies and retrofits It translates conservation ideas into realities 5

  6. Classification of energy audit Preliminary audit • Establish energy consumption • Estimate specific energy consumption of plant • Identify in-depth study areas Detailed audit • Data collection • Measurement and trials • Post audit analysis • Identification of Energy Conservation Measures (ECMs) • Techno-economic evaluation of ECMS • Implementation of selected ECMs 6

  7. Instruments used for detailed audit Instrument Application Measurement Power analyser Electrical Parameters Induction furnace, Air Harmonics analysis Compressor, Pumps, Motors, Lighting, Other electrical equipment Ultrasonic flow meter Water Velocity, Volume Pumping system Flue gas analyser Flue gas O 2 ,CO,CO 2 and Heat treatment furnace, Diesel Temperature fired melting furnace, Cupola Hygrometer Ambient Temperature & RH Digital temperature indicator Temperature Thermal imager Surface temperature and image Core shooter, Furnace temperature, Heat treatment Lux meter Lumen level Below lighting fixture Infrared thermometer Surface temperature Walls of furnace and heat treatment Anemometer Air velocity Air compressor Thermocouple High temperature Furnace 7

  8. Introduction to electrical systems Electrical systems Equipment • Electricity Billing • Electric motors • Maximum demand • Air compressors Control • Lighting systems • Power Factor Improvement 8

  9. Electricity billing Contract demand (kVA) Recorded demand (kVA) Billed demand (kVA) Billed power factor (pf) Electrical units consumption (kWh) Time of day details (TOD) Rebate / Penalty (+/-) Fuel escalation charge (Rs or %) Electricity duty, tax, surcharge (%) Total monthly amount (Rs./month) 9

  10. CD= 580 kVA BD= 451 kVA Previous hughest Electricity consumption 10

  11. Billed Demand Electricity charge 444 kVA Billed pf 1.0 TOD pf penal/ incentive Last six months Bill amount 11

  12. Maximum demand The monthly MD will be the highest among the demand values recorded every half hour over the month The industry has to pay for the highest MD registered even if it occurred for just one recording cycle Figure 1.4 Demand Curve Demand Curve duration

  13. Maximum demand As example, in an industry, if the drawl over a recording cycle of 30 minutes is : 3500 kVA for 4 minutes; 4600 kVA for 12 minutes; 3100 kVA for 6 minutes; 3800 kVA for 8 minutes; The MD recorder will be computing MD as: (3500x4) +(4600 x 12) + (3100 x 6) + (3800 x 8) 30 = 3940 kVA (average is only 3750)

  14. Maximum demand

  15. Methods of MD control Manual type Load scheduling Demand monitoring activity Even alarm can be set-up Automatic demand controllers • Large plant • Load characteristics Energy Management system • Acts as per demand + programmable • Monitoring Capability

  16. Power factor What causes Low Power Factor? low power factors would occur when kVAr is large. What causes a large kVAr in a system? The answer is… “INDUCTIVE LOADS”. Inductive loads include: – Transformers, Induction motors – Induction generators (wind mill generators) – High intensity discharge (HID) lighting These inductive loads constitute a major portion of the power consumed in industrial complexes.

  17. Power factor improvement 1. Reactive component of the network is reduced and so also the total current in the system from the source end. I 2 R power losses are reduced in the system because of 2. reduction in current. % power loss reduction = 100 x{1- (PF old/PF New) 2 } 3. Voltage level at the load end is increased. % voltage rise = kVAr of capacitor x % imp. of transformer kVA of transformer

  18. Location of capacitor It could be • At HT bus / transformer • LT bus of transformer • Main sub-plant buses • Load points Hence • Identify the sources of low pf loads in plant • Locate close to end equipment to reduce I 2 R loss • Release of system capacity(kVA) happens if reactive current is reduced.

  19. Location of capacitor Incoming supply C 4 Utilisation or distribution bus C 1 M C 3 C 2 C 2

  20. Losses in Electrical Distribution Equipment S.No Equipment % Energy Loss at Full Load Variations Min Max 1. Outdoor circuit breaker (15 to 230 KV) 0.002 0.015 2. Generators 0.019 3.5 3. Medium voltage switchgears (5 - 15 KV) 0.005 0.02 4. Current limiting reactors 0.09 0.30 5. Transformers 0.40 1.90 6. Load break switches 0.003 0.025 7. Medium voltage starters 0.02 0.15 8. Bus ways less than 430 V 0.05 0.50 9. Low voltage switchgear 0.13 0.34 10. Motor control centers 0.01 0.40 11. Cables 1.00 4.00 12. Large rectifiers 3.0 9.0 13. Static variable speed drives 6.0 15.0 14. Capacitors (Watts / kVAr) 0.50 6.0

  21. Location of capacitor It could be • At HT bus / transformer • LT bus of transformer • Main sub-plant buses • Load points Hence • Identify the sources of low pf loads in plant • Locate close to end equipment to reduce I 2 R loss • Release of system capacity(kVA) happens if reactive current is reduced.

  22. MSME Foundry Lighting, 1.1% Misc, 1.7% Sand plant and finishing, 9.9% Air compressor, 6.3% Cooling water circuit, 3.2% Induction furnace, 77.7%

  23. Pump and pumping system Power consumption (kW) • Usually lower than rated power • Near to or higher than rated if re-winded Flow rate (cu.m/hour) • Most cases it was lower than design, few cases < 60% of design flow rate Head (m) • Most cases pressure gauges found not functioning Optimizing piping design • Water velocity ~ 1.8 – 2.0 m/s 23

  24. Air compressor Performance evaluation Leakage test No load i.e. no usage of compressed Tank fill method air Switch on compressor Empty receiver Say setting is 6.0 bar to 7.0 bar Stop all usage of air, close receiver output valve Ton is time taken to compress air from 6.0 to 7.0 bar Start compressor, monitor time taken Toff is time taken for pressure to drop to fill the tank, in seconds back to 6.0 bar FAD (m3/min) = (Tank volume + Pipe Leakage % = Ton / (Ton + Toff) * 100 volume)/ Time taken in minutes 24

  25. Air compressor Air leakages For example • Leakage of compressed air: • 300cfm installed, generated 10 – 50 % FAD 264cfm, leakages 23 % • Energy Saving Potential: • 60 cfm wasted 5 – 35 % • Reducing leakages to 5 % = Variable Frequency Drive 14.0 % of electricity • Loading of air compressor: consumption by compressor 30 – 80 % • Investment : 1.0 lakh INR • Energy Saving up to 35 % possible • Saving potential : 3.2 lakh Optimum pressure setting INR • Simple Payback : 4.0 • One bar reduction months • Energy Saving 6 – 10 % 25

  26. Air compressor  Variable Frequency Drive 26

  27. Electric motors Power consumption (kW) For example • Usually lower than rated power • Shot blast turbine motor • Near to or higher than rated if re- • Name plate efficiency = 84% winded • Operating efficiency = 66% Loading (%) • Replace it with higher • Once motor fails, it is replace by efficiency motor same/higher hp motor • Saving potential: 24% • Leads to under loading • Investment : 0.26 lakh INR • Saving potential: 0.54 lakh INR Maintenance of motor • Simple Payback: 5.8 months • Keeping it dust free • Periodic lubrication, gear-box alignment 27

  28. Lighting Power consumption (W) For Example Lux level (lm/m 2 ) • Existing lighting fixtures • 15 T12 FTL of 40W Luminous efficacy (lm/W) • 12 MVL of 250W • Proposed lighting fixtures For example: • 15 T5 FTL of 28W • T12 FTL to T5 FTL • 12 MH of 150W • Saving potential 22W/fixture • Investment : 0.61 lakh INR • Higher luminous efficacy • Saving potential: 0.58 lakh INR • MVL to Metal Halide • Saving potential 100 – 200W/fixture • Simple Payback: 3.2 months • Higher luminous efficacy 28

  29. Lighting 120 25000 Liminous Efficacy (lm/W) 100 20000 Life (hrs) 20000 Liminous efficacy 80 15000 Life 60 10000 40 5000 20 6000 5000 5000 0 0 T12 T5 MVL MH 29

  30. Be the change you want to see in the world E Nand Gopal +91 99715 17752 e.nandgopal@yahoo.com enand.gopal@teri.res.in

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend