donaldson run tributary b stream restoration project
play

Donaldson Run Tributary B Stream Restoration Project Update - PowerPoint PPT Presentation

Donaldson Run Tributary B Stream Restoration Project Update Donaldson Run Civic Association Meeting April 18, 2012 Donaldson Run watershed Donaldson Run Watershed Boundary Tributary C Taylor School Tributary B Tributary A Big


  1. Donaldson Run Tributary B Stream Restoration Project Update Donaldson Run Civic Association Meeting April 18, 2012

  2. Donaldson Run watershed Donaldson Run Watershed Boundary Tributary C Taylor School Tributary B Tributary A

  3. ‘Big picture’ concepts  Past land use and drainage decisions have severely impacted County streams  Watershed improvements and in-stream restoration efforts are both essential  Urban stream corridor damage must be addressed comprehensively  Stream restoration accomplishes multiple resource management objectives  Neighborhood partnership is essential

  4. Sediment and Nutrients Unrestored Tributary B Restored Tributary A with visibly lower with visibly higher sediment content sediment content

  5. County/Donaldson Run Civic Association Partnership  10+ year partnership  Stream restoration top neighborhood priority  NCAC approved Tributary B funding in December 2007; County Board 2008; DES providing additional funds  Extensive County/DRCA public process: meetings, workshops, stream walks, newsletter articles, park signs, Citizen articles, and other media coverage

  6. KEY PROJECT FACTS: • Approved Neighborhood Conservation Program Project • 1,400 linear feet to Upton street • 26% impervious cover in watershed • Natural channel design approach

  7. Updates from prior design to current (~95%) design  Hydraulic analyses for FEMA permitting underway  Vertical elevation of water main determined; design adjustments in process  Storm pipe drainage inputs  Inspection of pipes completed  Easement process underway  Finalizing design  Advancement of planting plan and invasive plant management strategy  Consideration of construction access, equipment type, future maintenance access

  8. Storm pipe drainage inputs  Verified pipe conditions  Acquiring necessary easements  Incorporating needed repairs/modifications into project design

  9. 30” Water Main  Interim work completed to protect exposed pipe last year  Few apparent conflicts with stream restoration design except at stilling basin – design adjustments in process  Considering reinforced streambed crossings for future access to main if needed

  10. Trees  No change in tree impacts from project from 60% designs to current design  One tree removed to protect water main (previously listed as a potential removal)  One tree has fallen (previously listed as a removal)  Project impact: 36 trees>10” diameter, 72 trees overall

  11. Invasive Management & Planting Plan Goals:  To restore forest structure and function  To support recreational use and aesthetics

  12. Kudzu Invasive Plants  85-95% invasive species in the shrub and ground layers  invasive species present on both park and private properties  27 different species

  13. Implications  Invasive management considerable component of the project  Project requires integrated planting and invasive plant removal  4-6 year planting and invasive plant maintenance schedule  Complete removal of invasive species is likely not possible  Most successful if private citizens are involved in invasive management

  14. 2011 Invasive Management Actions  Invasive plant removal workdays – spring & fall  Invasive plant workshops  Upshur St - Hosted by Amy White  Stuart St - Hosted by Sarah & Jeffrey Knight  Invasive plant replacement mini-grants  Developed a native plant list for DR homeowners

  15. Future Actions  Spring and fall events - Tributary A & B  Invasive plant workshop(s)? – Tributary A & B  Native plant rescue  Creating a RIP team (Remove Invasive Plants)  Coordination with Arlington Master Naturalists

  16. Planning & Chemical Control  Limited chemical application in 2011  Contract spraying – Summer 2012  Invasive management plan – Tributary A

  17. Invasive Management  “Clean” equipment  Mulch or mats for trees/shrubs  Seed heavily • Protect trees and shrubs (deer) • Focus on stream banks • Target species • Coordinate invasive removal and planting • Timing of control will depend on plant life cycle • Flexible and adaptive • Budget

  18. Planting Plan  Site specific  All plants will be native to Zachary Taylor Park  Planting “zones” to account for habitat changes with elevation and distance from the stream.  Special plantings for sensitive areas  Multi-year to account for invasive control and natural forest succession

  19. Scarlet oak Arrowwood Bluestem goldenrod Quercus coccinea Viburnum dentatum Solidago caesia

  20. Zoned Planting - Example Slope Floodplain

  21. Special Areas – Bare Slopes

  22. Construction methods, equipment, & materials

  23. Smaller materials and equipment

  24. Tree protection techniques, Mats

  25. Next Steps  Finalize design work for storm pipe drainage inputs  Obtain necessary easements  Finalize planting plan and invasive plant management plan  Develop construction access/staging plan  Complete specifications including tree protection plan  Target design completion by fall  Construction schedule still TBD

  26. Tributary A, June 2010 Stream restoration, watershed retrofits, Chesapeake Bay Preservation Ordinance, Stormwater Permit and more…. Learn more at: www.arlingtonva.us – search “Donaldson Run.”

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend