11/3/2017 1
Procurement Con Conference 2017
November 29, 2017
DES ESIGN & CONSTRUCTION SER ERVICES
November 29, 2017
DES ESIGN & CONSTRUCTION SER ERVICES November 29, 2017 1 - - PDF document
11/3/2017 Procurement Con Conference 2017 November 29, 2017 NCDOA - State Construction Office DES ESIGN & CONSTRUCTION SER ERVICES November 29, 2017 1 11/3/2017 Who is s SCO? Agency within the Department of Administration
11/3/2017 1
November 29, 2017
November 29, 2017
11/3/2017 2
11/3/2017 3
(3)Architecture and Engineering
for the construction or renovation of:
lands, except those buildings over which a local building code inspection department has and exercises jurisdiction; and *except does not apply to UNC projects < $2,000,000
estimated expenditure of construction or repair work for which public bidding is required under G.S. 143-129 prior to the awarding of a contract for such work; and to examine and approve all changes in those plans and specifications made after the contract for such work has been awarded. (>$500,000)
11/3/2017 4
b. To assist, as necessary, all agencies in the preparation
renovation of all State buildings
G.S. 143-6 is feasible. For purposes of this sub- division, “feasible” means that the proposed project is sufficiently defined in overall scope; building program; site development; detailed design, construction, and equipment budgets; and comprehensive project scheduling so as to reasonably ensure that it may be completed with the amount of funds requested. At the discretion of the General Assembly, advanced planning funds may be appropriated in support of this
requests for appropriations of less than one hundred thousand dollars ($100,000).
11/3/2017 5
Environmental Quality, Health & Human Services, Justice, Public Instruction, Public Safety, Transportation
CH, UNCC, UNCG, UNCP, UNCW, NCSA, WCU, WSSU, NCSSM
11/3/2017 6
11/3/2017 7
13
INITIAL PROJECT CONCEPT
Needs FURTHER PROJECT DEVELOPMENT
for Large or Complex Projects COST CERTIFICATION PROCESS
Submits Cost Estimate Form OC-25 to State Construction Office
Reviews and Approves OC-25 CAPITAL BUDGET REQUEST PROCESS
Budget Request
Approval
OSBM Notifies Agency of Project Authorizations
14
11/3/2017 8
DESIGN PHASE
Interviews and Recommendations (SCO & Owner)
(SCO)
(SCO, Owner, Other Regulatory Agencies) BIDDING PHASE
Letter (SCO)
Contract Documents (SCO, OSBM, AG’s Office) CLOSE-OUT PHASE
Inspection and Provide Final Acceptance
Close-Out Documents
Claims, if any CONSTRUCTION PHASE
Progress
Work
Avoid Formal Claims
contract documents
15 16
11/3/2017 9
preparation of a Facility Condition Assessment Report with prioritized recommendations and estimated costs for the correction of deficiencies.
smallest building is the Sentry Post at Tryon Palace at 9 sf. The largest is at the Global Transpark listed at 600,000 sf. The inventory of facilities comprises 118,145,712 total sf. The approximate insurable value, as listed by the State Property Office, is $25.6 billion dollars.
constitutes a total of 4,336 buildings out of the total 12,000 state facilities. This represents 36% of the facilities that the state owns. However, the square footage of the buildings assessed totals approximately 111,436,870 sf which represents 94 % of the total gross sf and 95% of the total insurable value of all state-owned facilities.
17
amendment, Commissioning, Special inspections…
18
11/3/2017 10
&129, etc.
Mechanical, ADA, Energy
Institutional, etc.)
Concrete, Wood
standards
11/3/2017 11
check and triple check
construction and post construction
Inspection
because many code “violations” are resolved during the Design Review
to bidding
confirm adequate funding is in place, including construction contingency funds
contracts for accuracy and completeness, prior to releasing executed contracts
22
11/3/2017 12
milestones
parties, contractors, owner, designer and SCO monitor
23
DESIGNER
B I D S
CONTRACTOR
DESIGNER
CHANGE = $ ERROR = $ OMISSION= $ ADDITION = $ CHANGE = $
AGENCIES
Compliance with: Codes Statutes Regulations Procedures Contract Program Budget Codes Errors Omissions Guidelines Consistency Standards
11/3/2017 13
Penetrations, Fire Rated Shafts, Fire Alarm System, and Emergency Generator
11/3/2017 14
11/3/2017 15
publicly has to advertise or not
an estimated expenditure of public money >= $500,000
Formal
general circulation in NC
and opening of bids
5% bid security (cash, cashier’s check, certified check, bid bond)
11/3/2017 16
after 1st advertisement
for a minimum of 7 days
than 3 bids are received
not be opened in a private facility
bid opening
payment bonds – Owner may require
11/3/2017 17
1. Separate Prime Bidding (Multiprime) 2. Single Prime Bidding 3. Dual Bidding 4. Construction Manager at Risk 5. Alternative Contracting Methods
11/3/2017 18
11/3/2017 19
Governmental entity shall establish in writing the criteria used for determining the circumstances under which this is the appropriate method and this criteria shall address, at a minimum, all of the following:
thoroughly define the project requirements
the availability of staff or outside consultants who are experienced
business entities
using design-build in lieu of separate prime, single prime, or CMR
11/3/2017 20
response an explanation of its project team selection, which shall consist of either
professionals on the team
contractor and subcontractor selection based on Art. 8 of GS 143
will move to #2, etc.
11/3/2017 21
11/3/2017 22
thoroughly define the project requirements
including the availability of staff or outside consultants who are experienced
small business entities
CMR
11/3/2017 23
will move to #2, etc.
11/3/2017 24
intended space utilization
design-builder to make proposal
11/3/2017 25
11/3/2017 26
11/3/2017 27
11/3/2017 28
11/3/2017 29