design for deconstruction for sustainable composite steel
play

Design for Deconstruction for Sustainable Composite Steel- Concrete - PowerPoint PPT Presentation

Design for Deconstruction for Sustainable Composite Steel- Concrete Floor Systems Jerome F. Hajjar, Lizhong Wang Department of Civil and Environmental Engineering Northeastern University Mark D. Webster Simpson Gumpertz and Heger, Inc.


  1. Design for Deconstruction for Sustainable Composite Steel- Concrete Floor Systems Jerome F. Hajjar, Lizhong Wang Department of Civil and Environmental Engineering Northeastern University Mark D. Webster Simpson Gumpertz and Heger, Inc. Advances in Steel-Concrete Composite Structures (ASCCS 2018) Valencia, Spain, June 29, 2018

  2. Sustainable Building Systems End-of-life of Construction Materials End-of-life of construction materials Image from SteelConstruction.Info Introduction DfD Floor System Pushout Tests Beam Tests Design Conclusions

  3. Design for Deconstruction Composite Floor System • Conventional composite floor systems are cost-effective solutions for multi-story buildings • The integration of steel beams and concrete slab limits separation and reuse of the components • Proposed DfD System: Clamp precast planks to steel beams/girders in a steel framing system • Both the steel members and the precast planks may be reused 24'' Precast concrete plank Cast-in channels 6'' 6'' 12'' 6'' Steel beam a) Plank perpendicular to the steel beam Tongue and groove side joint 6'' 12'' 12'' 12'' 12'' 12'' Clamps Bolts b) Plank parallel to the steel girder Deconstructable composite beam prototype Precast concrete plank cross section Introduction Pushout Tests Beam Tests Design Conclusions DfD Floor System

  4. Design for Deconstruction DfD Floor System Goal: Achieve nearly 100% direct reusability for composite floor systems within the context of bolted steel framing systems 30' 30' 30' 10' 30' 10' 10' 10' 30' 10' 10' 10' 30' 10' 10' ConXtech moment connection Image from ConXtech Website Typical floor plan for DfD system Example of deconstructable bolted connection Introduction DfD Floor System Pushout Tests Beam Tests Design Conclusions

  5. Design for Deconstruction Test Program • Pushout tests: evaluate a wide range of parameters and formulate strength design equations for the clamping connectors • Beam tests: study the clamp connector behavior and associated composite beam strength and stiffness for different levels of composite action Self-reacting Frame Actuators Spreader System Steel Beam Reaction Angle Precast Concrete Plank Precast Concrete Planks Steel Beam Pushout test setup Composite beam test setup Introduction Pushout Tests Beam Tests Design Conclusions DfD Floor System

  6. Pushout Test Setup Pushout Test Configuration Load Elevation View Self-reacting Frame Actuators Load Steel Beam Reaction Precast Concrete Angle Plank Pushout test setup Plan View Introduction DfD Floor System Pushout Tests Beam Tests Design Conclusions

  7. Pushout Test Parameters Pushout Test Matrix Test parameters Series Specimen Bolt Number of Reinforcement Shim T bolts configuration diameter M 2-M24-T4-RH 4 Heavy No M24 M 3-M24-T4-RH-S 4 Heavy Yes M24 M 4-M24-T6-RH 6 Heavy No M24 M 5-M20-T4-RH M20 4 Heavy No C 6-C24-T4-RH M24 4 Heavy No C 7-C24-T4-RL M24 4 Light No C 8-C24-T4-RH-S M24 4 Heavy Yes C 9-C24-T6-RH M24 6 Heavy No C 10-C20-T4-RH M20 4 Heavy No Steel shims Three-channel specimen Two-channel specimen with shims Introduction DfD Floor System Pushout Tests Beam Tests Design Conclusions

  8. Pushout Test Parameters Reinforcement pattern Loading protocols • Light pattern: Contains reinforcement • Monotonic test: Displacement control designed for gravity loading only • Cyclic test: • Displacement control • Emulate AISC 341-10 K2.4b “Loading Sequences for Beam-to-Column Moment Connection” 128 150 6 mm 96 • Heavy pattern: Supplementary mm 100 4 64 reinforcement bridges all potential mm 32 concrete failure planes 50 2 16 mm 8.0 4.0 50% of 2.0 0.5 1.0 Slip (mm) mm Slip (in.) mm mm slip load mm mm mm 0 0 75% of 0.75 1.5 37.5% of 3.0 6.0 12 slip load slip load mm mm mm 24 mm mm -50 -2 mm 48 mm -100 -4 1.5 mm/min 6 mm/min 24 mm/min 0.375 mm/min 0.75 mm/min 3 mm/min 12 mm/min 48 mm/min -150 -6 0 6 12 18 22 26 30 34 38 42 46 50 54 Cumulative cycles Introduction DfD Floor System Pushout Tests Beam Tests Design Conclusions

  9. Pushout Test Results Monotonic Test Results Slip (in.) Slip (in.) 0 1 2 3 4 5 6 7 8 9 10 11 0 1 2 3 4 5 6 7 8 9 10 11 60 400 90 250 75 50 320 200 40 60 240 150 45 30 160 100 20 30 80 50 15 10 M24-T4-RH M20-T4-RH 0 0 0 0 0 30 60 90 120 150 180 210 240 270 0 30 60 90 120 150 180 210 240 270 Slip (mm) Slip (mm) • The shear strength of a M24 clamp is 98.3 kN, while the strength of a 19 mm (3/4 in.) diameter shear stud embedded in a 27.58 MPa (4 ksi) solid concrete slab is 95.6 kN. • The very large initial stiffness of the clamps reduces the slip at the steel-concrete interface at the serviceability and enhances the stiffness of the composite beams. • The M24 clamps can retain almost 80% of the peak strength even at a slip of 125 mm, while shear studs usually fracture under much less deformation (~8 mm). • The smaller M20 clamps are prone to rotate. The strength degradation starts at a slip of 17.3 mm, which is usually much larger than the maximum slip demand on shear connectors in composite beams. Introduction DfD Floor System Pushout Tests Beam Tests Design Conclusions

  10. Pushout Test Results Cyclic Test Results Slip (in.) Slip (in.) -1 -0.75 -0.5 -0.25 0 0.25 0.5 0.75 1 -6 -5 -4 -3 -2 -1 0 1 2 3 4 5 6 80 20 320 80 60 15 240 60 40 10 160 40 5 20 20 80 0 0 0 0 -20 -80 -5 -20 -40 -160 -10 -40 -60 -240 -15 Light reinforcement -60 -80 Heavy reinforcment -320 -20 -80 -150 -120 -90 -60 -30 0 30 60 90 120 150 -24 -18 -12 -6 0 6 12 18 24 Slip (mm) Slip (mm) Specimens C24-T4-RH and C24-T4-RL Specimen C24-T4-RH (within 25 mm slip) • Strength reduction similar to shear studs which exhibit lower strength and ductility when subjected to cyclic loading • The peak load reduces due to lowering of frictional coefficients and release of bolt tension caused by abrasion between the components. • Clamps have the potential to connect composite diaphragms and collector beams and could be designed as inelastic components to dissipate energy. Introduction DfD Floor System Pushout Tests Beam Tests Design Conclusions

  11. Beam Test Setup Composite Beam Test Composite beam test setup Percentage of # of Composite Steel beam Reinforcement Number of composite action Bolt size channels beam # section configuration bolts (clamps) Nominal Actual per plank 1-M24-2C-RH M24 2 W14x38 Heavy 56 86.7% 82.7% 2-M24-1C-RL M24 1 W14x38 Light 30 47.3% 45.1% 3-M20-3C-RL M20 3 W14x26 Light 90 129.2% 137.8% 4-M20-1C-RL M20 1 W14x26 Light 30 43.0 % 43.8% Introduction DfD Floor System Pushout Tests Beam Tests Design Conclusions

  12. Engineering Sustainability: DfD DfD Composite Beam Tests at STReSS Lab • Vertical load vs. vertical deflection DfD Beam Specimen 1: Fully Composite Overview of Specimen • Load transfer occurs through the clamps without causing damage to either the steel beam or concrete planks View Underneath DfD Beam Specimen 4: Partially Composite Specimen Showing Clamps in Action

  13. Beam Test Results Load-Deflection Curves Deflection (in.) Deflection (in.) 0 3 6 9 12 15 0 3 6 9 12 15 140 120 600 500 AISC prediction AISC prediction 120 100 500 400 100 80 Test 1-M24-2C-RH Test 2-M24-1C-RL 400 80 300 60 (11.43 mm, 96.39 kN) 300 60 (9.65 mm, 96.39 kN) Slip 200 Beam yielding Beam yielding 40 200 40 Slip Concrete crushing at east side First bang 100 First bang 100 20 20 Concrete crushing Concrete crushing at west side 0 0 0 0 0 50 100 150 200 250 300 350 0 50 100 150 200 250 300 350 Deflection (mm) Deflection (mm) Deflection (in.) Deflection (in.) 0 3 6 9 12 15 18 0 3 6 9 12 15 400 90 80 AISC prediction 300 350 AISC prediction 75 300 60 250 60 Test 3-M20-3C-RL Test 4-M20-1C-RL 250 200 200 45 40 (22.61 mm, 96.39 kN) 150 Slip 150 30 Beam yielding (20.07 mm, 96.39 kN) 100 100 Concrete crushing at east side Beam yielding 20 First bang Concrete crushing at west side 15 50 50 Concrete crushing at west side Concrete crushing at east side 0 0 0 0 0 50 100 150 200 250 300 350 400 450 0 50 100 150 200 250 300 350 Deflection (mm) Deflection (mm) Introduction DfD Floor System Pushout Tests Beam Tests Design Conclusions

  14. Beam Test Results Test Results Stiffness (kN/mm) Moment (kN-m) Maximum Slip (mm) Specimen # Test AISC Test/AISC Test AISC Test/AISC West Side East Side 1-M24-2C-RH 9.24 8.67 1.07 777 767 1.01 5.94 6.43 2-M24-1C-RL 7.76 6.81 1.14 634 632 1.00 8.18 6.45 3-M20-3C-RL 6.46 5.99 1.08 494 510 0.97 0.46 0.23 4-M20-1C-RL 6.08 4.43 1.37 476 400 1.19 8.79 8.08 Applied load versus slip Slip (in.) 0 0.1 0.2 0.3 0.4 140 600 T1W 120 500 T1E T2W 100 T2E 400 T3W 80 Test 1 Localized concrete crushing T3E 300 Test 2 T4W 60 Test 3 T4E 200 40 Test 4 100 20 0 0 0 2 4 6 8 10 Slip (mm) • Large initial stiffness demonstrated by the load-slip curves • Small slip at full service loading (dashed lines) Deconstructed steel beam Introduction DfD Floor System Pushout Tests Beam Tests Design Conclusions

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend