Asset criticality modelling in electricity distribution networks
Paul Mitchell and Simon Todd Commerce Commission
June 2018 EEA Conference
1
electricity distribution networks Paul Mitchell and Simon Todd - - PowerPoint PPT Presentation
Asset criticality modelling in electricity distribution networks Paul Mitchell and Simon Todd Commerce Commission June 2018 EEA Conference 1 Introduction Better understanding of EDB investment decisions Resilience and reliability
June 2018 EEA Conference
1
2
3
4
5
Identify asset hazard failure mode Estimate asset hazard failure mode return period (RP) Estimate cost of failure consequence (C) Estimate public or staff proximity to asset (HP) Calculate hazard risk cost Estimate asset health (AH - % or per unit)
Reliability risk cost
Modify asset expected failure rate by AH (FR) Estimate VoLL and affected load (VoLL, MW) Estimate asset
duration (h) Calculate reliability cost
𝐷 ∗ 𝐼𝑄 𝑆𝑄 𝐺𝑆 ∗ 𝑁𝑋 ∗ 𝑊𝑝𝑀𝑀 ∗ ℎ
* Note: This is an example only. We are not H&S experts. Please refer to relevant H&S advisors/Worksafe as appropriate.
6
7
8
9
10
11
12
(using VoLL and lost load)
13
14
15
16
* Note we have not included environmental or single asset HILP event costs but these could also be included
consultation – regulator understands also;
decisions;
17
18