Demand Management Options to Support VRE Grid Integration FP7 - - PowerPoint PPT Presentation

demand management options to support vre grid integration
SMART_READER_LITE
LIVE PREVIEW

Demand Management Options to Support VRE Grid Integration FP7 - - PowerPoint PPT Presentation

Demand Management Options to Support VRE Grid Integration FP7 ADVANCE Workshop Utrecht University 21 January 2015 Michael Hogan Senior Advisor Phone: +32 2-894-9300 rue de la Science 23 The Regulatory Assistance Project web:


slide-1
SLIDE 1

Demand Management Options to Support VRE Grid Integration

FP7 ADVANCE Workshop Utrecht University 21 January 2015 Michael Hogan

Senior Advisor

Phone: +32 2-894-9300 web: www.raponline.org rue de la Science 23 B - 1040 Brussels Belgium The Regulatory Assistance Project

slide-2
SLIDE 2

A more flexible thermal plant mix needed

2

Peak Mid-merit Baseload Peak Mid-merit Baseload

slide-3
SLIDE 3

A more flexible thermal plant mix needed

3

Source: G. Strbac, Imperial College London

slide-4
SLIDE 4

Flexible generation is just one piece of the puzzle

4

Source: IEA Energy Technology Perspectives 2014

slide-5
SLIDE 5

Flexible generation is just one piece of the puzzle

5

Source: IEA Energy Technology Perspectives 2014

slide-6
SLIDE 6

6

40% RES 30% CCS 30% nuclear 80% RES 10% CCS 10% nuclear 0% 20% 60% RES 20% CCS 20% nuclear 0% 20% 0% 20% Transmission & additional generation capacity requirements1 Pathways DSM Transmission Back-up and balancing RES curtailment2 % 3 2 2 1 2 2

Benefit of demand-side flexibility

Source: ECF, Roadmap 2050 (2010)

slide-7
SLIDE 7

Benefit-cost ratios of different flexibility options

7

Source: IEA, The Power of Transformation (2014)

slide-8
SLIDE 8

8 100 300 100 300 10000 100 100 10000 10

CAES Therma l H2O heaters Metal-air Na-S Flow Lead-acid Ni-Cd EV Li-ion Zinc-air H.P. capacitors H.P. flywheels L.D. flywheels L.D. capacitors Distributed/d emand-side Battery Grid-scale Flywheel/cap acitor

Capital cost per unit energy - $/kWh output Capital cost per unit power - $/kW

Cost per Unit of Performance for Various Energy Storage Options

PSH

Sources: Electricity Storage Association, EPRI, Sandia National Laboratories, Ecofys

slide-9
SLIDE 9

9

Gross Load (Peak) (6 weeks) Megawatts Hours

slide-10
SLIDE 10

10

Net Load (Peak) (6 weeks) Megawatts Hours

slide-11
SLIDE 11

11

Gross Load (Off-peak) (6 weeks) Hours Megawatts

slide-12
SLIDE 12

12

Net Load (Off-peak) (6 weeks) Megawatts Hours

slide-13
SLIDE 13

Business case: current example (PJM)

13

Millions of US dollars

slide-14
SLIDE 14

Balancing services markets

14

slide-15
SLIDE 15

Fast response mkt is lucrative…but tiny

15

Source: Electric Power Research Institute, 2010

slide-16
SLIDE 16

Energy markets: typical view

16

baseload mid-merit peaker cap/VoLL

slide-17
SLIDE 17

Suite of actual balancing options

17

Source: Brattle Group report to Texas Public Utilities Commission

slide-18
SLIDE 18

Energy markets: the reality

18

baseload mid-merit cap/VoLL peaker action 4 action 3 action 2 action 1

slide-19
SLIDE 19

VRE integration ≠ capacity

19

slide-20
SLIDE 20

The California ISO “Duck Curve”

20

slide-21
SLIDE 21

(It looks m ore like a m arbled godwit)

21

slide-22
SLIDE 22

Guess What: Ducks Can Fly

22

A duck in the water doesn’t look all that airworthy… …until you see it in flight! Our job is to straighten this duck out.

slide-23
SLIDE 23

Our Starting Point: A California Utility’s Projected “Duck”

23

4,000 MW Peak Demand; 2,000 MW Minimum Demand; Currently 73% Load Factor; Max 1-hour ramp: 400 MW Forecast: 2,500 MW of wind and solar added 2012 – 2020; Predicted 63% Load Factor; Max 1-hour ramp: 550 MW

500 1000 1500 2000 2500 3000 3500 4000 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Total Load Load Net of Wind/Solar

slide-24
SLIDE 24

Ten Strategies To Align Loads to Resources (and Resources to Loads) with Illustrative Values for Each

  • 1. Targeted energy

efficiency

  • 2. Orient solar panels
  • 3. Use CSTP with

heat storage

  • 4. TES: Manage

electric water heat

  • 5. TES: Require large

A/C & refrigeration to incl ice storage

  • 6. Increase operational flexibility
  • f conventional resources
  • 7. Concentrate demand charges

into “ramping” hours

  • 8. Deploy electricity storage in

targeted locations

  • 9. Implement aggressive demand

response programs 10.Use inter-regional exchanges

  • f power

24

Not every strategy will be applicable to every utility.

slide-25
SLIDE 25

Strategy 1: Targeted Energy Efficiency Focus efforts on EE measures with afternoon peak orientation.

25

5% of total usage; 3:1 ratio between on- peak and off- peak savings. Kitchen lighting a good example Air conditioning may be a big

  • pportunity
slide-26
SLIDE 26

Strategy 2: Orient Solar Panels to the West Fixed-axis solar panels produce a more valuable output if oriented to the West.

26

100 MW shift out

  • f AM into PM

hours, out of ~700 total rooftop solar assumed.

slide-27
SLIDE 27

Strategy 3: Use CSP with Storage in Place of Som e Solar PV Solar thermal energy is more expensive, but can be stored for a few hours at low cost.

27

Substitute 100 MW

  • f solar thermal for

100 MW of utility- scale PV, out of 1,500 MW of utility-scale solar total assumed.

slide-28
SLIDE 28

Strategy 4: Therm al energy storage: Control Electric Water Heating Install grid control of electric water heating; Supercharge during low-cost hours.

28

Illustrative utility has 9% electric water heating Gain control over 5% of the electric water heaters 300 MWh of load shifting.

slide-29
SLIDE 29

Strategy 5: Therm al energy storage: Require 2-hour Storage On New AC Require new AC units over 5 tons to include at least 2 hours of storage, under grid control.

29

Move 100 MWh of A/C load out of the 6 – 8 PM period into surplus production periods.

slide-30
SLIDE 30

Strategy 6: Increase operational flexibility of conventional generation Older steam plants with night minimum loads and slow ramping are retrofitted to increase flexibility or are replaced/ repowered with generators with more flexibility. No graphic; assumed to be embedded in the 2020 forecast from the sample utility.

30

slide-31
SLIDE 31

Strategy 7: Concentrate Dem and Charges Concentrate utility demand charges into the “ramping” hours; hourly real-time rates for large-volume customers.

31

5% of load moved out

  • f the

ramping hours with concentrate d demand charges.

slide-32
SLIDE 32

Strategy 8 : Selectively Deploy Electricity Storage

Selectively charge electric vehicle batteries; Add grid battery storage at strategic locations that help avoid T&D upgrade costs.

32

Storage equal to 1%

  • f total load

added. 100 MW max discharge capacity

slide-33
SLIDE 33

Strategy 9: Dem and Response

Contract with customers to curtail/ defer use

  • n as-needed basis when the ramp is steep.

33

3% curtailment

  • f peak

demand on high-ramp days. Currently ~8% at ISO-NE.

slide-34
SLIDE 34

Strategy 10 : Inter-regional Power Exchanges

Geographical diversity of loads, diversity of output from renewables, and diversity of reserves.

34

Exchange 600 MWh per day from early to late evening using the existing inter- regional interties (Arizona, Nevada, Utah, and the Northwest)

This duck is ready to spread its wings and fly.

slide-35
SLIDE 35

Teaching the Duck to Fly

Requesting Permission for Take-Off

slide-36
SLIDE 36

How Did We Do?

Pre-Strategy, without Solar/ Wind: 73% LF Pre-Strategy, with Solar/ Wind: 63% LF Post-Strategy, with Solar/ Wind: 8 3% LF

Maxim um Hourly Ram p: 34 0 MW vs. 550 MW

36

slide-37
SLIDE 37

About RAP

The Regulatory Assistance Project (RAP) is a global, non-profit team of experts that focuses on the long-term economic and environmental sustainability of the power and natural gas sectors. RAP has deep expertise in regulatory and market policies that:

  • Promote economic efficiency
  • Protect the environment
  • Ensure system reliability
  • Allocate system benefits fairly among all consumers

Learn more about RAP at www.raponline.org

Michael Hogan m hogan@raponline.org +1 (6 0 3) 738 8 6 52 (m obile)

slide-38
SLIDE 38

Business case: future example (CAISO)

38