SLIDE 1
Educational Session: Wednesday, March 28th 8:00 - 9:30 A.M. Matsen - - PowerPoint PPT Presentation
Educational Session: Wednesday, March 28th 8:00 - 9:30 A.M. Matsen - - PowerPoint PPT Presentation
Educational Session: Wednesday, March 28th 8:00 - 9:30 A.M. Matsen Ford Design Associates, Inc. Waukesha, Wisconsin Load Bearing and Exterior CFS Stud Walls Cold-Formed Steel NOT Light Gauge Floor System Roof System
SLIDE 2
SLIDE 3
¨ Load Bearing and Exterior CFS Stud Walls
§ Cold-Formed Steel NOT Light Gauge
¨ Floor System ¨ Roof System ¨ Lateral Force Resisting System
SLIDE 4
¨ ‰ Typical Stud Walls (Aligned @ 16” or 24” o.c.)
§ ‰
Generic Design
§ ‰
Proprietary
§ ‰
Top Track Designed Based on Floor System
§ ‰
HSS Distribution
¨ ‰ Openings
§ ‰
Headers (Generally Boxed)
§ ‰
Jambs (King Studs + Shoulder Studs)
SLIDE 5
Courtesy of: Wall-Tech, Inc.
SLIDE 6
¨ ‰ CFS Joists (16” or 24” o.c.)
§ ‰
Generic or Proprietary (8” to 16” deep)
§ ‰
Cementitious Board or Floor Deck w/ Lightweight Topping (1 ½” to 2” thickness)
¨ ‰ Long Span Deck
§ ‰
Typical Composite Profile
§ ‰
Dovetail Profile
§ ‰
Typically 4” to 6” total thickness
SLIDE 7
¨ ‰ Proprietary Composite Joist System (48” o.c.)
§ ‰
Delegated Design (L/D=20)
§ ‰
Concrete Slab or Slab-on-Deck
§ ‰
3”- 4” Slab + Joist Depth
¨ ‰ Hollow Core PCC Plank
§ ‰
Delegated Design
§ ‰
Set w/ Crane
§ ‰
Typically 8” PCC Plank + Topping
SLIDE 8
¨ ‰ CFS Trusses (24” to 48” o.c.)
§ ‰
Delegated Design (L/D=20)
§ ‰
Top or Bottom Chord Bearing
§ ‰
Cementitious Board or Floor Deck w/ Lightweight Topping (1 ½” to 2” thickness)
SLIDE 9
¨ ‰ CFS Joists (16” or 24” o.c.)
§ ‰
Generic or Proprietary (8” to 16” Deep)
§ ‰
Cementitious Board or Roof Deck w/ Rigid Insulation and Membrane
¨ ‰ Long Span Deck
§ ‰
Typical Composite Profile
§ ‰
Dovetail Profile
§ ‰
Typically 4” to 6” Thickness w/ Rigid Insulation and Membrane
SLIDE 10
¨ ‰ Proprietary Composite Joist System (48” o.c.)
§ ‰
Delegated Design (L/D=20)
§ ‰
Concrete Slab or Slab-on-Deck
§ ‰
3”- 4” Slab w/ Rigid Insulation and Membrane
¨ ‰ Hollow Core PCC Plank
§ ‰
Delegated Design
§ ‰
Set w/ Crane
§ ‰
Typically 8” PCC Plank w/ Rigid Insulation and Membrane
SLIDE 11
¨ ‰ CFS Trusses (24” to 48” o.c.)
§ ‰
Flat or Sloping
§ ‰
Top or Bottom Chord Bearing
§ ‰
Cementitious Board or Roof Deck w/ Rigid Insulation and Membrane
SLIDE 12
¨ ‰ CFS Shear Walls
§ ‰
X-Braced
§ ‰
Diaphragm (Gyp. Board, Steel Sheet, Proprietary)
¨ ‰ Stair and Elevator Cores
§ ‰
CMU
§ ‰
Cast-In Place Concrete
§ ‰
Pre-Cast Concrete
SLIDE 13
SLIDE 14
¨ Metreau Apartments is a mixed-use luxury apartment
complex located on the Fox River in Green Bay, WI. The eight story project features seven stories of residential units above the first story retail and amenities level and lower level parking.
¨ The residential levels are a mix of studio, one and two
bedroom and penthouse units. The amenities level features a Community Room, Fitness Center, Media Lounge and Sun Deck.
¨ Cold-Formed Steel Framing is featured as the primary
gravity and lateral load carrying structure at the residential levels above a pre-cast concrete transfer
- structure. All CFS walls and floors were panelized
- ffsite and delivered to the site.
¨ 170,000 ft2 Total, 114,000 ft2 @ CFS Levels.
SLIDE 15
¨ The upper seven stories are cold-formed steel
framed bearing walls and C-Joist floors with flat CFS pre-fabricated roof trusses.
¨ The first story and lower level is PCC post-and-
beam framing supporting PCC floor at 1st and 2nd floor transfer/podium slab.
¨ The foundation consists of concrete filled steel
piles and pile caps w/ grade beams.
¨ The main lateral resisting system is a mix of X-
braced CFS shear walls and PCC stair and elevator shear walls at the residential levels transferring thru the podium level diaphragm into PCC shear walls at the first level.
SLIDE 16
SLIDE 17
SLIDE 18
SLIDE 19
SLIDE 20
SLIDE 21
SLIDE 22
SLIDE 23
SLIDE 24
SLIDE 25
SLIDE 26
SLIDE 27
Loads and Serviceability Limits
SLIDE 28
SLIDE 29
Cast-In-Place & Pre-Cast Concrete
SLIDE 30
¨ Concrete Filled Piles w/ Pile Caps:
§ Poor Soil Bearing Capacity vs. Building Loads § Proximity to river § 10 3/4” x 3/8” Piles § Pile Caps vary from 2’-6” to 3’-11” deep supporting
groups of 1 to 30 Piles
¨ Grade Beams:
¡ 24” x 24”
¨ Slabs-on-Grade:
¡ 5” w/ WWF typically at lower level parking
SLIDE 31
Courtesy of: Wall-Tech, Inc.
SLIDE 32
¨ Post & Beam (Lower Lvl. & Level 1): ¨ Transfer Slab (Level 2):
§ Transfers Gravity and Lateral Loads § Line Loads and Point Loads (Gravity & Lateral)
Provided to PCC Designer by MFDA.
¨ Shear Walls:
§ 12” Thick Solid Stair and Elevator Cores § Transfer Beams below shear walls § Lateral Loads to Stair and Elevator Walls provided
by MFDA
SLIDE 33
Courtesy of: Wall-Tech, Inc.
SLIDE 34
SLIDE 35
Roof Trusses, Floor Joists and Wall Framing
SLIDE 36
¨ ‰ 36 “ Pre-Fabbed CFS Trusses @ 24” o.c.
§ ‰
36” Deep (Typ.) w/ 12” Deep at Corridors
§ ‰
Spans up to 44’-3”
§ ‰
1 ½” x 22 Gage Type B Deck
¨ ‰ Supported by CFS Stud Walls @ 16” o.c.
§ ‰
CFS Distribution Device for Off-Module Transfer
¨ ‰ Fall Arrest Anchors Built into Trusses ¨ ‰ Delegated Design Submittal ¨ ‰ Pre-Fabricated off-site
SLIDE 37
Interior Bearing Exterior Bearing w/ Parapet Exterior Non-Bearing w/ Parapet
SLIDE 38
¨ 12” x 16 gage (54 mil) to 12 gage (97 mil) C-
Joists (2” flange) @ 16” o.c. were used at Living Spaces & Terrace spans up to 26’ (Longer spans doubled at Terraces)
§
Spans up to 26’ (Longer spans doubled at Terraces)
¨ 8” x 16 ga. (54 mil) C-Joists @ 16” o.c. were
used at Corridors
¨ Strap & Blocking required @ +/- 6’-0” o.c. ¨ Fastened to end tracks & studs walls with 14
- ga. (68 mil) clips, Alternate for TradeReady
Rim Tracks
SLIDE 39
¨ End track was used in many locations to
eliminate the need for load bearing headers
¨ 9/16” x 22 ga. Type C Deck with LevelRock
flooring between studs walls (1 ½” total)
¨ Fall Arrest anchors built into terrace joists w/
HSS welded into webs of double joists
¨ Joists and End Tracks welded to embed plates
at PCC shear walls for lateral load transfer
¨ Floor Panel Drawing were reviewed by design
team for member and dimensional accuracy
¨ Pre-Fabricated Floor Panels built off-site
SLIDE 40
Exterior Bearing Interior Bearing
SLIDE 41
Connection at PCC Shear Wall (Gravity & Lateral Transfer) Fall Arrest Bracing at Terrace
SLIDE 42
Courtesy of: Wall-Tech, Inc.
SLIDE 43
SLIDE 44
¨ 6” x 12 gage (97 mil) to 18 gage (43 mil) C-Studs
(1-5/8” to 3” flanges) were used at exterior and interior bearing cases; 18 gage at exterior non-bearing cases; all spaced at 16”o.c. typ.
¨ ALL STUDS ALIGNED FROM FLOOR-TO-FLOOR ¨ Parapets designed for Fall Arrest Loading ¨ Bridging was cold-rolled channel with 16 gage clip
angles (or proprietary clips) @ 48” o.c.
¨ Top tracks were 1 ¼” flange of matching gage at non-
shear walls; Bottom tracks were 3” flange of matching gage
§
Pour Stop for floor topping and fastening surface for gypsum board
SLIDE 45
¨ Boxed Headers were used at typical load bearing
- penings with King + Shoulder Stud Jambs
¨ Rim Tracks and End Joists carry gravity loads at NLB
- penings and narrow LB openings with single BAF
jamb studs
¨ Wall Panel Drawings were reviewed by design team for
member and dimensional accuracy
¨ Walls were prefabricated off-site
§ Stud panels were compressed for tight seating in top
and bottom track
§ Typical fabrication was done with screw attachments
at lighter gages and welding of the heavier gages
SLIDE 46
¨ Typical Story Heights:
§ Levels 2 – 6 = 10’-8” § Level 7 = 12’-0” § Level 8 = 13’-1 1/8” (Setback)
¨ Maximum Loads per Stud:
§ Interior Bearing = 17.2 K § Exterior Bearing = 10.7 K (typ.)
= 12.9 K (Brick)
§ Exterior Non-Bearing = 1.9 K (typ.)
= 5.7 K (Brick)
¨ Studs had to be designed for eccentricity of
joists framing into the sides
SLIDE 47
SLIDE 48
SLIDE 49
Courtesy of: Wall-Tech, Inc.
SLIDE 50
SLIDE 51
SLIDE 52
¨ X-Braced:
§ Straps vary from 4” x 16 ga. to 10” x 12 ga. § Posts vary from HSS 6x6x3/16 @ 2-3, Dbl. S300’s @
4-6 & Single S250’s @ 7-8
§ Welded Ear Plates @ 1st, Dbl. Angles @ 2-6, Single
Angles @ 7-8
§ ¾”, 7/8” & 1” Diam. Bolts (A325 & A490)
SLIDE 53
SLIDE 54
SLIDE 55
¨ Balconies
§ CFS Posts at corners – 68 & 97 mil § Inset at South Elevation § Hanging at North Elevation § Off-Set Shelf-Angles and knife plates (by EOR) to
allow veneer to by-pass
§ C6 “Drop-In” Balcony Frames field bolted § Loads to posts provided by EOR
SLIDE 56
SLIDE 57
¨ Brick Relief
§ 7x6x3/8 Angle welded to CFS at window head ht. § Studs and headers designed for brick support
SLIDE 58
¨ Shear Wall Transfer at Podium
§ Embed Plates in PCC Deck for CFS Shear Walls § PCC Elevator Shear Walls stop at Podium Level § PCC Transfer Beams
SLIDE 59
¨ Parapet Design for Fall Arrest Loads
§ 1.8 K in either direction at any point § 600S200-97 nested inside 600T300-97 § Transfer loads to studs (axial & bending) § Lateral connection to structure
SLIDE 60
¨ Wall Panels:
§ 1106 Total Panels, 158 Panels per Floor § 11,508 ln. ft. total, 1,644 ln. ft. per Floor § Fabrication = 5.5 hr/150 ft2 (sheathed) § 455 HSS shapes fabricated into panels
¨ Floor Panels:
§ 670 Total Panels, 111 Panels per Floor § 97,236 ft2 total, 16,706 ft2 per Floor § Fabrication = 5.7 hr/150 ft2
¨ Shipping:
§ 12’-0” max. in one direction § Shipped flat § +/- 1500 lb./pnl. to avoid damage
SLIDE 61
¨ Erection:
§ Eight Man Crew § Walls = 5 Days per floor § Largest Panel = 28’-4” x 10’-6 ½” (1654 lb.) § Floors = 5 Days per floor incl. Deck § Largest Panel = 26’-0” x 12’-0” (1642 lb.) § Erection = 5 Days per Floor (8 man crew) § 2 weeks total per floor
SLIDE 62
SLIDE 63
SLIDE 64
SLIDE 65
¨ Project Architect:
§ Eppstein Uhen Architects – Milwaukee, WI
¨ Project Engineer:
§ Pierce Engineers, Inc. – Milwaukee, WI
¨ Specialty Engineer:
§ Matsen Ford Design Associates, Inc. – Waukesha, WI
¨ General Contractor:
§ Catalyst Construction – Milwaukee, WI
¨ Panelizer & Erector:
§ Wall-Tech, Inc. – DeForest, WI
SLIDE 66
SLIDE 67