MUDIT MAHESHWARI
MAKING ELECTRICAL AND FIRE SAFETY MANAGEMENT EFFECTIVE
ITC LIMITED
EFFECTIVE MUDIT MAHESHWARI ITC LIMITED ELECTRICAL SAFETY Need for - - PowerPoint PPT Presentation
MAKING ELECTRICAL AND FIRE SAFETY MANAGEMENT EFFECTIVE MUDIT MAHESHWARI ITC LIMITED ELECTRICAL SAFETY Need for safe work environment Electrical Mishaps & Accidents ALL INDIA ACCIDENT STATISTICS Source: https://data ta.gov.i v.in/
ITC LIMITED
Electrical Mishaps & Accidents Need for safe work environment
Source: https://data ta.gov.i v.in/
and installation as per standards
controls
Audits/ Inspections
as per standards
✓ITC’s Approach ✓Electrical & fire safety starts at the drawing board.
✓Designs of all projects is done as per national and international codes & standards, e.g., BIS, IEC, NFPA, IEEE etc. ✓Power system designs undergo a check at Corporate level - verification vis-à-vis codes, standards, best practices, etc. ✓Existing systems maintained as per BIS and international codes & standards and undergo periodic audit/ verification from Corporate
✓ Main hazards - Electrocution & Fire ✓ More importantly – Mitigation and prevention at different stages ✓ Then what should be the approach?
✓Design as per code des s & s standa andards ds ✓Procurement as per code des s & s standa andards ds ✓Installation as per code des s & s standa andards ds ✓Operation & Maintenance as per code des s & s standa andards ds
This s is the proce cess ss followe wed in ITC
✓Design
✓Procurement – example of Transformer ✓Installation – example of Cable ✓O & M – example of Switchgear panels Electrical Safety
✓IEC 61140 & IS 3043 provides guidance for protection against electric shock. ✓Under normal conditions – hazardous live parts shall not be accessible. ✓Under fault conditions – accessible conductive parts shall not be hazardous. Measures adopted to protect against this hazard, include; ✓Automatic disconnection of power supply.
disconnection of power supply system. .
As per IS:3043 - 1987 Clause 12.2.2.1 Issc/S = k/√t S = (Issc *√t)/k where S = Cross-sectional Area (sq.mm) Issc = Value (ac, rms) of fault current (Amp) t = Operating time of disconnection device (sec) k = Available Parameters t = 1 sec (max) k = 80 (for Steel with initial temp 40 deg C & final temp 500 deg C) = 205 (for Copper with initial temp 40 deg C & final temp 395 deg C) Earthing Strip Area Calculations (GI) Issc (Amp) t (sec) k (for bare Steel) Earthing Strip Area (sq. mm) Corrosion Allowance Final Earthing Strip Area Requirement (sq.mm) GI Earthing Strip Size (sq. mm) 10,000 1 80 125 15% 144 25 x 6 18,000 1 80 225 15% 259 50 x 6 25,000 1 80 313 15% 359 50 x 10 35,000 1 80 438 15% 503 50 x 10 42,000 1 80 525 15% 604 75 x 10 50,000 1 80 625 15% 719 75 x 10 65,000 1 80 813 15% 934 2 x 50 x 10 a ip ip Factor dependent on the material of the protective conductor, the insulation & initial & final Temepratures
Earthing Strip Sizing Basis
200 amps circuit breaker
Earth resistance 0.8 Ω Earth resistance 0.8 Ω Bonding wire 300m, 70sq mm copper @0.2 Ω /km = 0.06 Ω
Without bonding fault current = 240 / 1.6 = 150 amps (circuit breaker will not trip) With bonding fault current = 240 / 0.06 = 4000 amps (circuit breaker trips instantly)
Precautions against lightning
Source: https://NCRB.gov.in
✓ Air termination location – Angle method or Rolling sphere method ✓ An equal spacing of downcond conduct ctor is preferred around the perimeter of the building/ structure. Typical preferred values of distance between the downconductors should be as per following table.
Equipment – transformer / motor / switchgear / cable / UPS etc., conforms to relevant standards. How to verify ?
Tests on a power transformer (Refer IS 2026 & IEC 60076) Type tests
Temperature rise test as per IS 2026-2 Lightning Impulse test as per IS 2026-3
Routine tests
Winding resistance Voltage ratio and phase displacement Short circuit impedance and load loss No-load loss and current Dielectric routine tests Tests on OLTCs.
✓Most common failures for oil filled transformers
✓OLTCs ✓Bushing failure
✓Mode of power cable laying
✓MV power cables directly buried IS 1255 : Installation & maintenance of power cable
✓Relevant codes of practice to be followed. For LV switchgear assemblies:
➢Annual mV drop test across terminations or thermography tests.
Refer IS 16168
Date of tragedy: 23rd March 2010 Fatalities: 43
Courtesy Inshorts
Preliminary investigations (for various incidents) revealed: 1. Deviations from the approved municipal plan 2. Highly flammable materials stored 3. Exit routes and emergency exit staircases locked
25
What are the fire risks/ hazards involved in the process/ operations? Are the risks acceptable ? Who could be harmed ? Can the risks be reduced by altering designs or use of alternate technology/ materials ? What are the statutory Implications? Which codes/ standards are applicable ? What types of fire safety systems are required?
Factories Act and State factory Rules National Building Code of India Oil Industry Safety Directive (OISD) Petroleum Act and Rules CEA Regulations 2010 (Measures relating to Safety and Electric Supply) Insurance Risk Assessments
How to restrict fire?
Incipient stage Smouldering stage Flaming stage Fully developed stage Degradation stage
Time Temp
How to restrict fire?
Prevent Ignition:
Incipient stage Smouldering stage Flaming stage Fully developed stage Degradation stage
Time Temp
management
How to restrict fire?
Control combustion: Use of Fire retardant/ non-combustible material for interiors, Upholstery, office partitions, false ceiling etc.
Incipient stage Smouldering stage Flaming stage Fully developed stage Degradation stage
Time Temp
How to restrict fire?
Suppress fire:
Incipient stage Smouldering stage Flaming stage Fully developed stage Degradation stage
Time Temp
How to restrict fire?
Restrict by construction:
Incipient stage Smouldering stage Flaming stage Fully developed stage Degradation stage
Time Temp
Inadequate exiting arrangements Exits kept locked preventing people from escaping Inhalation of toxic gases such as Carbon monoxide, hydrogen cyanide (burning of plastics), phosgene (vinyl materials), etc.
BASEMENTS 1,2 KC ITC 1 IT1 [ building with fire consideration]
Shall be held with sufficient frequency to familiarize occupants with the drill procedure and to establish conduct of the drill as a matter of routine. Planning and conduct of drills shall be assigned only to competent persons. To be held at expected and unexpected times and under varying conditions. Orderly evacuation should receive priority over the speed of evacuation. Occupants should be accounted for. A record shall be kept.
Sources: Oregon Fire Code, NFPA, OSHA.
✓Standards followed in ITC
✓BIS ✓IEC ✓IEEE ✓BS EN ✓NFPA
Overview through Design Reviews and Audits
✓ Best in class Hazard Identification and Risk Assessment System ✓ Work permit controls ✓ Training Management ✓ Accident Investigations ✓ Usage of PPEs enforced
Overview through Audits and Inspections
Lets make a difference..