Emily Emily Emily Couric Emily Couric Couric Clinical Couric - - PowerPoint PPT Presentation
Emily Emily Emily Couric Emily Couric Couric Clinical Couric - - PowerPoint PPT Presentation
Emily Emily Emily Couric Emily Couric Couric Clinical Couric Clinical Clinical Clinical Brittany Muth Brittany Muth Cancer Center Cancer Center Construction Management Construction Management University of Virginia University of
Outline Outline
Background Background Background Background Solar Panels Solar Panels
- Electrical Breadth
Electrical Breadth BIM BIM for Façade for Façade Prefabrication Prefabrication
- Mechanical Breadth
Mechanical Breadth Conclusions Conclusions Questions Questions
Introduction Background Solar Panels
- Electrical
Breadth
Building Statistics: Building Statistics:
- 154,000 SF
154,000 SF
BIM for Façade Prefabrication
- Mechanical
Breadth Conclusions Questions
- 5 floors + penthouse
5 floors + penthouse
- $74 million
$74 million
- Outpatient diagnostic
Outpatient diagnostic and treatment center and treatment center A 2008 A 2008 D 2010 D 2010
- Apr. 2008
- Apr. 2008 – Dec. 2010
- Dec. 2010
- Design
Design-
- Bid
Bid-
- Build
Build
Introduction Background Solar Panels
- Electrical
Breadth
Architecture: Architecture:
- Consolidate existing services into
Consolidate existing services into
BIM for Façade Prefabrication
- Mechanical
Breadth Conclusions Questions
- ne building
- ne building
- Offices, exam rooms, linear
Offices, exam rooms, linear accelerators, radiation/oncology accelerators, radiation/oncology
- 4
4th
th floor expansion
floor expansion p
- Entrance Lobby
Entrance Lobby
Introduction Background Solar Panels
- Electrical
Breadth
Mechanical System: Mechanical System:
- All air, local reheat in
All air, local reheat in Electrical System: Electrical System:
- 23 local
23 local
BIM for Façade Prefabrication
- Mechanical
Breadth Conclusions Questions
each room each room
- 4 main AHU’s
4 main AHU’s
- 288 air terminal units
288 air terminal units transformers transformers
- 83 panel boards
83 panel boards
- 65 different light
65 different light fixtures, fixtures, fixtures, fixtures, fluorescent fluorescent
Introduction Background Solar Panels
- Electrical
Breadth
Building Envelope: Building Envelope:
- Brick veneer, stone, and curtain wall
Brick veneer, stone, and curtain wall EPDM i l EPDM i l l f b / l f b /
BIM for Façade Prefabrication
- Mechanical
Breadth Conclusions Questions
- EPDM single
EPDM single-
- ply roof membrane w/
ply roof membrane w/ white acrylic coating white acrylic coating
- Roof garden
Roof garden
Introduction Background Solar Panels
- Electrical
Breadth
Possible Limitations: Possible Limitations: BIM for Façade Construction BIM for Façade Construction
BIM for Façade Prefabrication
- Mechanical
Breadth Conclusions Questions
- Learning curve
Learning curve
- Technology
Technology
- Experience
Experience Possible Benefits: Possible Benefits:
- Quicker construction
Quicker construction
- Better coordination
Better coordination
- Shorter schedule
Shorter schedule
Introduction Background Solar Panels
- Electrical
Breadth
Survey Results: Survey Results:
- Increase
Increase BIM for Façade Construction BIM for Façade Construction
60 60 70 70 80 80
BIM for Façade Prefabrication
- Mechanical
Breadth Conclusions Questions
Constructability? Constructability?
- Yes
Yes
- Structural analysis
Structural analysis
- Coordination
Coordination
20 20 30 30 40 40 50 50 60 60
- Details
Details
10 10 Strongly Strongly Disagree Disagree Disagree Disagree Neutral Neutral Agree Agree Strongly Strongly Agree Agree
Introduction Background Solar Panels
- Electrical
Breadth
Survey Results: Survey Results:
- Increase Productivity?
Increase Productivity? BIM for Façade Construction BIM for Façade Construction
60 60 70 70
BIM for Façade Prefabrication
- Mechanical
Breadth Conclusions Questions
- Yes
Yes
- Communication
Communication
- Plan execution
Plan execution
10 10 20 20 30 30 40 40 50 50 10 10 Strongly Strongly Disagree Disagree Disagree Disagree Neutral Neutral Agree Agree Strongly Strongly Agree Agree
Introduction Background Solar Panels
- Electrical
Breadth
Survey Results: Survey Results:
- Beneficial for Façade
Beneficial for Façade BIM for Façade Construction BIM for Façade Construction
60 60 70 70 80 80
BIM for Façade Prefabrication
- Mechanical
Breadth Conclusions Questions
Analysis/ Analysis/ Coordination? Coordination?
- Yes
Yes
- Quantifying materials
Quantifying materials
20 20 30 30 40 40 50 50 60 60
Q y g Q y g
- Understanding water
Understanding water infiltration and infiltration and energy loss energy loss
10 10 Strongly Strongly Disagree Disagree Disagree Disagree Neutral Neutral Agree Agree Strongly Strongly Agree Agree
Introduction Background Solar Panels
- Electrical
Breadth
Survey Results: Survey Results:
- Learning curve =
Learning curve = BIM for Façade Construction BIM for Façade Construction
50 50 60 60
BIM for Façade Prefabrication
- Mechanical
Breadth Conclusions Questions
negative affects? negative affects?
- No
No
- Find right people
Find right people
10 10 20 20 30 30 40 40 10 10 Strongly Strongly Disagree Disagree Disagree Disagree Neutral Neutral Agree Agree Strongly Strongly Agree Agree
Introduction Background Solar Panels
- Electrical
Breadth
Survey Results: Survey Results:
- Reduce cost of façade
Reduce cost of façade BIM for Façade Construction BIM for Façade Construction
50 50 60 60
BIM for Façade Prefabrication
- Mechanical
Breadth Conclusions Questions
construction? construction?
- Neutral
Neutral
- Saves on errors
Saves on errors
- Increase in
Increase in
10 10 20 20 30 30 40 40
productivity productivity
10 10 Strongly Strongly Disagree Disagree Disagree Disagree Neutral Neutral Agree Agree Strongly Strongly Agree Agree
Introduction Background Solar Panels
- Electrical
Breadth
Survey Results: Survey Results: BIM for Façade Construction BIM for Façade Construction
BIM for Façade Prefabrication
- Mechanical
Breadth Conclusions Questions
Survey Results: Survey Results:
- Most difficult parts:
Most difficult parts:
- Level of details
Level of details
- Training
Training Subcontractors Subcontractors
- Most beneficial parts:
Most beneficial parts:
- Increase field productivity
Increase field productivity
- Managing costs
Managing costs
- Coordination
Coordination
- Subcontractors
Subcontractors
- Coordination
Coordination
Introduction Background Solar Panels
- Electrical
Breadth
Conclusion: Conclusion: BIM for Façade Construction BIM for Façade Construction
BIM for Façade Prefabrication
- Mechanical
Breadth Conclusions Questions
- Use for mock ups
Use for mock ups
- Not for complete model
Not for complete model
Introduction Background Solar Panels
- Electrical
Breadth
Prefabrication of Brick Facade Prefabrication of Brick Facade Advantages: Advantages: Disadvantages: Disadvantages:
BIM for Façade Prefabrication
- Mechanical
Breadth Conclusions Questions
- Shorter schedule
Shorter schedule
- Better quality
Better quality
- Possibly cheaper
Possibly cheaper
- constructability
constructability
- Possibly more expensive
Possibly more expensive
- Storage
Storage y
Introduction Background Solar Panels
- Electrical
Breadth
Prefabrication of Brick Facade Prefabrication of Brick Facade Brick Facade: Brick Facade:
BIM for Façade Prefabrication
- Mechanical
Breadth Conclusions Questions
- Area = 33,472 SF
Area = 33,472 SF
- Schedule = 244 days
Schedule = 244 days
- Original cost = $1.8
Original cost = $1.8 million million
Introduction Background Solar Panels
- Electrical
Breadth
Materials: Materials:
BIM for Façade Prefabrication
- Mechanical
Breadth Conclusions Questions
- 8” CMU Backup
8” CMU Backup
- 2” Insulation
2” Insulation
- Mortar Net
Mortar Net
- Weeps
Weeps p
- Brick Veneer
Brick Veneer
Introduction Background Solar Panels
- Electrical
Breadth
Materials Excluded with Materials Excluded with Prefab: Prefab:
BIM for Façade Prefabrication
- Mechanical
Breadth Conclusions Questions
- Mortar Net
Mortar Net
- Weeps
Weeps
- Air Cavity
Air Cavity
- Steel Plates
Steel Plates
- CMU Backup
CMU Backup
Introduction Background Solar Panels
- Electrical
Breadth
Thin Brick Prefab System: Thin Brick Prefab System:
- Cold formed structural stud:
Cold formed structural stud: 6" 16 6" 16 ga.
- ga. 1
1-
- 5/8" @ 16"
5/8" @ 16" o.c
- .c.
.
- 5/8
5/8" sheathing sheathing
BIM for Façade Prefabrication
- Mechanical
Breadth Conclusions Questions
- 5/8
5/8 sheathing sheathing
- WP membrane
WP membrane
- Z
Z
- 5/8
5/8" " sheathing sheathing
- Lath
Lath Lath Lath
- Scratch coat
Scratch coat
- Laticrete
Laticrete
- Thin
Thin brick brick
Introduction Background Solar Panels
- Electrical
Breadth
Prefabrication of Brick Facade Prefabrication of Brick Facade New Advantages: New Advantages: Sh t h d l Sh t h d l New Disadvantages: New Disadvantages:
BIM for Façade Prefabrication
- Mechanical
Breadth Conclusions Questions
- Shorter schedule
Shorter schedule
- Better quality
Better quality
- No air cavity, no leaks
No air cavity, no leaks
- Constructability
Constructability
- More expensive
More expensive
Introduction Background Solar Panels
- Electrical
Breadth
Prefabrication of Brick Facade Prefabrication of Brick Facade Panel Calculations: Panel Calculations: ’ ’ ’ ’ S
30’ 7’
BIM for Façade Prefabrication
- Mechanical
Breadth Conclusions Questions
- Panel Area = 30’ x 7’
Panel Area = 30’ x 7’ = 210 SF = 210 SF
- # of panels = 33,472 SF / 210 SF=
# of panels = 33,472 SF / 210 SF= 159 panels 159 panels
30 7
- Days = 159 panels / 8 panels per
Days = 159 panels / 8 panels per day = 20 days day = 20 days
Introduction Background Solar Panels
- Electrical
Breadth
Prefabrication of Brick Facade Prefabrication of Brick Facade Comparison: Comparison:
BIM for Façade Prefabrication
- Mechanical
Breadth Conclusions Questions
- Original:
Original:
- Cost = $1.8 million
Cost = $1.8 million
- Schedule = 244 days
Schedule = 244 days
- Prefabricated:
Prefabricated:
- Cost = $3.2 million
Cost = $3.2 million
- Schedule = 178 days
Schedule = 178 days
Introduction Background Solar Panels
- Electrical
Breadth
Prefabrication of Brick Facade Prefabrication of Brick Facade Conclusion: Conclusion:
- Too expensive
Too expensive
BIM for Façade Prefabrication
- Mechanical
Breadth Conclusions Questions
- Too expensive
Too expensive
- Not a fast track schedule
Not a fast track schedule
Introduction Background Solar Panels
- Electrical
Breadth
Mechanical Breadth Mechanical Breadth Original Wall Properties: Original Wall Properties:
- R value = 10 63
value = 10 63 Prefab Wall Properties: Prefab Wall Properties:
- R value = 13 28
value = 13 28
BIM for Façade Prefabrication
- Mechanical
Breadth Conclusions Questions
- R-value = 10.63
value = 10.63
- U
U-
- value = 0.094
value = 0.094
- Thickness = 16”
Thickness = 16”
- R-value = 13.28
value = 13.28
- U
U-
- value = 0.075
value = 0.075
- Thickness = 11”
Thickness = 11”
Introduction Background Solar Panels
- Electrical
Breadth
Mechanical Breadth Mechanical Breadth Heat Loss: Heat Loss:
- Original Design
Original Design
BIM for Façade Prefabrication
- Mechanical
Breadth Conclusions Questions
Original Design Original Design
- 176,384 BTU/HR
176,384 BTU/HR
- Prefab Design
Prefab Design
- 141,145
141,145 BTU/HR BTU/HR
- 19 9% better
19 9% better
- 19.9% better
19.9% better
Introduction Background Solar Panels
- Electrical
Breadth
Mechanical Breadth Mechanical Breadth Conclusion: Conclusion:
- Prefab has better
Prefab has better
BIM for Façade Prefabrication
- Mechanical
Breadth Conclusions Questions
- Prefab has better
Prefab has better mechanical properties mechanical properties
- Still too expensive
Still too expensive
Introduction Background Solar Panels
- Electrical
Breadth
Conclusions Conclusions
- Solar panels not economical
Solar panels not economical
BIM for Façade Prefabrication
- Mechanical
Breadth Conclusions Questions
p
- BIM should have been used
BIM should have been used for mockups for mockups
- Prefab definitely shortens the
Prefab definitely shortens the schedule and adds quality schedule and adds quality schedule and adds quality, schedule and adds quality, but too expensive but too expensive
Introduction Background Solar Panels
- Electrical
Breadth
Acknowledments Acknowledments
University of University of Virginia: Virginia:
- Fred Dunn
Fred Dunn
- Jeff Moore
Jeff Moore
- Dee
Dee Eadie Eadie Gilb Gilb B ildi C B ildi C Clark Clark Nexson Nexson
- Jonathan
Jonathan Walker Walker
BIM for Façade Prefabrication
- Mechanical
Breadth Conclusions Questions
Gilbane Gilbane Building Company Building Company
- Mike
Mike Poulin Poulin, Project Executive , Project Executive ISEC, Inc.: ISEC, Inc.:
- Matt
Matt Heistand Heistand
- Paul
Paul Harsch Harsch Davis Davis Construction Construction Balfour Balfour Beatty Beatty Jacobs Jacobs Engineering Engineering United United States Army Corps States Army Corps Engineers Engineers
- Jim
Jim McAllister McAllister Eastern Exterior Wall Systems Inc.: Eastern Exterior Wall Systems Inc.:
- Wayne Martin
Wayne Martin United United States Army Corps States Army Corps Engineers Engineers The The Pennsylvania State University: Pennsylvania State University:
- Faculty