SLIDE 2 6/11/2014 2
Downtown Master Plan Process
1.
Data Collection/Inventory – now through early July
2.
Downtown Analysis – June‐August
A.
What’s working/What needs work
B.
Public input survey 3.
Plan Preparation – September
A.
Public input summary
B.
Goals & Objectives
C.
Future Land Use
D.
Focus areas: Infill design concepts, expansion area, refined recommendations from Visioning Report
E.
Implementation Strategies 4.
Draft Plan – October
5.
Required Review – October/November
6.
Public Hearing – December/January
7.
Approval by DDA, Adoption by Planning Commission, & Adoption by City Council