Monday, December 18, 2017 1 Region 8: Woodbury Transit & Economic Development Hub (Route 17 at Route 32 - Exit 131) Reconstruction Project Thursday, December 14, 2017 2 Agenda Welcome & Team Introductions Project Update


slide-1
SLIDE 1

Thursday, December 14, 2017

Region 8: Woodbury Transit & Economic Development Hub (Route 17 at Route 32 - Exit 131) Reconstruction Project

1 Monday, December 18, 2017

slide-2
SLIDE 2

Agenda

  • Welcome & Team Introductions
  • Project Update
  • Project Overview
  • Open House Format & Comments

2

slide-3
SLIDE 3

Project Update

  • RFP process
  • Procurement process

3

slide-4
SLIDE 4

Project Benefits

  • Improved levels of service/travel time
  • Improved safety
  • Fewer environmental impacts
  • Utility upgrades

4

slide-5
SLIDE 5

5

Project Overview

slide-6
SLIDE 6

Benefits of the Project

6

  • Improved access to the surrounding

retail, school, highway, & local roadways

  • Minimizes impact on local

neighborhoods and businesses during construction

  • Minimizes conflict points and increased

safety

  • Simplifies driver navigation
  • Relocate existing overhead utilities

underground

slide-7
SLIDE 7

Existing

  • Three phase signals along Route 32
  • Two travel lanes and a left turn bay along Route 32

Proposed

  • Two phase signals along Route 32
  • Three travel lanes and a left turn bay on Route 32

Exit 131 Eastbound Ramps at Route 32

slide-8
SLIDE 8

8

slide-9
SLIDE 9

9

slide-10
SLIDE 10

Existing

  • Route 17 WB Off-Ramp has minimal time to

access Route 32

  • One right turn lane from Route 32 southbound to

Nininger Road

Proposed

  • Route 17 WB Off-Ramp gets maximum allowable time

depending on Route 32 traffic conditions

  • Two right turn lanes from Route 32 to Nininger Road
  • Nininger Road Extension separates local traffic and

connect to Woodbury Common Premium Outlets on the south side

Exit 131 Westbound Ramps/Nininger Road at Route 32

slide-11
SLIDE 11

Existing

  • Two travel lanes on Route 32 with turn lanes
  • Two approach lanes off of Route 6
  • Park-N-Ride holds 100 vehicles

Proposed

  • Three travel lanes on Route 32 with turn lanes
  • Three approach lanes off of Route 6
  • Park-N-Ride holds 200 vehicles

Route 32 Corridor Between US 6 and Route 17

slide-12
SLIDE 12

Existing

  • One northbound lane enters Woodbury Commons
  • Two exits from Woodbury Commons to Route 32
  • Two travel lanes in each direction on Route 32

Proposed

  • Two northbound lanes entering Woodbury Commons
  • One exit from Woodbury Commons to Route 32 and
  • ne to the Nininger Road Extension
  • Three travel lanes in each direction on Route 32

Route 32 Corridor Between Woodbury Commons and School

slide-13
SLIDE 13

13

slide-14
SLIDE 14

Project Timeline

  • Minor construction activities start winter of 2018
  • Major construction activities start spring of 2018
  • Route 32 southbound work completed fall of 2018
  • Route 17 eastbound work completed winter of 2018
  • Route 32 northbound work completed/DDI implementation late summer of 2019
  • Route 17 westbound work completed late summer of 2019
  • Project completion fall of 2019

14

slide-15
SLIDE 15

Open House

  • Staff to answer questions
  • Stenographer to collect comments
  • Comment forms & comment box
  • Sign up for project updates & information

15

slide-16
SLIDE 16

Divergent Diamond Design

  • FHWA video (https://www.youtube.com/watch?v=BcxUaNLaJVM)

16