EFFECTIVE MUDIT MAHESHWARI ITC LIMITED ELECTRICAL SAFETY Need for - - PowerPoint PPT Presentation

effective
SMART_READER_LITE
LIVE PREVIEW

EFFECTIVE MUDIT MAHESHWARI ITC LIMITED ELECTRICAL SAFETY Need for - - PowerPoint PPT Presentation

MAKING ELECTRICAL AND FIRE SAFETY MANAGEMENT EFFECTIVE MUDIT MAHESHWARI ITC LIMITED ELECTRICAL SAFETY Need for safe work environment Electrical Mishaps & Accidents ALL INDIA ACCIDENT STATISTICS Source: https://data ta.gov.i v.in/


slide-1
SLIDE 1

MUDIT MAHESHWARI

MAKING ELECTRICAL AND FIRE SAFETY MANAGEMENT EFFECTIVE

ITC LIMITED

slide-2
SLIDE 2

ELECTRICAL SAFETY

Electrical Mishaps & Accidents Need for safe work environment

slide-3
SLIDE 3

ALL INDIA ACCIDENT STATISTICS

Source: https://data ta.gov.i v.in/

slide-4
SLIDE 4
  • Design, procurement

and installation as per standards

  • Training & Behavioural

controls

  • Robust tracking through

Audits/ Inspections

  • Operation & Maintenance

as per standards

SAFETY MANAGEMENT IN ITC LIMITED

slide-5
SLIDE 5

SAFETY HAZARDS

✓ITC’s Approach ✓Electrical & fire safety starts at the drawing board.

✓Designs of all projects is done as per national and international codes & standards, e.g., BIS, IEC, NFPA, IEEE etc. ✓Power system designs undergo a check at Corporate level - verification vis-à-vis codes, standards, best practices, etc. ✓Existing systems maintained as per BIS and international codes & standards and undergo periodic audit/ verification from Corporate

slide-6
SLIDE 6

ELECTRICAL SAFETY

✓ Main hazards - Electrocution & Fire ✓ More importantly – Mitigation and prevention at different stages ✓ Then what should be the approach?

✓Design as per code des s & s standa andards ds ✓Procurement as per code des s & s standa andards ds ✓Installation as per code des s & s standa andards ds ✓Operation & Maintenance as per code des s & s standa andards ds

This s is the proce cess ss followe wed in ITC

slide-7
SLIDE 7

STAGE WISE PREVENTION & MITIGATION

✓Design

  • example of Earthing & Lightning

✓Procurement – example of Transformer ✓Installation – example of Cable ✓O & M – example of Switchgear panels Electrical Safety

slide-8
SLIDE 8

✓IEC 61140 & IS 3043 provides guidance for protection against electric shock. ✓Under normal conditions – hazardous live parts shall not be accessible. ✓Under fault conditions – accessible conductive parts shall not be hazardous. Measures adopted to protect against this hazard, include; ✓Automatic disconnection of power supply.

  • Let us start with the minimum basic safety requirement for automatic

disconnection of power supply system. .

  • Interventions in earthing system design

DESIGN STAGE - EXAMPLE

slide-9
SLIDE 9

EARTHING

As per IS:3043 - 1987 Clause 12.2.2.1 Issc/S = k/√t S = (Issc *√t)/k where S = Cross-sectional Area (sq.mm) Issc = Value (ac, rms) of fault current (Amp) t = Operating time of disconnection device (sec) k = Available Parameters t = 1 sec (max) k = 80 (for Steel with initial temp 40 deg C & final temp 500 deg C) = 205 (for Copper with initial temp 40 deg C & final temp 395 deg C) Earthing Strip Area Calculations (GI) Issc (Amp) t (sec) k (for bare Steel) Earthing Strip Area (sq. mm) Corrosion Allowance Final Earthing Strip Area Requirement (sq.mm) GI Earthing Strip Size (sq. mm) 10,000 1 80 125 15% 144 25 x 6 18,000 1 80 225 15% 259 50 x 6 25,000 1 80 313 15% 359 50 x 10 35,000 1 80 438 15% 503 50 x 10 42,000 1 80 525 15% 604 75 x 10 50,000 1 80 625 15% 719 75 x 10 65,000 1 80 813 15% 934 2 x 50 x 10 a ip ip Factor dependent on the material of the protective conductor, the insulation & initial & final Temepratures

Earthing Strip Sizing Basis

slide-10
SLIDE 10

DESIGN STAGE - EARTHING

200 amps circuit breaker

Earth resistance 0.8 Ω Earth resistance 0.8 Ω Bonding wire 300m, 70sq mm copper @0.2 Ω /km = 0.06 Ω

Without bonding fault current = 240 / 1.6 = 150 amps (circuit breaker will not trip) With bonding fault current = 240 / 0.06 = 4000 amps (circuit breaker trips instantly)

slide-11
SLIDE 11

DESIGN STAGE – LIGHTNING PROTECTION

Precautions against lightning

slide-12
SLIDE 12

LIGHTNING PROTECTION

Source: https://NCRB.gov.in

slide-13
SLIDE 13

LIGHTNING PROTECTION

✓ Air termination location – Angle method or Rolling sphere method ✓ An equal spacing of downcond conduct ctor is preferred around the perimeter of the building/ structure. Typical preferred values of distance between the downconductors should be as per following table.

slide-14
SLIDE 14

LIGHTNING PROTECTION

slide-15
SLIDE 15

LIGHTNING PROTECTION

slide-16
SLIDE 16

CHECKING DURING PROCUREMENT

Equipment – transformer / motor / switchgear / cable / UPS etc., conforms to relevant standards. How to verify ?

 Check the type test report and verify it as per relevant standard.  Check the routine test report and verify it as per relevant standard.  Let us see the same for a power transformer ..

slide-17
SLIDE 17

CHECKING DURING PROCUREMENT

Tests on a power transformer (Refer IS 2026 & IEC 60076) Type tests

 Temperature rise test as per IS 2026-2  Lightning Impulse test as per IS 2026-3

Routine tests

 Winding resistance  Voltage ratio and phase displacement  Short circuit impedance and load loss  No-load loss and current  Dielectric routine tests  Tests on OLTCs.

✓Most common failures for oil filled transformers

✓OLTCs ✓Bushing failure

slide-18
SLIDE 18

CHECKING DURING INSTALLATION

slide-19
SLIDE 19

CHECKING DURING INSTALLATION

✓Mode of power cable laying

✓MV power cables directly buried IS 1255 : Installation & maintenance of power cable

slide-20
SLIDE 20

CHECKING DURING O & M

✓Relevant codes of practice to be followed. For LV switchgear assemblies:

➢Annual mV drop test across terminations or thermography tests.

Refer IS 16168

slide-21
SLIDE 21

CHECKING DURING O & M

slide-22
SLIDE 22

FIRE SAFETY

slide-23
SLIDE 23

STEPHEN COURT - KOLKATA

Date of tragedy: 23rd March 2010 Fatalities: 43

slide-24
SLIDE 24

COACHING CENTRE – SURAT

Courtesy Inshorts

slide-25
SLIDE 25

TROUBLING ISSUES

Preliminary investigations (for various incidents) revealed: 1. Deviations from the approved municipal plan 2. Highly flammable materials stored 3. Exit routes and emergency exit staircases locked

25

slide-26
SLIDE 26

WE, MUST KNOW

What are the fire risks/ hazards involved in the process/ operations? Are the risks acceptable ? Who could be harmed ? Can the risks be reduced by altering designs or use of alternate technology/ materials ? What are the statutory Implications? Which codes/ standards are applicable ? What types of fire safety systems are required?

slide-27
SLIDE 27

FACTORS INFLUENCING FIRE SAFETY

Factories Act and State factory Rules National Building Code of India Oil Industry Safety Directive (OISD) Petroleum Act and Rules CEA Regulations 2010 (Measures relating to Safety and Electric Supply) Insurance Risk Assessments

slide-28
SLIDE 28

FIRE PROTECTION

How to restrict fire?

Incipient stage Smouldering stage Flaming stage Fully developed stage Degradation stage

Time Temp

slide-29
SLIDE 29

FIRE PROTECTION

How to restrict fire?

Prevent Ignition:

  • Good House Keeping
  • Good Storage Practices
  • Good Engineering practices
  • Good O&M practices

Incipient stage Smouldering stage Flaming stage Fully developed stage Degradation stage

Time Temp

  • Adopt standards
  • Best training

management

slide-30
SLIDE 30

FIRE PROTECTION

How to restrict fire?

Control combustion: Use of Fire retardant/ non-combustible material for interiors, Upholstery, office partitions, false ceiling etc.

Incipient stage Smouldering stage Flaming stage Fully developed stage Degradation stage

Time Temp

slide-31
SLIDE 31

FIRE PROTECTION

How to restrict fire?

Suppress fire:

  • Portable fire extinguishers
  • Automatic sprinklers
  • Water mist suppression systems
  • Special extinguishing systems

Incipient stage Smouldering stage Flaming stage Fully developed stage Degradation stage

Time Temp

slide-32
SLIDE 32

FIRE PROTECTION

How to restrict fire?

Restrict by construction:

  • Fire compartmentation

Incipient stage Smouldering stage Flaming stage Fully developed stage Degradation stage

Time Temp

slide-33
SLIDE 33

Almost 74% of fire deaths have been due to panic and inhalation of smoke and other toxic fire gases. (Source: NFPA) Causes of deaths

 Inadequate exiting arrangements  Exits kept locked preventing people from escaping  Inhalation of toxic gases such as Carbon monoxide, hydrogen cyanide (burning of plastics), phosgene (vinyl materials), etc.

FIRE PROTECTION

slide-34
SLIDE 34
  • Typical Building 3-D view

BASEMENTS 1,2 KC ITC 1 IT1 [ building with fire consideration]

FIRE PROTECTION – EGRESS MODELLING

slide-35
SLIDE 35

FIRE PROTECTION

slide-36
SLIDE 36

FIRE PROTECTION

slide-37
SLIDE 37

Emergency Egress and Relocation Drills

 Shall be held with sufficient frequency to familiarize occupants with the drill procedure and to establish conduct of the drill as a matter of routine.  Planning and conduct of drills shall be assigned only to competent persons.  To be held at expected and unexpected times and under varying conditions.  Orderly evacuation should receive priority over the speed of evacuation.  Occupants should be accounted for.  A record shall be kept.

Sources: Oregon Fire Code, NFPA, OSHA.

FIRE PROTECTION - TRAINING

slide-38
SLIDE 38

FIRE PROTECTION

slide-39
SLIDE 39

✓Standards followed in ITC

✓BIS ✓IEC ✓IEEE ✓BS EN ✓NFPA

ADOPTING STANDARDS & CODES TO ENSURE EFFECTIVE SAFETY MANAGEMENT SYSTEMS

Overview through Design Reviews and Audits

slide-40
SLIDE 40

✓ Best in class Hazard Identification and Risk Assessment System ✓ Work permit controls ✓ Training Management ✓ Accident Investigations ✓ Usage of PPEs enforced

BEST PROCESSES TO ENSURE EFFECTIVE SAFETY MANAGEMENT SYSTEMS

Overview through Audits and Inspections

slide-41
SLIDE 41

THANK YOU

Lets make a difference..