September 18, 2019
Chris Hatton – Project Manager, Diversion
Div Diver erting the ting the Peace eace Riv River er Chris - - PowerPoint PPT Presentation
Div Diver erting the ting the Peace eace Riv River er Chris Hatton Project Manager, Diversion September 18, 2019 Pr Pres esen enta tation tion over erview view What is river diversion? Stages of the river diversion
September 18, 2019
Chris Hatton – Project Manager, Diversion
the construction of the Site C dam
And how do we do it?
3
4
5
approximately 750 metres long and 11 metres in diameter
Peace River
summer 2018
pass 3,000 cubic metres of water per second (combined)
6
in both tunnels
construction
7
8
9 Peace Island Park Halfway River
10
11
12
13
✓ More than 55 environmental and regulatory requirements are met ✓ Debris management infrastructure and system are in place ✓ Fishway is complete and commissioned ✓ Both tunnels and operating gates are commissioned and readied for service ✓ Operating gates are opened and the inlet and outlet cofferdams are excavated, allowing water to flow through the tunnels ✓ A rockfill berm is constructed immediately downstream of the intake for the purpose of directing the water to the tunnels ✓ Upstream and downstream cofferdams are constructed, and the area between the cofferdams is emptied of water
Diversion can begin when:
14
Examples of normal–low, normal–high and spring runoff events
15
SITE C PROJECT CONSTRUCTION DIVERSION HEADPOND River flow rates during river diversion
For illustrative purposes only
Normal–low flow month (August)
16
SITE C PROJECT CONSTRUCTION DIVERSION HEADPOND River flow rates during river diversion Normal–low flow month (August)
For illustrative purposes only
Normal–high flow month (December)
17 For illustrative purposes only
SITE C PROJECT CONSTRUCTION DIVERSION HEADPOND River flow rates during river diversion Normal–high flow month (December)
diversion process, navigation restrictions and portage program
How we will help communities prepare
18
19